New Home Construction Cost: Four Builds Compared (2026 Baseline)

Four new houses, fully itemized: a 1,050 sf cottage, a builder-grade 1,500 sf and a mid-grade 1,600 sf slab ranch, and a 2,400 sf two-story over a full basement. Every quantity, rate and formula shown, with crew hours.

Direct answer: Building a new single-family house has a direct job cost of $191,610 for a 1,050 sf two-bedroom cottage up to $452,741 for a 2,400 sf four-bedroom two-story over a full unfinished basement. At illustrative markups of 25% to 40%, that is a selling price of about $239,513 to $268,254 for the first and $565,926 to $633,837 for the second. Direct job cost is labor and materials only, with no contractor overhead or profit, and is not a price: no contractor performs work at job cost. Permit and inspection fees are not included.
Clamp's Generate from description screen with the 1,500 sf spec ranch described in plain words

Describe the house

Clamp's review draft for the spec house: at a glance summary, what's included, not included and assumed, with permits shown outside the total

Review the draft

The 1,500 sf ranch in the Clamp app: the job described the way a builder would text it, then the review draft with what's included, what's not and what's assumed, before the itemized estimate. The draft even flags the vanity-top question this page's build pins to laminate. Sample data.

Four builds, side by side

Four houses on the same researched baseline rates: a 1,050 sf cottage, a builder-grade 1,500 sf spec ranch, a mid-grade 1,600 sf ranch, and a 2,400 sf two-story over a full unfinished basement. Size and finish both step up from build to build.

BuildJob costLaborCrew hoursMaterialsIllustrative selling price
A. 1,050 sf cottage$191,610$81,1671235 to 1462 h$82,003$239,513 to
$268,254
B. 1,500 sf spec ranch, builder grade$261,875$106,6101557 to 1848 h$116,887$327,344 to
$366,625
C. 1,600 sf ranch, mid grade$289,326$113,6071681 to 1992 h$138,190$361,658 to
$405,057
D. 2,400 sf two-story$452,741$189,0162965 to 3505 h$209,281$565,926 to
$633,837

Materials include allowances. Illustrative selling price is the job cost at a 25% to 40% markup; your price depends on your own overhead and profit. Labor hours are a planning range and include setup, daily cleanup and material runs; they are never a charge to the customer. Permit and inspection fees are not included; requirements vary by jurisdiction.

Each build in detail

A. 1,050 sf cottage: $191,610

Two bedrooms and one bath on a crawlspace, vinyl siding, stock cabinets with laminate tops, LVP, an electric heat pump and a 40 foot gravel driveway. No garage. Labor is $81,167 of the $191,610 job cost, or 42.4%. It is about 1235 to 1462 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Margin×1.25Mid-Range×1.30High-Margin×1.40
Permits & PM2 to 6 h$325$406$422$455
Sitework3 to 8 h$319$399$415$447
Masonry85 to 144 h$4,804$6,005$6,245$6,726
Plumbing62 to 81 h$6,000$7,500$7,800$8,400
Electrical128 to 176 h$14,322$17,903$18,619$20,051
HVAC73 to 109 h$7,670$9,588$9,971$10,738
Insulation16 to 34 h$1,184$1,480$1,539$1,658
Drywall104 to 174 h$7,188$8,985$9,344$10,063
Carpentry270 to 337 h$21,282$26,603$27,667$29,795
Tile15 to 25 h$1,048$1,310$1,362$1,467
Flooring18 to 37 h$2,046$2,557$2,660$2,864
Painting73 to 101 h$4,956$6,195$6,443$6,938
Vanity & Fixtures1 to 3 h$240$300$312$336
Appliances1 to 3 h$170$212$221$238
Exterior28 to 48 h$2,511$3,139$3,264$3,515
Cleanup & Disposal12 to 49 h$2,100$2,625$2,730$2,940
Roofing30 to 48 h$3,662$4,577$4,761$5,127
Landscaping14 to 26 h$1,340$1,675$1,742$1,876
Setup, cleanup and material runs87 to 264 hin the prices
All labor1235 to 1462 h$81,167$101,459$105,517$113,634

