Project cost · modeled example · 5 builds

3×5 Shower Replacement Cost: Five Builds Compared (2026 Baseline)

The same 60x36 shower torn out and rebuilt five ways, from a multi-piece fiberglass remodel unit to tile on a mud-bed pan, with add-ons and the problems that show up once the old shower is out. Every quantity, rate and formula shown.

Direct answer: Replacing a 3×5 shower (also written 5x3 or 60x36) has a direct job cost of $4,765 for an acrylic base with a surround kit up to $9,037 for tile walls on a mud-bed pan. At illustrative markups of 30% to 100%, that is a selling price of about $6,195 to $9,531 for the first and $11,748 to $18,073 for the second. Direct job cost is labor and materials only, with no contractor overhead or profit, and is not a price: no contractor performs work at job cost. Permit and inspection fees are not included.

Five builds, side by side

Same room, same 60x36 footprint, same demolition. Only the shower changes.

BuildJob costLaborCrew hoursMaterialsIllustrative selling price
A. Multi-piece remodel unit$4,915$2,91839 to 53 h$1,772$6,390 to
$9,831
B. Acrylic base + surround kit$4,765$2,91839 to 53 h$1,622$6,195 to
$9,531
C. Tile walls, acrylic base$6,667$3,75045 to 61 h$2,692$8,667 to
$13,334
D. Tile walls, foam tray pan$8,494$5,01655 to 74 h$3,253$11,042 to
$16,988
E. Tile walls, mud-bed pan$9,037$6,01458 to 78 h$2,798$11,748 to
$18,073

Dump fees and other costs ($225) are the same in every build and included in the job cost. Materials include allowances. Illustrative selling price is the job cost at a 30% to 100% markup; your price depends on your own overhead and profit. Crew hours are a planning range for your own crew and include setup, daily cleanup and material runs; they are never a charge to the customer. Permit and inspection fees are not included; requirements vary by jurisdiction.

Each build in detail

A. Multi-piece remodel unit: $4,915

Old tile shower out, a three- or four-piece fiberglass remodel unit set direct to the studs, new valve and trim. Labor is $2,918 of the $4,915 job cost, or 59.4%. It is about 39 to 53 hours of work for your own crew, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure for your own crew, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Overhead×1.30Established×1.50Full-Service×2.00
Demo & Prep4 to 8 h$451$586$677$902
Plumbing11 to 20 h$1,275$1,657$1,913$2,550
Drywall7 to 14 h$657$854$985$1,314
Tile4 to 10 h$486$632$729$972
Paintingunder 1 h$49$64$73$98
Setup, cleanup and material runs3 to 10 hin the prices
All labor39 to 53 h$2,918$3,793$4,377$5,836

Every line item

Labor $2,918 + materials and allowances $1,772 + dump fees and other $225 = $4,915 direct job cost. Some labor quantities include a difficulty factor (large-format tile, for example, is counted at 1.35 times its area), so they can exceed the tiled area; each row’s derivation is in the downloadable data.

Line items (19)
ItemQtyUnitLaborMaterialLine cost
Demo & Prep
Bathroom Fixture Removal1ea$125$0$125
Haul-Off Per Load1ea$0$0$225
Interior Demolition Labor15sf$26$0$26
Site Protection, One Room (per job)1ea$300$0$300
Plumbing
Multi-Piece Remodel Shower Unit Allowance1ea$0$1,100$1,100
Shower valve trim allowance1ea$0$285$285
Shower/Tub Valve Set1ea$425$0$425
Shower Unit Install Labor1ea$850$0$850
Shower Valve Rough-In Body Allowance1ea$0$200$200
Drywall
Drywall Removal88sf$88$0$88
Drywall Patch Repair4ea$500$0$500
Drywall Skim Coat Materials60sf$0$19$19
Skim Coat Labor60sf$69$0$69
Tile
Tile Floor Removal15sf$68$0$68
Wall Tile Removal88sf$418$0$418
Painting
Interior Paint Apply Labor60sf$36$0$36
Premium Paint Allowance0.38gallon$0$18$18
Paint Prep Labor60sf$13$0$13
Paint Sundries Materials1ls$0$150$150
Direct job cost$2,918$1,772$4,915

B. Acrylic base + surround kit: $4,765

Acrylic base with a three-panel acrylic surround glued to new backer, new valve and trim. Labor is $2,918 of the $4,765 job cost, or 61.2%. It is about 39 to 53 hours of work for your own crew, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure for your own crew, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Overhead×1.30Established×1.50Full-Service×2.00
Demo & Prep4 to 8 h$451$586$677$902
Plumbing11 to 20 h$1,275$1,657$1,913$2,550
Drywall7 to 14 h$657$854$985$1,314
Tile4 to 10 h$486$632$729$972
Paintingunder 1 h$49$64$73$98
Setup, cleanup and material runs3 to 10 hin the prices
All labor39 to 53 h$2,918$3,793$4,377$5,836

Every line item

Labor $2,918 + materials and allowances $1,622 + dump fees and other $225 = $4,765 direct job cost. Some labor quantities include a difficulty factor (large-format tile, for example, is counted at 1.35 times its area), so they can exceed the tiled area; each row’s derivation is in the downloadable data.

