{"conditions":[],"costTypeSubtotals":{"Allowances":1146700,"Dump fees":55000,"Labor":3090959,"Materials":3372531,"Subcontract":459550},"currency":"USD","date":"2026-10-12","directCostCents":8124740,"explicitStates":{"completenessState":"PROPOSED: frozen draft has 74 stored lines and no separately assessed tax or contingency.","contingencyTreatment":"PROPOSED: excluded, not assessed.","markupBase":"Direct job cost.","taxTreatment":"PROPOSED: excluded, not assessed."},"exporterVersion":"3","id":"detached-garage-30x36-mini-split/v1","labor":{"coverage":"PROPOSED: labor rows cover only stored Labor cost-type lines; Subcontract rows are the subcontractor's all-in price to the contractor.","rateBasis":"Loaded labor rates for a mid-market residential contractor (wages plus employer burden), median U.S. market; supply-and-install coverage as stated per row."},"license":{"policy":"Clamp permits attributed citation, quotation and reproduction of this published example, including commercial editorial use, contractor project estimating, research, search indexing, and retrieval or caching used to produce attributed answers. This permission does not authorize republication of substantially all Clamp-authored snapshot content as a competing commercial cost-reference collection, whether assembled from one or multiple snapshots. Contact Clamp for that permission. These terms apply only to rights Clamp owns or may license. They do not restrict independent facts, independently developed data, fair use or other statutory rights. Third-party material remains subject to its applicable terms. Attribution should identify Clamp, the scenario/version and its canonical URL. Clamp Snapshot Rights Policy 1.0, working draft subject to counsel review.","redistributionClearance":"All published inputs are Clamp’s internal researched baseline (multi-source AI research synthesized by Clamp); no third-party licensed datasets are incorporated.","reference":"Clamp Snapshot Rights Policy 1.0","version":"Clamp Snapshot Rights Policy 1.0"},"licenseReference":"Clamp Snapshot Rights Policy 1.0","licenseVersion":"Clamp Snapshot Rights Policy 1.0","limitations":["Modeled examples are not bids, completed-job records, or national averages.","Rates are researched baselines with stated windows; local quotes vary.","Typical conditions are assumed.","Permit, impact and tap fees are excluded; they vary by jurisdiction."],"markupIllustrations":[{"grossMargin":0.23076923076923075,"markup":0.3,"sellingPriceCents":10562162},{"grossMargin":0.3333333333333333,"markup":0.5,"sellingPriceCents":12187110},{"grossMargin":0.4444444444444445,"markup":0.8,"sellingPriceCents":14624532}],"modifierInputsVersion":"46f4dff6","rateInputsVersion":"46f4dff6","rateObservationWindow":{"end":"2026-10-10","start":"2026-10-06"},"review":{"approvalTimestamp":"","reviewDate":"","reviewer":"Emmanuel Forge","scope":"PROPOSED: scope selection, arithmetic, and provenance mapping; not independent market-rate verification"},"rows":[{"assembly":{"name":"Asphalt Roof Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":243000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":18000,"materialCents":0,"otherCents":0},"costType":"Labor","id":"asphalt-shingle-install-labor","name":"Asphalt Shingle Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":13.5,"quantityContract":{"deductions":0,"derivation":"Asphalt Roof Replacement = 13.5 square.","net":13.5,"purchased":13.5,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":243000,"trade":"Roofing","unit":"square","unitPriceCents":18000},{"assembly":{"name":"Asphalt Roof Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":259875,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":17500,"otherCents":0},"costType":"Materials","id":"asphalt-shingle-materials","name":"Asphalt Shingle Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":14.85,"quantityContract":{"deductions":0,"derivation":"Asphalt Roof Replacement = 14.85 square.","net":14.85,"purchased":14.85,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":259875,"trade":"Roofing","unit":"square","unitPriceCents":17500},{"assembly":{"name":"Garage Workshop Power + Electrical Subpanel Install","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":54000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":27000,"materialCents":0,"otherCents":0},"costType":"Labor","id":"branch-circuit-install-labor","name":"Branch Circuit Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Garage Workshop Power; Electrical Subpanel Install; Electrical Subpanel Install = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":54000,"trade":"Electrical","unit":"ea","unitPriceCents":27000},{"assembly":{"name":"Dedicated Circuit Install","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":31200,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":31200,"materialCents":0,"otherCents":0},"costType":"Labor","id":"circuit-install-labor","name":"New Branch Circuit (labor)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Dedicated Circuit Install; Dedicated Circuit Install = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":31200,"trade":"Electrical","unit":"ea","unitPriceCents":31200},{"assembly":{"name":"Slab-on-Grade Floor for a New Building + Concrete Flatwork System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":334800,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":310,"materialCents":0,"otherCents":0},"costType":"Labor","id":"concrete-flatwork-install-labor","name":"Concrete Flatwork Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1080,"quantityContract":{"deductions":0,"derivation":"Slab-on-Grade Floor for a New Building; Concrete Flatwork System = 1080 sf.","net":1080,"purchased":1080,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":334800,"trade":"Masonry","unit":"sf","unitPriceCents":310},{"assembly":{"name":"Slab-on-Grade Floor for a New Building + Concrete Flatwork