Every line item

Labor $81,167 + materials and allowances $82,003 + dump fees and other $28,440 = $191,610 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Permits & PM
Paving Crew Mobilization (per job)1ea2 to 6 h$325$0$325
Permits & PM subtotal2 to 6 h$325
Permits & PM subtotal2 to 6 h$325
Sitework
Silt Fence Install Labor228lf3 to 8 h$319$0$319
Excavation Equipment Rental1day$0$0$550
Foundation Excavation (Machine, Per Cubic Yard)61.58cubic_yard$0$0$985
Portable Toilet Rental (per month)5month$0$0$1,125
Site Survey and Building Staking (per project)1ea$0$0$1,200
Sitework subtotal3 to 8 h$4,179
Sitework subtotal3 to 8 h$4,179
Masonry
Concrete Flatwork Install Labor72sf2 to 5 h$223$0$223
Concrete Flatwork MaterialsLabor on: Concrete Flatwork Install Labor79.2sf$0$416$416
Concrete Footing Install Labor147lf22 to 48 h$1,544$0$1,544
Concrete Footing MaterialsLabor on: Concrete Footing Install Labor161.7lf$0$2,345$2,345
Foundation Dampproofing, Spray Applied408sf$0$0$510
Foundation Pour Labor13.5cubic_yard49 to 103 h$3,037$0$3,037
Foundation Pour MaterialsLabor on: Foundation Pour Labor14.85cubic_yard$0$4,232$4,232
Under-Slab Vapor Retarder (per sf)1050sf$0$0$577
Masonry subtotal85 to 144 h$12,884
Masonry subtotal85 to 144 h$12,884
Plumbing
Dishwasher Hookup Labor1ea1 to 3 h$185$0$185
DWV Install Labor22lf7 to 15 h$792$0$792
Expansion Tank AllowanceLabor on: Expansion Tank Service Labor1ea$0$75$75
Expansion Tank Service Labor1ea1 to 2 h$110$0$110
Exterior Footing Drain (per lf)136lf$0$0$1,904
Faucet AllowanceLabor on: Fixture Set Labor1ea$0$100$100
Kitchen Sink AllowanceLabor on: Fixture Set Labor1ea$0$360$360
Lavatory Sink AllowanceLabor on: Fixture Set Labor1ea$0$90$90
Toilet AllowanceLabor on: Fixture Set Labor1ea$0$160$160
Fixture Set Labor5ea8 to 17 h$975$0$975
Hose Bib Fixture AllowanceLabor on: Fixture Set Labor2ea$0$76$76
Lavatory faucet allowanceLabor on: Fixture Set Labor1ea$0$90$90
DWV MaterialsLabor on: DWV Install Labor42.8lf$0$267$267
Plumbing Main Lines, New House (per sf)1050sf$0$0$4,462
Rough Plumbing ConsumablesLabor on: Plumbing Rough-In Per Fixture4ea$0$168$168
Plumbing Rough-In Per Fixture4ea10 to 22 h$1,600$0$1,600
Supply Pipe MaterialsLabor on: Supply Line Install Labor71lf$0$248$248
Sewer Cleanout Assembly AllowanceLabor on: Sewer Cleanout Install Labor1ea$0$95$95
Sewer Cleanout Install Labor1ea2 to 5 h$385$0$385
Shower valve trim allowanceLabor on: Shower/Tub Valve Set1ea$0$110$110
Shower/Tub Valve Set1ea2 to 5 h$325$0$325
Shower Valve Rough-In Body AllowanceLabor on: Shower/Tub Valve Set1ea$0$75$75
Shutoff Valve Install2ea1 to 2 h$116$0$116
Supply Line Install Labor43lf2 to 7 h$258$0$258
Alcove tub setting materialsLabor on: Fixture Set Labor1ea$0$65$65
Tub Unit AllowanceLabor on: Fixture Set Labor1ea$0$450$450
Tub Waste and Overflow KitLabor on: Fixture Set Labor1ea$0$65$65
Washer Box Install Labor1ea1 to 3 h$230$0$230
Tank Water Heater AllowanceLabor on: Tank Water Heater Install1ea$0$750$750
Water Heater Connection KitLabor on: Tank Water Heater Install1ea$0$63$63
Tank Water Heater Install1ea1 to 4 h$297$0$297
Water Service Pipe Install Labor50lf2 to 6 h$212$0$212
Water Service Pipe MaterialsLabor on: Water Service Pipe Install Labor52.5lf$0$289$289
Water Service Pressure Test Labor1ea1 to 3 h$190$0$190
Water Service Trenching Labor50lf3 to 8 h$325$0$325
Plumbing subtotal62 to 81 h$15,962
Plumbing subtotal62 to 81 h$15,962
Electrical
Bath Fan Duct Install Labor8lfunder 1 h$38$0$38
Bath Fan Duct MaterialsLabor on: Bath Fan Duct Install Labor9.2lf$0$25$25
Bath Fan Electrical Hookup Labor1each1 to 2 h$100$0$100
Bath Fan Termination Install Labor1each1 to 2 h$110$0$110
Bath Fan Termination MaterialsLabor on: Bath Fan Termination Install Labor1each$0$45$45
Bath Fan Housing Install Labor1each1 to 3 h$190$0$190
Bath Fan Testing & Commissioning1eachunder 1 h$30$0$30
Electrical Box ExtenderLabor on: Outlet Integration Labor2ea$0$7$7
Branch Circuit Install16ea33 to 70 h$4,320$0$4,320
New Branch Circuit (labor)1ea1 to 3 h$240$0$240
Dedicated Appliance Circuit1ea2 to 5 h$275$0$275
Dedicated Circuit Breaker AllowanceLabor on: Branch Circuit Install5ea$0$108$108
240V Outlet Install1ea1 to 4 h$235$0$235
Underground Electric Service Lateral (per lf)50lf$0$0$1,400