Line items (19)
ItemQtyUnitLaborMaterialLine cost
Demo & Prep
Bathroom Fixture Removal1ea$125$0$125
Haul-Off Per Load1ea$0$0$225
Interior Demolition Labor15sf$26$0$26
Site Protection, One Room (per job)1ea$300$0$300
Plumbing
Shower Base and Surround Kit Allowance1ea$0$950$950
Shower valve trim allowance1ea$0$285$285
Shower/Tub Valve Set1ea$425$0$425
Shower Unit Install Labor1ea$850$0$850
Shower Valve Rough-In Body Allowance1ea$0$200$200
Drywall
Drywall Removal88sf$88$0$88
Drywall Patch Repair4ea$500$0$500
Drywall Skim Coat Materials60sf$0$19$19
Skim Coat Labor60sf$69$0$69
Tile
Tile Floor Removal15sf$68$0$68
Wall Tile Removal88sf$418$0$418
Painting
Interior Paint Apply Labor60sf$36$0$36
Premium Paint Allowance0.38gallon$0$18$18
Paint Prep Labor60sf$13$0$13
Paint Sundries Materials1ls$0$150$150
Direct job cost$2,918$1,622$4,765

C. Tile walls, acrylic base: $6,667

Tiled walls to the ceiling over a waterproofed backer, on a factory acrylic base. All wall backer is new, because the old shower comes out to the studs. Labor is $3,750 of the $6,667 job cost, or 56.2%. It is about 45 to 61 hours of work for your own crew, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure for your own crew, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Overhead×1.30Established×1.50Full-Service×2.00
Demo & Prep4 to 8 h$451$586$677$902
Plumbing2 to 5 h$425$553$637$850
Drywall1 to 2 h$88$114$132$176
Tile29 to 43 h$2,786$3,622$4,179$5,572
Setup, cleanup and material runs3 to 11 hin the prices
All labor45 to 61 h$3,750$4,875$5,625$7,500

Every line item

Labor $3,750 + materials and allowances $2,692 + dump fees and other $225 = $6,667 direct job cost. Some labor quantities include a difficulty factor (large-format tile, for example, is counted at 1.35 times its area), so they can exceed the tiled area; each row’s derivation is in the downloadable data.

Line items (21)
ItemQtyUnitLaborMaterialLine cost
Demo & Prep
Bathroom Fixture Removal1ea$125$0$125
Haul-Off Per Load1ea$0$0$225
Interior Demolition Labor15sf$26$0$26
Site Protection, One Room (per job)1ea$300$0$300
Plumbing
Shower Pan Materials1ea$0$475$475
Shower valve trim allowance1ea$0$285$285
Shower/Tub Valve Set1ea$425$0$425
Shower Valve Rough-In Body Allowance1ea$0$200$200
Drywall
Drywall Removal88sf$88$0$88
Tile
Tile Grout Install Labor88sf$154$0$154
Tile Grout Materials88sf$0$40$40
Bathroom Tile Install Labor88sf$1,188$0$1,188
Bath Tile Setting Materials96.8sf$0$82$82
Bathroom Tile Substrate Materials88sf$0$131$131
Bathroom Tile Substrate Prep Labor88sf$286$0$286
Tile Waterproofing Install Labor88sf$198$0$198
Bath Tile Waterproofing Materials88sf$0$172$172
Bathroom wall tile material allowance96.8sf$0$1,307$1,307
Tile Floor Removal15sf$67$0$67
Wall Tile Removal88sf$418$0$418
Shower Pan Install Labor1ea$475$0$475
Direct job cost$3,750$2,692$6,667

D. Tile walls, foam tray pan: $8,494

Tiled walls and a tiled floor on a sloped foam tray with a bonded membrane. All wall backer is new, because the old shower comes out to the studs. Labor is $5,016 of the $8,494 job cost, or 59.1%. It is about 55 to 74 hours of work for your own crew, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure for your own crew, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Overhead×1.30Established×1.50Full-Service×2.00
Demo & Prep4 to 8 h$451$586$677$902
Plumbing2 to 5 h$425$553$637$850
Drywall1 to 2 h$88$114$132$176
Tile37 to 54 h$4,052$5,268$6,078$8,104
Setup, cleanup and material runs4 to 13 hin the prices
All labor55 to 74 h$5,016$6,521$7,524$10,032

Every line item

Labor $5,016 + materials and allowances $3,253 + dump fees and other $225 = $8,494 direct job cost. Some labor quantities include a difficulty factor (large-format tile, for example, is counted at 1.35 times its area), so they can exceed the tiled area; each row’s derivation is in the downloadable data.