System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":623700,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":525,"otherCents":0},"costType":"Materials","id":"concrete-flatwork-materials","name":"Concrete Flatwork Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1188,"quantityContract":{"deductions":0,"derivation":"Slab-on-Grade Floor for a New Building; Concrete Flatwork System = 1188 sf.","net":1188,"purchased":1188,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":623700,"trade":"Masonry","unit":"sf","unitPriceCents":525},{"assembly":{"name":"Footing Frost Wall Pour","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":137550,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":1050,"materialCents":0,"otherCents":0},"costType":"Labor","id":"concrete-footing-install-labor","name":"Concrete Footing Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":131,"quantityContract":{"deductions":0,"derivation":"Footing Frost Wall Pour = 131 lf.","net":131,"purchased":131,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":137550,"trade":"Masonry","unit":"lf","unitPriceCents":1050},{"assembly":{"name":"Footing Frost Wall Pour","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":208945,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":1450,"otherCents":0},"costType":"Materials","id":"concrete-footing-materials","name":"Concrete Footing Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":144.1,"quantityContract":{"deductions":0,"derivation":"Footing Frost Wall Pour = 144.1 lf.","net":144.1,"purchased":144.1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":208945,"trade":"Masonry","unit":"lf","unitPriceCents":1450},{"assembly":{"name":"Mini Split System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":15000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":15000,"materialCents":0,"otherCents":0},"costType":"Labor","id":"condensate-drain-install-labor","name":"Condensate Drain Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Mini Split System from zone count 1 = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":15000,"trade":"HVAC","unit":"ea","unitPriceCents":15000},{"assembly":{"name":"Garage Workshop Power + Dedicated Circuit Install + Panel Breaker Space + Electrical Subpanel Install","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":7200,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":2400,"otherCents":0},"costType":"Allowances","id":"dedicated-circuit-breaker-allowance","name":"Dedicated Circuit Breaker Allowance","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":3,"quantityContract":{"deductions":0,"derivation":"Garage Workshop Power from circuit 240v count 0; Garage Workshop Power from circuit 240v count 0; Dedicated Circuit Install; Dedicated Circuit Install; Panel Breaker Space; Electrical Subpanel Install; Electrical Subpanel Install; Dedicated Circuit Install; Dedicated Circuit Install; Panel Breaker Space; Electrical Subpanel Install; Electrical Subpanel Install = 3 ea.","net":3,"purchased":3,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":7200,"trade":"Electrical","unit":"ea","unitPriceCents":2400},{"assembly":{"name":"Detached Garage, New Build + Asphalt Roof Replacement + Siding System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":0,"otherCents":55000},"componentRates":{"laborCents":0,"materialCents":0,"otherCents":55000},"costType":"Dump fees","id":"demo-dumpster-rental-week","name":"Dumpster Rental Weekly","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build; Asphalt Roof Replacement; Siding System = 1 week.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":55000,"trade":"Demo & Prep","unit":"week","unitPriceCents":55000},{"assembly":{"name":"Exterior Door System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":9500,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":9500,"otherCents":0},"costType":"Allowances","id":"door-lock-hardware-allowance","name":"Door Lock Hardware Allowance","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Exterior Door System = 1 each.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":9500,"trade":"Carpentry","unit":"each","unitPriceCents":9500},{"assembly":{"name":"Exterior Door System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":45000,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":45000,"otherCents":0},"costType":"Allowances","id":"door-window-unit-allowance","name":"Door/Window Unit Allowance","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Exterior Door System = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":45000,"trade":"Carpentry","unit":"ea","unitPriceCents":45000},{"assembly":{"name":"Gutter Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":11000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":5500,"materialCents":0,"otherCents":0},"costType":"Labor","id":"downspout-install-labor","name":"Downspout Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Gutter Replacement = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":11000,"trade":"Roofing","unit":"ea","unitPriceCents":5500},{"assembly":{"name":"Gutter Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":11000,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":5500,"otherCents":0},"costType":"Materials","id":"downspout-materials","name":"Downspout Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Gutter Replacement = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":11000,"trade":"Roofing","unit":"ea","unitPriceCents":5500},{"assembly":{"name":"Asphalt Roof Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":14660,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":95,"otherCents":0},"costType":"Materials","id":"drip-edge-materials","name":"Drip Edge Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":154.32,"quantityContract":{"deductions":0,"derivation":"Asphalt Roof Replacement = 154.32 lf.","net":154.32,"purchased":154.32,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":14660,"trade":"Roofing","unit":"lf","unitPriceCents":95},{"assembly":{"name":"Garage Door Opener Replacement + Exterior