Electrical Box and Device MaterialsLabor on: Electrical Rough-In Per Device60ea$0$510$510
Electrical Rough ConsumablesLabor on: Electrical Rough-In Per Device23ea$0$150$150
Electrical Rough-In Per Device61ea23 to 50 h$2,562$0$2,562
GFCI/AFCI Device Install5ea1 to 4 h$240$0$240
Gfci Unit AllowanceLabor on: GFCI/AFCI Device Install6ea$0$120$120
HVAC Condenser DisconnectLabor on: Air Source Heat Pump Install1ea$0$35$35
Light Fixture AllowanceLabor on: Light Fixture Install8ea$0$400$400
Light Fixture Install13ea7 to 15 h$1,105$0$1,105
Lighting Dimmer AllowanceLabor on: Outlet/Switch Install1ea$0$28$28
Meter Socket AllowanceLabor on: Service Meter and Riser Install1ea$0$150$150
NM Cable 10/3 (30 A, 240 V)Labor on: Branch Circuit Install184lf$0$340$340
Outlet Integration Labor1ea1 to 3 h$185$0$185
Outlet/Switch Install43ea6 to 15 h$1,290$0$1,290
Outlet Unit AllowanceLabor on: Outlet/Switch Install29ea$0$88$88
Recessed Can AllowanceLabor on: Recessed Light, New Work (open ceiling)16ea$0$508$508
Recessed Light, New Work (open ceiling)11ea4 to 10 h$572$0$572
Romex Wire MaterialsLabor on: Electrical Rough-In Per Device1763.6lf$0$1,411$1,411
Service Meter and Riser Install1ea4 to 10 h$1,200$0$1,200
Service Panel AllowanceLabor on: Service Panel Install Labor1ea$0$950$950
Service Panel Install Labor1ea5 to 13 h$1,450$0$1,450
Smoke / CO Detector AllowanceLabor on: Smoke/CO Detector Install4ea$0$220$220
Smoke/CO Detector Install4ea1 to 3 h$180$0$180
Switch Unit AllowanceLabor on: Outlet/Switch Install15ea$0$35$35
Temporary Power Service (per month)5month$0$0$825
Electrical subtotal128 to 176 h$21,677
Electrical subtotal128 to 176 h$21,677
HVAC
Appliance Vent Termination1ea1 to 3 h$195$0$195
Backup Strip Heat AllowanceLabor on: Backup Strip Heat Install Labor1ea$0$275$275
Backup Strip Heat Install Labor1ea1 to 4 h$225$0$225
Bathroom Exhaust Fan Unit AllowanceLabor on: Bath Fan Housing Install Labor1ea$0$215$215
Condensate Drain Install1ea1 to 3 h$150$0$150
Dryer Vent Install Labor10lf1 to 3 h$165$0$165
Ducted Heat Pump System Equipment (per system)Labor on: Air Source Heat Pump Install1ea$0$3,467$3,467
Ductwork Install216lf28 to 59 h$2,700$0$2,700
Ductwork MaterialsLabor on: Ductwork Install226.8lf$0$1,758$1,758
Air Source Heat Pump Install1ea14 to 30 h$2,700$0$2,700
HVAC Commissioning and Balance1ea1 to 5 h$340$0$340
HVAC Install Consumables1ea$0$285$285
HVAC Load Calculation Labor1ea2 to 6 h$340$0$340
Range hood exhaust duct install10lf1 to 4 h$95$0$95
Range hood exhaust duct materialsLabor on: Range hood exhaust duct install10lf$0$115$115
Refrigerant Line Set Install30lf1 to 4 h$255$0$255
Refrigerant Line MaterialsLabor on: Refrigerant Line Set Install34.5lf$0$293$293
Register Boot AllowanceLabor on: Ductwork Install12ea$0$384$384
Register and Grille Install12ea1 to 3 h$168$0$168
Return Duct Install Labor45lf1 to 5 h$247$0$247
Return Duct MaterialsLabor on: Return Duct Install Labor45lf$0$427$427
Standard Thermostat Install1ea1 to 2 h$90$0$90
Thermostat Unit AllowanceLabor on: Standard Thermostat Install1ea$0$200$200
HVAC subtotal73 to 109 h$15,089
HVAC subtotal73 to 109 h$15,089
Insulation
Air Sealing Package, New House1050sf$0$0$788
Attic Blown Insulation, Installed (per sf at R-49)1050sf$0$0$1,733
Bath Fan Air Sealing Labor1eachunder 1 h$28$0$28
Floor Insulation from Below, Installed (per sf)1050sf$0$0$1,732
Rim Joist Insulation Install (per lf)136lf15 to 34 h$1,156$0$1,156
Rim Joist Rigid Foam (per lf)Labor on: Rim Joist Insulation Install (per lf)136lf$0$218$218
Wall Batt Insulation, Installed (per sf)896sf$0$0$941
Insulation subtotal16 to 34 h$6,596
Insulation subtotal16 to 34 h$6,596
Drywall
Drywall Finish Labor3885sf52 to 110 h$4,779$0$4,779
Drywall Hang Labor3885sf37 to 79 h$2,409$0$2,409
Drywall Sheets MaterialsLabor on: Drywall Hang Labor4273.5sf$0$3,205$3,205
Drywall subtotal104 to 174 h$10,393
Drywall subtotal104 to 174 h$10,393
Carpentry
Floor System Framing Labor1050sf34 to 71 h$3,675$0$3,675
Floor System Framing MaterialsLabor on: Floor System Framing Labor1102.5sf$0$4,961$4,961
Bathroom Accessory AllowanceLabor on: Bathroom Accessory Install Labor3ea$0$75$75
Bathroom Accessory Install Labor3ea1 to 2 h$84$0$84
Cabinet Fillers, End Panels and Toe KickLabor on: Cabinet Install Labor12lf$0$300$300
Cabinet Install Labor17lf6 to 14 h$638$0$638