Line items (24)
ItemQtyUnitLaborMaterialLine cost
Demo & Prep
Bathroom Fixture Removal1ea$125$0$125
Haul-Off Per Load1ea$0$0$225
Interior Demolition Labor15sf$26$0$26
Site Protection, One Room (per job)1ea$300$0$300
Plumbing
Shower Pan Materials1ea$0$575$575
Shower valve trim allowance1ea$0$285$285
Shower/Tub Valve Set1ea$425$0$425
Shower Valve Rough-In Body Allowance1ea$0$200$200
Drywall
Drywall Removal88sf$88$0$88
Tile
Tile Grout Install Labor103sf$180$0$180
Tile Grout Materials103sf$0$46$46
Bathroom Tile Install Labor103sf$1,428$0$1,428
Bathroom Tile Material Allowance16.5sf$0$182$182
Bath Tile Setting Materials113.3sf$0$96$96
Bathroom Tile Substrate Materials88sf$0$131$131
Bathroom Tile Substrate Prep Labor88sf$286$0$286
Tile Waterproofing Install Labor88sf$330$0$330
Bath Tile Waterproofing Materials88sf$0$286$286
Bathroom wall tile material allowance96.8sf$0$1,307$1,307
Tile Floor Removal15sf$68$0$68
Wall Tile Removal88sf$418$0$418
Shower Curb Materials1ea$0$145$145
Shower Flood Test Labor1ea$250$0$250
Shower Pan Install Labor1ea$1,092$0$1,092
Direct job cost$5,016$3,253$8,494

E. Tile walls, mud-bed pan: $9,037

Tiled walls and a tiled floor on a site-built mortar bed, with a bonded sheet membrane and a bonding-flange drain instead of a liner. All wall backer is new, because the old shower comes out to the studs. Labor is $6,014 of the $9,037 job cost, or 66.5%. It is about 58 to 78 hours of work for your own crew, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure for your own crew, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Overhead×1.30Established×1.50Full-Service×2.00
Demo & Prep4 to 8 h$451$586$677$902
Plumbing2 to 5 h$425$553$637$850
Drywall1 to 2 h$88$114$132$176
Tile41 to 58 h$5,050$6,565$7,575$10,100
Setup, cleanup and material runs4 to 14 hin the prices
All labor58 to 78 h$6,014$7,818$9,021$12,028

Every line item

Labor $6,014 + materials and allowances $2,798 + dump fees and other $225 = $9,037 direct job cost. Some labor quantities include a difficulty factor (large-format tile, for example, is counted at 1.35 times its area), so they can exceed the tiled area; each row’s derivation is in the downloadable data.

Line items (23)
ItemQtyUnitLaborMaterialLine cost
Demo & Prep
Bathroom Fixture Removal1ea$125$0$125
Haul-Off Per Load1ea$0$0$225
Interior Demolition Labor15sf$26$0$26
Site Protection, One Room (per job)1ea$300$0$300
Plumbing
Shower Pan Materials1ea$0$265$265
Shower valve trim allowance1ea$0$285$285
Shower/Tub Valve Set1ea$425$0$425
Shower Valve Rough-In Body Allowance1ea$0$200$200
Drywall
Drywall Removal88sf$88$0$88
Tile
Tile Grout Install Labor103sf$180$0$180
Tile Grout Materials103sf$0$46$46
Bathroom Tile Install Labor103sf$1,428$0$1,428
Bathroom Tile Material Allowance16.5sf$0$182$182
Bath Tile Setting Materials113.3sf$0$96$96
Bathroom Tile Substrate Materials88sf$0$131$131
Bathroom Tile Substrate Prep Labor88sf$286$0$286
Tile Waterproofing Install Labor88sf$330$0$330
Bath Tile Waterproofing Materials88sf$0$286$286
Bathroom wall tile material allowance96.8sf$0$1,307$1,307
Tile Floor Removal15sf$68$0$68
Wall Tile Removal88sf$418$0$418
Shower Flood Test Labor1ea$250$0$250
Shower Pan Install Labor1ea$2,090$0$2,090
Direct job cost$6,014$2,798$9,037

Add-ons

Each add-on is added to build E (tile walls, mud-bed pan) and priced as one change to that same estimate. A range appears where the add-on includes an allowance, since the fixture or glass you pick sets the price.