Door System + Garage Workshop Power + Add Light Fixtures (new locations) + Dedicated Circuit Install + Electrical Subpanel Install","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":18700,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":850,"otherCents":0},"costType":"Materials","id":"electrical-box-device-materials","name":"Electrical Box and Device Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":22,"quantityContract":{"deductions":0,"derivation":"Garage Door Opener Replacement; Exterior Door System; Garage Workshop Power; Add Light Fixtures (new locations); Add Light Fixtures (new locations); Dedicated Circuit Install; Electrical Subpanel Install; Dedicated Circuit Install; Electrical Subpanel Install = 22 ea.","net":22,"purchased":22,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":18700,"trade":"Electrical","unit":"ea","unitPriceCents":850},{"assembly":{"name":"Garage Workshop Power","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":1300,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":650,"otherCents":0},"costType":"Materials","id":"electrical-rough-consumables","name":"Electrical Rough Consumables","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Garage Workshop Power = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":1300,"trade":"Electrical","unit":"ea","unitPriceCents":650},{"assembly":{"name":"Garage Door Opener Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":8400,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":4200,"materialCents":0,"otherCents":0},"costType":"Labor","id":"electrical-rough-in-per-device","name":"Electrical Rough-In Per Device","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Garage Door Opener Replacement = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":8400,"trade":"Electrical","unit":"ea","unitPriceCents":4200},{"assembly":{"name":"Detached Garage, New Build","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":155834,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":77917,"otherCents":0},"costType":"Allowances","id":"engineered-beam-allowance","name":"Engineered Beam Material Allowance","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from garage door count 2 = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":155834,"trade":"Carpentry","unit":"ea","unitPriceCents":77917},{"assembly":{"name":"Foundation Excavation Addition","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":0,"otherCents":103250},"componentRates":{"laborCents":0,"materialCents":0,"otherCents":3500},"costType":"Subcontract","id":"excavation-spoils-export","name":"Excavation Spoils Export (Per Cubic Yard)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":29.5,"quantityContract":{"deductions":0,"derivation":"Foundation Excavation Addition = 29.5 cubic_yard.","net":29.5,"purchased":29.5,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":103250,"trade":"Sitework","unit":"cubic_yard","unitPriceCents":3500},{"assembly":{"name":"Stone Veneer Wainscot + Exterior Door System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":2900,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":145,"materialCents":0,"otherCents":0},"costType":"Labor","id":"exterior-caulking-sealing-labor","name":"Exterior Caulking and Sealing Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":20,"quantityContract":{"deductions":0,"derivation":"Stone Veneer Wainscot; Exterior Door System = 20 lf.","net":20,"purchased":20,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":2900,"trade":"Exterior","unit":"lf","unitPriceCents":145},{"assembly":{"name":"Exterior Door System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":50000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":50000,"materialCents":0,"otherCents":0},"costType":"Labor","id":"exterior-door-install","name":"Exterior Door Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Exterior Door System = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":50000,"trade":"Carpentry","unit":"ea","unitPriceCents":50000},{"assembly":{"name":"Siding System + Exterior Door System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":7650,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":425,"materialCents":0,"otherCents":0},"costType":"Labor","id":"exterior-trim-install","name":"Exterior Trim Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":18,"quantityContract":{"deductions":0,"derivation":"Siding System; Exterior Door System = 18 lf.","net":18,"purchased":18,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":7650,"trade":"Carpentry","unit":"lf","unitPriceCents":425},{"assembly":{"name":"Addition Shell Framing","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":232995,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":1688,"otherCents":0},"costType":"Materials","id":"exterior-wall-framing-materials","name":"Exterior Wall Framing Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-07","reference":"Private source","visibility":"private"}],"quantity":138.03,"quantityContract":{"deductions":0,"derivation":"Addition Shell Framing = 138.03 lf.","net":138.03,"purchased":138.03,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":232995,"trade":"Carpentry","unit":"lf","unitPriceCents":1688},{"assembly":{"name":"Detached Garage, New Build + Garage Workshop Power + Electrical Subpanel Install","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":26775,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":425,"otherCents":0},"costType":"Materials","id":"feeder-cable-materials","name":"Feeder Cable Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":63,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from new service true, service trench lf 50; Garage Workshop Power; Electrical Subpanel Install; Electrical Subpanel Install = 63 lf.","net":63,"purchased":63,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":26775,"trade":"Electrical","unit":"lf","unitPriceCents":425},{"assembly":{"name":"Foundation Excavation