Closet System Install24lf3 to 7 h$504$0$504
Countertop Install, Laminate34sf2 to 6 h$238$0$238
Crawlspace Access Door1ea$0$0$485
Door Lock Hardware AllowanceLabor on: Exterior Door Install2each$0$190$190
Door/Window Unit AllowanceLabor on: Exterior Door Install2ea$0$1,540$1,540
Exterior Door Install2ea4 to 10 h$1,000$0$1,000
Exterior Trim Install36lf1 to 4 h$153$0$153
Exterior Wall Framing MaterialsLabor on: Stud Wall Framing Install142.8lf$0$1,928$1,928
Framing Fasteners and HardwareLabor on: Stud Wall Framing Install220.5lf$0$243$243
Sheathing Install2468sf19 to 40 h$2,715$0$2,715
Stud Wall Framing Install267lf34 to 73 h$2,670$0$2,670
Interior Door Hardware AllowanceLabor on: Interior Door Install8each$0$600$600
Interior Door Install8ea11 to 25 h$1,400$0$1,400
Interior Door Slab AllowanceLabor on: Interior Door Install8each$0$720$720
Door Threshold Transition Labor3each1 to 3 h$96$0$96
Microwave Install Labor1ea2 to 5 h$160$0$160
Partition Door Rough Opening6ea2 to 7 h$408$0$408
Porch Ceiling, Install Labor72sf2 to 6 h$342$0$342
Porch Ceiling MaterialLabor on: Porch Ceiling, Install Labor79.2sf$0$178$178
Porch Posts and Beam, Framing Labor13lf6 to 15 h$754$0$754
Porch Posts and Beam, MaterialsLabor on: Porch Posts and Beam, Framing Labor13lf$0$546$546
Roof Trusses and Roof Sheathing Materials (per roofing square)Labor on: Roof Truss Set and Brace (per roofing square)14.49square$0$7,028$7,028
Roof Truss Set and Brace (per roofing square)13.8square14 to 30 h$1,173$0$1,173
Base Shoe / Quarter Round Install23lfunder 1 h$31$0$31
Base Shoe / Quarter Round MaterialsLabor on: Base Shoe / Quarter Round Install25.3lf$0$32$32
Shower Curtain Rod AllowanceLabor on: Shower Curtain Rod Install Labor1ea$0$85$85
Shower Curtain Rod Install Labor1eaunder 1 h$55$0$55
Soffit and Fascia Install156lf14 to 30 h$1,014$0$1,014
Stud Wall Framing MaterialsLabor on: Stud Wall Framing Install144.1lf$0$973$973
Baseboard and Casing Install477lf12 to 26 h$1,312$0$1,312
Trim MaterialsLabor on: Baseboard and Casing Install796.7lf$0$1,673$1,673
Vanity Install Labor1ea3 to 7 h$425$0$425
Vanity Mirror Install (per unit)1eaunder 1 h$65$0$65
Wall Sheathing MaterialsLabor on: Sheathing Install1196.8sf$0$1,137$1,137
Window Caulk & Flash MaterialsLabor on: Window Install10each$0$480$480
Window and Door Install ConsumablesLabor on: Exterior Door Install2ea$0$96$96
Window Exterior Trim MaterialsLabor on: Exterior Trim Install36lf$0$117$117
Window Install10ea13 to 29 h$1,950$0$1,950
Window Stool and Apron Stock (per window)Labor on: Window Stool and Apron Install10ea$0$220$220
Window Stool and Apron Install10ea4 to 9 h$420$0$420
Window Unit AllowanceLabor on: Window Install10each$0$3,000$3,000
Carpentry subtotal270 to 337 h$47,889
Carpentry subtotal270 to 337 h$47,889
Tile
Tile Grout Install Labor80sf1 to 4 h$140$0$140
Tile Grout MaterialsLabor on: Tile Grout Install Labor80sf$0$36$36
Bathroom Tile Install Labor80sf6 to 15 h$520$0$520
Bathroom Tile Material AllowanceLabor on: Bathroom Tile Install Labor88sf$0$220$220
Bath Tile Setting MaterialsLabor on: Bathroom Tile Install Labor88sf$0$75$75
Bathroom Tile Substrate MaterialsLabor on: Bathroom Tile Substrate Prep Labor80sf$0$119$119
Bathroom Tile Substrate Prep Labor80sf2 to 5 h$180$0$180
Tile Grout Sealer21sfunder 1 h$9$0$9
Tile Material AllowanceLabor on: Wall Tile Install21sf$0$136$136
Tile Setting MaterialsLabor on: Wall Tile Install21sf$0$39$39
Wall Tile Install21sf1 to 5 h$199$0$199
Tile subtotal15 to 25 h$1,673
Tile subtotal15 to 25 h$1,673
Flooring
Floor Transition Install2ea1 to 3 h$80$0$80
Floor Transition MaterialsLabor on: Floor Transition Install5ea$0$175$175
Floor Underlayment Materials936sf$0$515$515
Flooring Install Consumables2ea$0$170$170
LVP/LVT Install936sf17 to 36 h$1,966$0$1,966
LVP/LVT Material AllowanceLabor on: LVP/LVT Install1029.6sf$0$3,346$3,346
Flooring subtotal18 to 37 h$6,252
Flooring subtotal18 to 37 h$6,252
Painting
Interior Ceiling Paint Apply Labor1050sf6 to 14 h$588$0$588
Interior Door Paint (per door)8ea6 to 13 h$496$0$496
Interior Paint Apply Labor2865sf14 to 30 h$1,604$0$1,604
Paint Masking Setup Labor2865sfunder 1 h$29$0$29
Premium Paint AllowanceLabor on: Interior Paint Apply Labor29.37gallon$0$1,410$1,410
Paint Prep Labor2985sf5 to 12 h$269$0$269