Add-onAdds to job cost
Framed, tiled niche, one shelf$563 to $710
Framed, tiled niche, two shelves$738 to $885
Prefab foam niche insert, tiled in$638 to $785
Rain head plus handheld, on a diverter$703 to $2,088
Curtain on a fixed rod$190 to $353
Framed glass sliding door$526 to $1,288
Semi-frameless glass door and panel$1,416 to $3,603
Frameless 3/8 inch glass door and panel$1,549 to $3,895
Steam package, with the frameless door made vapor-tight and a transom (on top of the frameless door)$5,318 to $12,405

The glass rows replace each other, and the curtain replaces glass. Heavy frameless glass can need wall blocking, which is cheap while the walls are open and expensive after tile. Steam needs a sealed enclosure with a waterproofed, sloped ceiling, so it is priced on top of the frameless door.

Problems found once the old work is out

What it adds to the job cost when the wall or floor tells you something the walkthrough could not.

FoundAdds to job cost
Rotted subfloor under the pan, about 12 square feet$168
Drain moved to center the new pan$745
Valve moved to a new height or location$1,100
Plaster and lath walls instead of drywall$286
Pre-1978 home, lead-safe practices$685

Methodology & reproducibility

5 snapshots, one per build. Each build is frozen from its own estimate run with the same old work, system type and takeoff pinned, so the builds differ only in what is being built. Add-ons and problems found are each one stated change on build E, priced the same way.

Direct cost equals the sum of each row’s rounded quantity × (labor + material + other). Amounts are shown in whole dollars; every column adds to its total.

Scope selection, prose accuracy, arithmetic and provenance mapping reviewed; not independent market-rate verification.

Questions

Is a 5x3 shower the same as a 3x5?

Yes. Both describe a 60x36 inch shower, the size that replaces a standard tub. This page prices that footprint.

How does this compare with a full bathroom remodel?

This page prices only the shower. The published 5×8 bathroom remodel replaces the tub with a tiled surround, the vanity, toilet, fan, lighting, floor tile and paint, for a direct job cost of $11,799.

How much labor is in a 60x36 shower replacement?

In these builds labor runs from $2,918 for a multi-piece remodel unit to $6,014 for tile on a mud-bed pan. Tile is where the labor goes: setting backer, waterproofing, the pan, the curb and the tile itself.

Where does the cost difference between tile and fiberglass come from?

Mostly labor. A multi-piece unit is set and connected in a day; a tiled shower adds new backer, a waterproofing membrane, a pan, a curb, tile and grout. Build C, the cheapest tile build, costs $6,667 against $4,915 for the multi-piece unit.

Is a glass door included?

No. Every build is priced without a door so the builds compare evenly. A framed sliding door adds $838, semi-frameless $2,291, frameless $2,489, and a curtain on a fixed rod $255.

What does a mud-bed pan cost compared with a foam tray?

In these builds the mud bed costs $543 more than the foam tray. The mortar bed takes more labor; the foam tray costs more in materials and saves time.

What changes if the drain has to move?

Moving the drain to center a new pan adds $745 to the job cost in this example, before any floor framing repair. Rotted subfloor under the pan adds $168 for about 12 square feet.

Are permits included?

No. Permit and inspection fees are not included in any total on this page. Many jurisdictions require a plumbing permit when the valve is replaced, so check locally.

Why is the direct job cost lower than a contractor's price?

Direct job cost is labor and materials only. A contractor's price adds overhead and profit on top; at the illustrative 30% to 100% markups on this page, build E sells for $11,748 to $18,073.

Related

Sources & provenance

  1. 5×8 Bathroom Remodel v3 reviewed snapshot Clamp Research
  2. Multi-piece remodel unit reviewed snapshot Clamp Research
  3. Acrylic base + surround kit reviewed snapshot Clamp Research
  4. Tile walls, acrylic base reviewed snapshot Clamp Research
  5. Tile walls, foam tray pan reviewed snapshot Clamp Research
  6. Tile walls, mud-bed pan reviewed snapshot Clamp Research
Changes: Oct 2, 2026: Created draft from candidate snapshots; not published.; Oct 11, 2026: Re-priced on the current job-cost rates (sub-price labor basis); crew hours added, including setup, daily cleanup and material runs; not published.; Oct 11, 2026: Published after owner review of the rates.