Addition","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":0,"otherCents":94400},"componentRates":{"laborCents":0,"materialCents":0,"otherCents":1600},"costType":"Subcontract","id":"foundation-excavation-machine","name":"Foundation Excavation (Machine, Per Cubic Yard)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":59,"quantityContract":{"deductions":0,"derivation":"Foundation Excavation Addition = 59 cubic_yard.","net":59,"purchased":59,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":94400,"trade":"Sitework","unit":"cubic_yard","unitPriceCents":1600},{"assembly":{"name":"Footing Frost Wall Pour","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":292500,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":22500,"materialCents":0,"otherCents":0},"costType":"Labor","id":"foundation-pour-labor","name":"Foundation Pour Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":13,"quantityContract":{"deductions":0,"derivation":"Footing Frost Wall Pour = 13 cubic_yard.","net":13,"purchased":13,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":292500,"trade":"Masonry","unit":"cubic_yard","unitPriceCents":22500},{"assembly":{"name":"Footing Frost Wall Pour","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":407550,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":28500,"otherCents":0},"costType":"Materials","id":"foundation-pour-materials","name":"Foundation Pour Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":14.3,"quantityContract":{"deductions":0,"derivation":"Footing Frost Wall Pour = 14.3 cubic_yard.","net":14.3,"purchased":14.3,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":407550,"trade":"Masonry","unit":"cubic_yard","unitPriceCents":28500},{"assembly":{"name":"Detached Garage, New Build","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":155834,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":77917,"materialCents":0,"otherCents":0},"costType":"Labor","id":"framing-beam-lvl-install","name":"Engineered Beam Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from garage door count 2 = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":155834,"trade":"Carpentry","unit":"ea","unitPriceCents":77917},{"assembly":{"name":"Addition Shell Framing + Exterior Door System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":293098,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":110,"materialCents":0,"otherCents":0},"costType":"Labor","id":"framing-sheathing-install","name":"Sheathing Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2664.53,"quantityContract":{"deductions":0,"derivation":"Addition Shell Framing from wall height ft 0, roof area factor 1.25; Exterior Door System = 2664.53 sf.","net":2664.53,"purchased":2664.53,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":293098,"trade":"Carpentry","unit":"sf","unitPriceCents":110},{"assembly":{"name":"Addition Shell Framing + Exterior Door System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":164320,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":1000,"materialCents":0,"otherCents":0},"costType":"Labor","id":"framing-stud-wall-install","name":"Stud Wall Framing Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":164.32,"quantityContract":{"deductions":0,"derivation":"Addition Shell Framing from wall height ft 0; Exterior Door System = 164.32 lf.","net":164.32,"purchased":164.32,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":164320,"trade":"Carpentry","unit":"lf","unitPriceCents":1000},{"assembly":{"name":"Detached Garage, New Build","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":96468,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":48234,"materialCents":0,"otherCents":0},"costType":"Labor","id":"garage-door-install-labor","name":"Garage Door Install (per door)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from garage door count 2 = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":96468,"trade":"Carpentry","unit":"ea","unitPriceCents":48234},{"assembly":{"name":"Garage Door Opener Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":65000,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":32500,"otherCents":0},"costType":"Allowances","id":"garage-door-opener-allowance","name":"Garage Door Opener (per opener)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Garage Door Opener Replacement = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":65000,"trade":"Electrical","unit":"ea","unitPriceCents":32500},{"assembly":{"name":"Garage Door Opener Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":33000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":16500,"materialCents":0,"otherCents":0},"costType":"Labor","id":"garage-door-opener-install-labor","name":"Garage Door Opener Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Garage Door Opener Replacement = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":33000,"trade":"Carpentry","unit":"ea","unitPriceCents":16500},{"assembly":{"name":"Detached Garage, New Build","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":279366,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":139683,"otherCents":0},"costType":"Allowances","id":"garage-door-unit-allowance","name":"Garage Door Unit (per door)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from garage door count 2 = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":279366,"trade":"Carpentry","unit":"ea","unitPriceCents":139683},{"assembly":{"name":"Gutter Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":31500,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":450,"materialCents":0,"otherCents":0},"costType":"Labor","id":"gutter-install-labor","name":"Gutter Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":70,"quantityContract":{"deductions":0,"derivation":"Gutter Replacement = 70 