Paint Primer Application Labor3597.8sf7 to 17 h$792$0$792
Paint and Primer MaterialsLabor on: Paint Primer Application Labor11.95gallon$0$382$382
Paint Sundries Materials1ls$0$150$150
Trim Caulk and Filler MaterialsLabor on: Trim Paint Apply Labor809lf$0$178$178
Trim Paint Apply Labor673lf15 to 33 h$1,178$0$1,178
Painting subtotal73 to 101 h$7,076
Painting subtotal73 to 101 h$7,076
Vanity & Fixtures
Cabinet Hardware (per piece)27ea$0$68$68
Cabinet Install Fasteners and ShimsLabor on: Cabinet Install Labor22lf$0$61$61
Cabinet Material AllowanceLabor on: Cabinet Install Labor17lf$0$3,060$3,060
Closet System AllowanceLabor on: Closet System Install26.4lf$0$1,188$1,188
Countertop Material, LaminateLabor on: Countertop Install, Laminate34sf$0$476$476
Countertop Seam Labor1eaunder 1 h$75$0$75
Countertop Sink Cutout Labor1ea1 to 2 h$165$0$165
Fixture Set MaterialsLabor on: Fixture Set Labor3ea$0$135$135
Laminate Countertop (per sf)Labor on: Vanity Install Labor9.5sf$0$114$114
Vanity Cabinet AllowanceLabor on: Vanity Install Labor5lf$0$650$650
Vanity Mirror or Medicine Cabinet (per unit)Labor on: Vanity Mirror Install (per unit)1ea$0$55$55
Vanity & Fixtures subtotal1 to 3 h$6,047
Vanity & Fixtures subtotal1 to 3 h$6,047
Appliances
Dishwasher Unit AllowanceLabor on: Dishwasher Hookup Labor1ea$0$500$500
Dryer Vent MaterialsLabor on: Dryer Vent Install Labor11lf$0$47$47
Dryer Vent Termination Allowance1ea$0$35$35
Microwave Unit AllowanceLabor on: Microwave Install Labor1ea$0$250$250
Range Set and Connect1ea1 to 2 h$85$0$85
Range Unit AllowanceLabor on: Range Set and Connect1ea$0$700$700
Refrigerator Install Labor1ea1 to 2 h$85$0$85
Refrigerator Unit AllowanceLabor on: Refrigerator Install Labor1ea$0$900$900
Washer Box AllowanceLabor on: Washer Box Install Labor1ea$0$65$65
Appliances subtotal1 to 3 h$2,667
Appliances subtotal1 to 3 h$2,667
Exterior
Exterior Caulking and Sealing Labor111.28lf2 to 5 h$161$0$161
House Wrap Install Labor1224sf6 to 14 h$441$0$441
House Wrap MaterialsLabor on: House Wrap Install Labor1346.4sf$0$565$565
Soffit and Fascia MaterialsLabor on: Soffit and Fascia Install171.6lf$0$1,459$1,459
Vinyl Siding Install Labor1032sf16 to 34 h$1,909$0$1,909
Vinyl Siding MaterialsLabor on: Vinyl Siding Install Labor1135.2sf$0$3,519$3,519
Exterior subtotal28 to 48 h$8,054
Exterior subtotal28 to 48 h$8,054
Specialty
Sewer Line Install50lf$0$0$4,250
Temporary Utilities Setup2ea$0$0$2,100
Utility Locate Service1ea$0$0$450
Specialty subtotal$6,800
Specialty subtotal$6,800
Cleanup & Disposal
Construction Dumpster, per Haul3ea$0$0$1,950
Final Construction Clean (per sf)1050sf$0$0$473
Rough Clean, per Phase3ea12 to 49 h$2,100$0$2,100
Cleanup & Disposal subtotal12 to 49 h$4,523
Cleanup & Disposal subtotal12 to 49 h$4,523
General
Generic Install Consumables3ls$0$255$255
General subtotal$255
General subtotal$255
Roofing
Asphalt Shingle Install Labor13.8square14 to 30 h$2,484$0$2,484
Asphalt Shingle MaterialsLabor on: Asphalt Shingle Install Labor15.18square$0$2,657$2,657
Downspout Install Labor4ea1 to 5 h$220$0$220
Downspout MaterialsLabor on: Downspout Install Labor4ea$0$220$220
Drip Edge MaterialsLabor on: Asphalt Shingle Install Labor156.02lf$0$148$148
Gutter Install Labor85lf4 to 10 h$382$0$382
Gutter MaterialsLabor on: Gutter Install Labor93.5lf$0$514$514
Ice Water Shield Install Labor2.07sq1 to 3 h$75$0$75
Ice Water Shield MaterialsLabor on: Ice Water Shield Install Labor2.07sq$0$197$197
Ridge Vent Install Labor44.58lf1 to 2 h$87$0$87
Ridge Vent MaterialsLabor on: Ridge Vent Install Labor44.58lf$0$189$189
Synthetic Underlayment Install Labor13.8square2 to 6 h$414$0$414
Synthetic Underlayment Materials14.49square$0$217$217
Roofing subtotal30 to 48 h$7,804
Roofing subtotal30 to 48 h$7,804
Landscaping
Compacted Gravel Base (per sf)480sf$0$408$408
Gravel Path Spread and Compact (per sf)480sf9 to 20 h$696$0$696
Gravel Path Surface (per sf)Labor on: Gravel Path Spread and Compact (per sf)480sf$0$504$504
Landscaping Allowance, New House1ea$0$3,000$3,000
Silt Fence Materials (per lf)Labor on: Silt Fence Install Labor250.8lf$0$213$213
Site Grading Labor2929sf3 to 8 h$644$0$644
Landscaping subtotal14 to 26 h$5,465
Landscaping subtotal14 to 26 h$5,465
DIRECT JOB COST1235 to 1462 h$191,610
DIRECT JOB COST1235 to 1462 h$191,610