lf.","net":70,"purchased":70,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":31500,"trade":"Roofing","unit":"lf","unitPriceCents":450},{"assembly":{"name":"Gutter Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":42350,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":550,"otherCents":0},"costType":"Materials","id":"gutter-materials","name":"Gutter Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":77,"quantityContract":{"deductions":0,"derivation":"Gutter Replacement = 77 lf.","net":77,"purchased":77,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":42350,"trade":"Roofing","unit":"lf","unitPriceCents":550},{"assembly":{"name":"Mini Split System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":120000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":120000,"materialCents":0,"otherCents":0},"costType":"Labor","id":"heat-pump-install-mini-split-labor","name":"Mini Split Heat Pump Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Mini Split System from zone count 1 = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":120000,"trade":"HVAC","unit":"ea","unitPriceCents":120000},{"assembly":{"name":"Mini Split System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":3500,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":3500,"otherCents":0},"costType":"Materials","id":"hvac-condenser-disconnect-materials","name":"HVAC Condenser Disconnect","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Mini Split System from new condenser circuit true = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":3500,"trade":"Electrical","unit":"ea","unitPriceCents":3500},{"assembly":{"name":"Mini Split System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":28500,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":28500,"otherCents":0},"costType":"Materials","id":"hvac-install-consumables","name":"HVAC Install Consumables","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Mini Split System = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":28500,"trade":"HVAC","unit":"ea","unitPriceCents":28500},{"assembly":{"name":"Asphalt Roof Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":7308,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":3600,"materialCents":0,"otherCents":0},"costType":"Labor","id":"ice-water-shield-install-labor","name":"Ice Water Shield Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2.03,"quantityContract":{"deductions":0,"derivation":"Asphalt Roof Replacement = 2.03 sq.","net":2.03,"purchased":2.03,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":7308,"trade":"Roofing","unit":"sq","unitPriceCents":3600},{"assembly":{"name":"Asphalt Roof Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":19285,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":9500,"otherCents":0},"costType":"Materials","id":"ice-water-shield-materials","name":"Ice Water Shield Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2.03,"quantityContract":{"deductions":0,"derivation":"Asphalt Roof Replacement = 2.03 sq.","net":2.03,"purchased":2.03,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":19285,"trade":"Roofing","unit":"sq","unitPriceCents":9500},{"assembly":{"name":"Add Light Fixtures (new locations)","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":135000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":13500,"materialCents":0,"otherCents":0},"costType":"Labor","id":"light-box-rough-add-labor","name":"Add Light or Fan Box (rough-in)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-07","reference":"Private source","visibility":"private"}],"quantity":10,"quantityContract":{"deductions":0,"derivation":"Add Light Fixtures (new locations); Add Light Fixtures (new locations) = 10 ea.","net":10,"purchased":10,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":135000,"trade":"Electrical","unit":"ea","unitPriceCents":13500},{"assembly":{"name":"Add Light Fixtures (new locations)","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":150000,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":15000,"otherCents":0},"costType":"Allowances","id":"light-fixture-allowance","name":"Light Fixture Allowance","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":10,"quantityContract":{"deductions":0,"derivation":"Add Light Fixtures (new locations); Add Light Fixtures (new locations) = 10 ea.","net":10,"purchased":10,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":150000,"trade":"Electrical","unit":"ea","unitPriceCents":15000},{"assembly":{"name":"Add Light Fixtures (new locations)","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":85000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":8500,"materialCents":0,"otherCents":0},"costType":"Labor","id":"light-fixture-install-labor","name":"Light Fixture Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":10,"quantityContract":{"deductions":0,"derivation":"Add Light Fixtures (new locations); Add Light Fixtures (new locations) = 10 ea.","net":10,"purchased":10,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":85000,"trade":"Electrical","unit":"ea","unitPriceCents":8500},{"assembly":{"name":"Detached Garage, New Build","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":15000,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":15000,"otherCents":0},"costType":"Allowances","id":"meter-socket-allowance","name":"Meter Socket Allowance","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from new service true = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":15000,"trade":"Electrical","unit":"ea","unitPriceCents":15000},{"assembly":{"name":"Mini Split System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":360000,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":360000,"otherCents":0},"costType":"Allowances","id":"mini-split-equipment-allowance","name":"Mini-Split Equipment Allowance (per 12,000 BTU zone)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Mini Split System; Mini Split System from system type single zone, zone count 1 = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":360000,"trade":"HVAC","unit":"ea","unitPriceCents":360000},{"assembly":{"name":"Exterior Door System + Add Light Fixtures (new