B. 1,500 sf spec ranch, builder grade: $261,875

A builder-grade spec: three bedrooms and two baths on a slab, an attached two-car garage, vinyl siding, stock white shaker cabinets, a quartz kitchen with laminate vanity tops, fiberglass tub showers and LVP everywhere. Cover over the front door only, and no driveway was stated or priced. Labor is $106,610 of the $261,875 job cost, or 40.7%. It is about 1557 to 1848 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Margin×1.25Mid-Range×1.30High-Margin×1.40
Sitework4 to 9 h$374$468$486$524
Masonry70 to 141 h$6,694$8,368$8,702$9,371
Plumbing79 to 105 h$7,915$9,894$10,289$11,081
Electrical175 to 239 h$19,119$23,899$24,855$26,767
HVAC87 to 132 h$8,923$11,154$11,600$12,492
Insulationunder 1 h$56$70$73$78
Drywall154 to 256 h$10,612$13,265$13,796$14,857
Carpentry345 to 435 h$27,503$34,379$35,754$38,504
Tile24 to 38 h$1,614$2,017$2,098$2,260
Flooring25 to 52 h$2,873$3,591$3,735$4,022
Painting103 to 142 h$7,056$8,820$9,173$9,878
Appliances1 to 3 h$170$212$221$238
Exterior47 to 80 h$4,212$5,265$5,476$5,897
Cleanup & Disposal12 to 49 h$2,100$2,625$2,730$2,940
Roofing51 to 82 h$6,417$8,021$8,342$8,984
Landscaping5 to 12 h$972$1,215$1,263$1,361
Setup, cleanup and material runs111 to 334 hin the prices
All labor1557 to 1848 h$106,610$133,263$138,593$149,254

Every line item

Labor $106,610 + materials and allowances $116,887 + dump fees and other $38,378 = $261,875 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Sitework
Construction Entrance, Stabilized Stone1ea$0$0$2,400
Silt Fence Install Labor267lf4 to 9 h$374$0$374
Excavation Equipment Rental1day$0$0$550
Foundation Excavation (Machine, Per Cubic Yard)62.31cubic_yard$0$0$997
Portable Toilet Rental (per month)6month$0$0$1,350
Site Survey and Building Staking (per project)1ea$0$0$1,200
Sitework subtotal4 to 9 h$6,871
Sitework subtotal4 to 9 h$6,871
Masonry
Concrete Flatwork Install Labor2096sf65 to 136 h$6,498$0$6,498
Concrete Flatwork MaterialsLabor on: Concrete Flatwork Install Labor2305.6sf$0$12,104$12,104
Slab Thickened Edge (per lf)235lf$0$0$4,935
Stone Install Consumables1ea$0$135$135
Under-Slab Rigid Insulation Lay (per sf)326sf3 to 7 h$196$0$196
Under-Slab Vapor Retarder (per sf)2076sf$0$0$1,142
Masonry subtotal70 to 141 h$25,010
Masonry subtotal70 to 141 h$25,010
Plumbing
Dishwasher Hookup Labor1ea1 to 3 h$185$0$185
DWV Install Labor22lf7 to 15 h$792$0$792
Expansion Tank AllowanceLabor on: Expansion Tank Service Labor1ea$0$75$75
Expansion Tank Service Labor1ea1 to 2 h$110$0$110
Faucet AllowanceLabor on: Fixture Set Labor1ea$0$100$100
Kitchen Sink AllowanceLabor on: Fixture Set Labor1ea$0$360$360
Lavatory Sink AllowanceLabor on: Fixture Set Labor2ea$0$180$180
Toilet AllowanceLabor on: Fixture Set Labor2ea$0$320$320
Fixture Set Labor7ea11 to 24 h$1,365$0$1,365
Hose Bib Fixture AllowanceLabor on: Fixture Set Labor2ea$0$76$76
Lavatory faucet allowanceLabor on: Fixture Set Labor2ea$0$180$180
DWV MaterialsLabor on: DWV Install Labor62.6lf$0$391$391
Plumbing Main Lines, New House (per sf)1500sf$0$0$6,375
Rough Plumbing ConsumablesLabor on: Plumbing Rough-In Per Fixture7ea$0$294$294
Plumbing Rough-In Per Fixture7ea18 to 38 h$2,800$0$2,800
Supply Pipe MaterialsLabor on: Supply Line Install Labor97.4lf$0$341$341
Sewer Cleanout Assembly AllowanceLabor on: Sewer Cleanout Install Labor1ea$0$95$95
Sewer Cleanout Install Labor1ea2 to 5 h$385$0$385
Shower valve trim allowanceLabor on: Shower/Tub Valve Set2ea$0$220$220
Shower/Tub Valve Set2ea4 to 10 h$650$0$650
Shower Valve Rough-In Body AllowanceLabor on: Shower/Tub Valve Set2ea$0$150$150
Shutoff Valve Install2ea1 to 2 h$116$0$116
Supply Line Install Labor43lf2 to 7 h$258$0$258
Alcove tub setting materialsLabor on: Fixture Set Labor2ea$0$130$130
Tub Unit AllowanceLabor on: Fixture Set Labor2ea$0$900$900
Tub Waste and Overflow KitLabor on: Fixture Set Labor2ea$0$130$130
Washer Box Install Labor1ea1 to 3 h$230$0$230
Tank Water Heater AllowanceLabor on: Tank Water Heater Install1ea$0$750$750
Water Heater Connection KitLabor on: Tank Water Heater Install1ea$0$63$63
Tank Water Heater Install1ea1 to 4 h$297$0$297
Water Service Pipe Install Labor50lf2 to 6 h$212$0$212
Water Service Pipe MaterialsLabor on: Water Service Pipe Install Labor52.5lf$0$289$289
Water Service Pressure Test Labor1ea1 to 3 h$190$0$190
Water Service Trenching Labor50lf3 to 8 h$325$0$325
Plumbing subtotal79 to 105 h$19,334
Plumbing subtotal79 to 105 h$19,334
Electrical
Bath Fan Duct Install Labor16lf1 to 2 h$76$0$76
Bath Fan Duct MaterialsLabor on: Bath Fan Duct Install Labor18.4lf$0$51$51
Bath Fan Electrical Hookup Labor2each1 to 3 h$200$0$200
Bath Fan Termination Install Labor2each1 to 4 h$220$0$220
Bath Fan Termination MaterialsLabor on: Bath Fan Termination Install Labor2each$0$90$90
Bath Fan Housing Install Labor2each2 to 6 h$380$0$380
Bath Fan Testing & Commissioning2eachunder 1 h$60$0$60
Electrical Box ExtenderLabor on: Outlet Integration Labor2ea$0$7$7
Branch Circuit Install20ea41 to 87 h$5,400$0$5,400
New Branch Circuit (labor)2ea2 to 5 h$480$0$480
Dedicated Appliance Circuit1ea2 to 5 h$275$0$275
Dedicated Circuit Breaker AllowanceLabor on: Branch Circuit Install6ea$0$120$120
240V Outlet Install1ea1 to 4 h$235$0$235
Underground Electric Service Lateral (per lf)50lf$0$0$1,400
Electrical Box and Device MaterialsLabor on: Electrical Rough-In Per Device93ea$0$791$791
Electrical Rough ConsumablesLabor on: Electrical Rough-In Per Device27ea$0$176$176
Electrical Rough-In Per Device93ea36 to 76 h$3,906$0$3,906
Garage Door Opener (per opener)Labor on: Garage Door Opener Install Labor1ea$0$325$325
GFCI/AFCI Device Install6ea1 to 5 h$288$0$288
Gfci Unit AllowanceLabor on: GFCI/AFCI Device Install8ea$0$160$160
HVAC Condenser DisconnectLabor on: Air Source Heat Pump Install1ea$0$35$35
Light Fixture AllowanceLabor on: Light Fixture Install14ea$0$700$700
Light Fixture Install19ea10 to 22 h$1,615$0$1,615
Lighting Dimmer AllowanceLabor on: Outlet/Switch Install1ea$0$28$28
Meter Socket AllowanceLabor on: Service Meter and Riser Install1ea$0$150$150
NM Cable 10/3 (30 A, 240 V)Labor on: Branch Circuit Install184lf$0$340$340