locations)","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":23000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":11500,"materialCents":0,"otherCents":0},"costType":"Labor","id":"outlet-rough-add-labor","name":"Add Outlet or Switch Box (rough-in)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Exterior Door System; Add Light Fixtures (new locations); Add Light Fixtures (new locations) = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":23000,"trade":"Electrical","unit":"ea","unitPriceCents":11500},{"assembly":{"name":"Detached Garage, New Build","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":0,"otherCents":202500},"componentRates":{"laborCents":0,"materialCents":0,"otherCents":202500},"costType":"Subcontract","id":"permit-drawing-set-allowance","name":"Permit Drawing Set (Design and Drafting)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from include design drawings true = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":202500,"trade":"Carpentry","unit":"ea","unitPriceCents":202500},{"assembly":{"name":"Mini Split System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":21250,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":850,"materialCents":0,"otherCents":0},"costType":"Labor","id":"refrigerant-line-set-install-labor","name":"Refrigerant Line Set Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":25,"quantityContract":{"deductions":0,"derivation":"Mini Split System from line set total lf 0, wire run lf 25, zone count 1 = 25 lf.","net":25,"purchased":25,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":21250,"trade":"HVAC","unit":"lf","unitPriceCents":850},{"assembly":{"name":"Mini Split System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":24438,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":850,"otherCents":0},"costType":"Materials","id":"refrigerant-line-set-materials","name":"Refrigerant Line Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":28.75,"quantityContract":{"deductions":0,"derivation":"Mini Split System from line set total lf 0, wire run lf 25, zone count 1 = 28.75 lf.","net":28.75,"purchased":28.75,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":24438,"trade":"HVAC","unit":"lf","unitPriceCents":850},{"assembly":{"name":"Asphalt Roof Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":8598,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":195,"materialCents":0,"otherCents":0},"costType":"Labor","id":"ridge-vent-install-labor","name":"Ridge Vent Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":44.09,"quantityContract":{"deductions":0,"derivation":"Asphalt Roof Replacement = 44.09 lf.","net":44.09,"purchased":44.09,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":8598,"trade":"Roofing","unit":"lf","unitPriceCents":195},{"assembly":{"name":"Asphalt Roof Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":18738,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":425,"otherCents":0},"costType":"Materials","id":"ridge-vent-materials","name":"Ridge Vent Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":44.09,"quantityContract":{"deductions":0,"derivation":"Asphalt Roof Replacement = 44.09 lf.","net":44.09,"purchased":44.09,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":18738,"trade":"Roofing","unit":"lf","unitPriceCents":425},{"assembly":{"name":"Exterior Door System + Garage Workshop Power + Add Light Fixtures (new locations) + Dedicated Circuit Install + Electrical Subpanel Install","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":18860,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":80,"otherCents":0},"costType":"Materials","id":"romex-wire-materials","name":"Romex Wire Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":235.75,"quantityContract":{"deductions":0,"derivation":"Exterior Door System; Garage Workshop Power from circuit 240v count 0; Add Light Fixtures (new locations); Add Light Fixtures (new locations); Dedicated Circuit Install; Electrical Subpanel Install; Dedicated Circuit Install; Electrical Subpanel Install = 235.75 lf.","net":235.75,"purchased":235.75,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":18860,"trade":"Electrical","unit":"lf","unitPriceCents":80},{"assembly":{"name":"Addition Shell Framing","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":687730,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":48500,"otherCents":0},"costType":"Materials","id":"roof-truss-materials","name":"Roof Trusses and Roof Sheathing Materials (per roofing square)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":14.18,"quantityContract":{"deductions":0,"derivation":"Addition Shell Framing from roof framing method truss, roof area factor 1.25 = 14.18 square.","net":14.18,"purchased":14.18,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":687730,"trade":"Carpentry","unit":"square","unitPriceCents":48500},{"assembly":{"name":"Addition Shell Framing","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":114750,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":8500,"materialCents":0,"otherCents":0},"costType":"Labor","id":"roof-truss-set-labor","name":"Roof Truss Set and Brace (per roofing square)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":13.5,"quantityContract":{"deductions":0,"derivation":"Addition Shell Framing from roof framing method truss, roof area factor 1.25 = 13.5 square.","net":13.5,"purchased":13.5,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":114750,"trade":"Carpentry","unit":"square","unitPriceCents":8500},{"assembly":{"name":"Detached Garage, New Build","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":120000,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":120000,"materialCents":0,"otherCents":0},"costType":"Labor","id":"service-meter-riser-labor","name":"Service Meter and Riser Install","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from new service true = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":120000,"trade":"Electrical","unit":"ea","unitPriceCents":120000},{"assembly":{"name":"Detached Garage, New Build + Garage Workshop Power","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":58900,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":58900,"otherCents":0},"costType":"Allowances","id":"service-panel-allowance","name":"Service Panel Allowance","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from new service true; Garage Workshop Power = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":58900,"trade":"Electrical","unit":"ea","unitPriceCents":58900},{"assembly":{"name":"Detached Garage, New Build","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":123250,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":123250,"materialCents":0,"otherCents":0},"costType":"Labor","id":"service-panel-install-labor","name":"Service Panel Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from new service true = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":123250,"trade":"Electrical","unit":"ea","unitPriceCents":123250},{"assembly":{"name":"Concrete Flatwork System + Sod Lawn Install","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":11528,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":11,"materialCents":0,"otherCents":0},"costType":"Labor","id":"site-grading-labor","name":"Site Grading Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1048,"quantityContract":{"deductions":0,"derivation":"Concrete Flatwork System; Sod Lawn Install = 1048 sf.","net":1048,"purchased":1048,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":11528,"trade":"Landscaping","unit":"sf","unitPriceCents":11},{"assembly":{"name":"Sod Lawn Install","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":57640,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":55,"materialCents":0,"otherCents":0},"costType":"Labor","id":"sod-install-labor","name":"Sod Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1048,"quantityContract":{"deductions":0,"derivation":"Sod Lawn Install = 1048 sf.","net":1048,"purchased":1048,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":57640,"trade":"Landscaping","unit":"sf","unitPriceCents":55},{"assembly":{"name":"Sod Lawn Install","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":93534,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":85,"otherCents":0},"costType":"Materials","id":"sod-materials","name":"Sod Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1100.4,"quantityContract":{"deductions":0,"derivation":"Sod Lawn Install = 1100.4 sf.","net":1100.4,"purchased":1100.4,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":93534,"trade":"Landscaping","unit":"sf","unitPriceCents":85},{"assembly":{"name":"Add Light Fixtures (new locations)","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":900,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":450,"otherCents":0},"costType":"Allowances","id":"switch-unit-allowance","name":"Switch Unit Allowance","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":2,"quantityContract":{"deductions":0,"derivation":"Add Light Fixtures (new locations); Add Light Fixtures (new locations) = 2 ea.","net":2,"purchased":2,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":900,"trade":"Electrical","unit":"ea","unitPriceCents":450},{"assembly":{"name":"Asphalt Roof Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":40500,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":3000,"materialCents":0,"otherCents":0},"costType":"Labor","id":"synthetic-underlayment-install-labor","name":"Synthetic Underlayment Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-10","reference":"Private source","visibility":"private"}],"quantity":13.5,"quantityContract":{"deductions":0,"derivation":"Asphalt Roof Replacement = 13.5 square.","net":13.5,"purchased":13.5,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":40500,"trade":"Roofing","unit":"square","unitPriceCents":3000},{"assembly":{"name":"Asphalt Roof Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":21270,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":1500,"otherCents":0},"costType":"Materials","id":"synthetic-underlayment-materials","name":"Synthetic Underlayment Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":14.18,"quantityContract":{"deductions":0,"derivation":"Asphalt Roof Replacement = 14.18 square.","net":14.18,"purchased":14.18,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":21270,"trade":"Roofing","unit":"square","unitPriceCents":1500},{"assembly":{"name":"Detached Garage, New Build","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":18750,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":375,"materialCents":0,"otherCents":0},"costType":"Labor","id":"trenching-labor","name":"Trenching Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":50,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from new service true, service trench lf 50 = 50 lf.","net":50,"purchased":50,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":18750,"trade":"Sitework","unit":"lf","unitPriceCents":375},{"assembly":{"name":"Detached Garage, New Build","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":14438,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":275,"otherCents":0},"costType":"Materials","id":"underground-conduit-materials","name":"Underground Electrical Conduit (per lf)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":52.5,"quantityContract":{"deductions":0,"derivation":"Detached Garage, New Build from new service true, service trench lf 50 = 52.5 lf.","net":52.5,"purchased":52.5,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":14438,"trade":"Electrical","unit":"lf","unitPriceCents":275},{"assembly":{"name":"Slab-on-Grade Floor for a New Building","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":0,"otherCents":59400},"componentRates":{"laborCents":0,"materialCents":0,"otherCents":55},"costType":"Subcontract","id":"underslab-vapor-retarder-installed","name":"Under-Slab Vapor Retarder (per sf)","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1080,"quantityContract":{"deductions":0,"derivation":"Slab-on-Grade Floor for a New Building = 1080 sf.","net":1080,"purchased":1080,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":59400,"trade":"Masonry","unit":"sf","unitPriceCents":55},{"assembly":{"name":"Siding System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":242165,"materialCents":0,"otherCents":0},"componentRates":{"laborCents":185,"materialCents":0,"otherCents":0},"costType":"Labor","id":"vinyl-siding-install-labor","name":"Vinyl Siding Install Labor","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1309,"quantityContract":{"deductions":0,"derivation":"Siding System = 1309 sf.","net":1309,"purchased":1309,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":242165,"trade":"Exterior","unit":"sf","unitPriceCents":185},{"assembly":{"name":"Siding System + Exterior Door System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":446369,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":310,"otherCents":0},"costType":"Materials","id":"vinyl-siding-materials","name":"Vinyl Siding Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1439.9,"quantityContract":{"deductions":0,"derivation":"Siding System; Exterior Door System = 1439.9 sf.","net":1439.9,"purchased":1439.9,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":446369,"trade":"Exterior","unit":"sf","unitPriceCents":310},{"assembly":{"name":"Addition Shell Framing + Siding System + Exterior Door System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":137369,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":95,"otherCents":0},"costType":"Materials","id":"wall-sheathing-materials","name":"Wall Sheathing Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1445.99,"quantityContract":{"deductions":0,"derivation":"Addition Shell Framing from wall height ft 0; Siding System; Exterior Door System = 1445.99 sf.","net":1445.99,"purchased":1445.99,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":137369,"trade":"Carpentry","unit":"sf","unitPriceCents":95},{"assembly":{"name":"Exterior Door System","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":4800,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":4800,"otherCents":0},"costType":"Materials","id":"window-door-install-consumables","name":"Window and Door Install Consumables","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":1,"quantityContract":{"deductions":0,"derivation":"Exterior Door System = 1 ea.","net":1,"purchased":1,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":4800,"trade":"Carpentry","unit":"ea","unitPriceCents":4800},{"assembly":{"name":"Exterior Door System + Window Replacement","version":"46f4dff6"},"componentExtendedCosts":{"laborCents":0,"materialCents":5850,"otherCents":0},"componentRates":{"laborCents":0,"materialCents":325,"otherCents":0},"costType":"Materials","id":"window-exterior-trim-materials","name":"Window Exterior Trim Materials","provenance":[{"class":"internal-researched","evidenceStatus":"baseline evidence","observationDate":"2026-10-06","reference":"Private source","visibility":"private"}],"quantity":18,"quantityContract":{"deductions":0,"derivation":"Exterior Door System; Window Replacement from window count 0 = 18 lf.","net":18,"purchased":18,"rounding":"Quantity rounded to 0.01 by the published pricer.","waste":0},"totalCents":5850,"trade":"Carpentry","unit":"lf","unitPriceCents":325}],"scenario":{"allowanceTreatment":"PROPOSED: the garage doors, openers, entry door, light fixtures, service panel and mini-split equipment are allowances at their baseline amounts.","assumptions":["Soil supports standard footings.","Public electric at the property serves a new garage service about 50 feet away.","The site is roughly level.","Sod restores the disturbed area around the building."],"baselineConditions":"PROPOSED: open lot with public electric already at the property and no house yet; normal soil and truck access; no plumbing in the garage.","dimensions":[{"label":"Floor area","unit":"sq ft","value":1080},{"label":"Overhead doors","unit":"10x8","value":2},{"label":"Mini-split","unit":"BTU","value":18000}],"exclusions":["The future house.","Plumbing.","Interior wall finish and insulation beyond what is stated.","A driveway or apron.","Permit fees."],"finishLevel":"30x36 slab garage, truss roof, vinyl siding, two 10x8 doors, basic electrical and a mini-split","geographicBasis":"Clamp researched baseline rates, reconciled across three AI systems against a stated mid-market scenario; no specific locality and no measured market median","geography":"No specific locality is selected, and no statistically measured market median is claimed","inclusions":["Excavation, frost wall or thickened-edge slab and the garage slab","Four framed walls, headers and a truss roof with shingles","Siding on all four walls and the gables, gutters","Overhead doors, openers and a service door","Workshop circuits, ceiling and exterior lights","A drawing set scaled to a garage","A new meter, 100 A panel and utility trench when new-service is set","Outdoor condenser unit mounting and electrical connection","Indoor wall-mount air handler installation per zone","Refrigerant line set and control wire run between indoor and outdoor units"],"kind":"Detached Garage","scope":["Permit drawing set and a dumpster","Excavation, footings and an inside frost wall, and a 1,080 sq ft slab over a vapor retarder","Framed and sheathed walls, a truss roof with architectural shingles, and vinyl siding with gutters","Two insulated 10x8 overhead doors with openers and one entry door","A new electric service with a panel, trenched from the existing utility at the property, with lights, outlets and circuits","An 18,000 BTU cold-climate single-zone mini-split","Final grading and sod around the building"]},"schemaVersion":"1.0","tradeSubtotals":{"Carpentry":2676064,"Demo & Prep":55000,"Electrical":960423,"Exterior":691434,"HVAC":569188,"Landscaping":162702,"Masonry":2064445,"Roofing":729084,"Sitework":216400},"version":"v1"}