Outlet Integration Labor1ea1 to 3 h$185$0$185
Outlet/Switch Install68ea11 to 23 h$2,040$0$2,040
Outlet Unit AllowanceLabor on: Outlet/Switch Install47ea$0$135$135
Recessed Can AllowanceLabor on: Recessed Light, New Work (open ceiling)22ea$0$736$736
Recessed Light, New Work (open ceiling)17ea6 to 15 h$884$0$884
Romex Wire MaterialsLabor on: Electrical Rough-In Per Device2795.6lf$0$2,236$2,236
Service Meter and Riser Install1ea4 to 10 h$1,200$0$1,200
Service Panel AllowanceLabor on: Service Panel Install Labor1ea$0$950$950
Service Panel Install Labor1ea5 to 13 h$1,450$0$1,450
Smoke / CO Detector AllowanceLabor on: Smoke/CO Detector Install5ea$0$275$275
Smoke/CO Detector Install5ea1 to 4 h$225$0$225
Switch Unit AllowanceLabor on: Outlet/Switch Install23ea$0$56$56
Temporary Power Service (per month)6month$0$0$990
Electrical subtotal175 to 239 h$28,870
Electrical subtotal175 to 239 h$28,870
HVAC
Appliance Vent Termination1ea1 to 3 h$195$0$195
Backup Strip Heat AllowanceLabor on: Backup Strip Heat Install Labor1ea$0$275$275
Backup Strip Heat Install Labor1ea1 to 4 h$225$0$225
Bathroom Exhaust Fan Unit AllowanceLabor on: Bath Fan Housing Install Labor2ea$0$430$430
Condensate Drain Install1ea1 to 3 h$150$0$150
Dryer Vent Install Labor10lf1 to 3 h$165$0$165
Ducted Heat Pump System Equipment (per system)Labor on: Air Source Heat Pump Install1ea$0$4,333$4,333
Ductwork Install292lf37 to 79 h$3,650$0$3,650
Ductwork MaterialsLabor on: Ductwork Install306.6lf$0$2,376$2,376
Air Source Heat Pump Install1ea14 to 31 h$2,850$0$2,850
HVAC Commissioning and Balance1ea1 to 5 h$340$0$340
HVAC Install Consumables1ea$0$285$285
HVAC Load Calculation Labor1ea2 to 6 h$340$0$340
Radiant Underslab Insulation Board (per sf)Labor on: Under-Slab Rigid Insulation Lay (per sf)342.3sf$0$616$616
Range hood exhaust duct install10lf1 to 4 h$95$0$95
Range hood exhaust duct materialsLabor on: Range hood exhaust duct install10lf$0$115$115
Refrigerant Line Set Install30lf1 to 4 h$255$0$255
Refrigerant Line MaterialsLabor on: Refrigerant Line Set Install34.5lf$0$293$293
Register Boot AllowanceLabor on: Ductwork Install17ea$0$544$544
Register and Grille Install17ea1 to 4 h$238$0$238
Return Duct Install Labor60lf2 to 6 h$330$0$330
Return Duct MaterialsLabor on: Return Duct Install Labor60lf$0$570$570
Standard Thermostat Install1ea1 to 2 h$90$0$90
Thermostat Unit AllowanceLabor on: Standard Thermostat Install1ea$0$200$200
HVAC subtotal87 to 132 h$18,960
HVAC subtotal87 to 132 h$18,960
Insulation
Air Sealing Package, New House1500sf$0$0$1,125
Attic Blown Insulation, Installed (per sf at R-49)1500sf$0$0$2,475
Bath Fan Air Sealing Labor2eachunder 1 h$56$0$56
Wall Batt Insulation, Installed (per sf)1052sf$0$0$1,105
Insulation subtotalunder 1 h$4,761
Insulation subtotalunder 1 h$4,761
Drywall
Drywall Finish Labor5766sf76 to 159 h$6,977$0$6,977
Drywall Hang Labor5550sf54 to 113 h$3,441$0$3,441
Drywall Sheets MaterialsLabor on: Drywall Hang Labor6105sf$0$4,579$4,579
Type X Drywall Hang, Fire-Rated (per sf)216sf2 to 6 h$194$0$194
Type X Fire-Rated Drywall Materials (per sf)Labor on: Type X Drywall Hang, Fire-Rated (per sf)237.6sf$0$162$162
Drywall subtotal154 to 256 h$15,353
Drywall subtotal154 to 256 h$15,353
Carpentry
Bathroom Accessory AllowanceLabor on: Bathroom Accessory Install Labor6ea$0$150$150
Bathroom Accessory Install Labor6ea1 to 4 h$168$0$168
Cabinet Fillers, End Panels and Toe KickLabor on: Cabinet Install Labor12lf$0$300$300
Cabinet Install Labor20lf7 to 17 h$750$0$750
Closet System Install32lf4 to 9 h$672$0$672
Door Lock Hardware AllowanceLabor on: Exterior Door Install2each$0$190$190
Door/Window Unit AllowanceLabor on: Exterior Door Install2ea$0$1,540$1,540
Engineered Beam Material AllowanceLabor on: Engineered Beam Install1ea$0$1,204$1,204
Exterior Door Install2ea4 to 10 h$1,000$0$1,000
Exterior Trim Install36lf1 to 4 h$153$0$153
Exterior Wall Framing MaterialsLabor on: Stud Wall Framing Install256.2lf$0$3,459$3,459
Fire-Rated Self-Closing Door Unit (each)Labor on: Interior Door Install1ea$0$475$475
Firestop at a Penetration (each)4ea1 to 3 h$96$0$96
Engineered Beam Install1ea5 to 12 h$1,204$0$1,204
Framing Fasteners and HardwareLabor on: Stud Wall Framing Install324lf$0$356$356
Sheathing Install4530sf35 to 74 h$4,983$0$4,983
Stud Wall Framing Install432lf56 to 117 h$4,320$0$4,320
Garage Door Install (per door)1ea6 to 14 h$595$0$595
Garage Door Opener Install Labor1ea2 to 5 h$165$0$165
Garage Door Unit (per door)Labor on: Garage Door Install (per door)1ea$0$1,980$1,980
Interior Door Hardware AllowanceLabor on: Interior Door Install12each$0$900$900
Interior Door Install12ea17 to 38 h$2,144$0$2,144
Interior Door Slab AllowanceLabor on: Interior Door Install11each$0$990$990
Door Threshold Transition Labor5each1 to 4 h$160$0$160
Microwave Install Labor1ea2 to 5 h$160$0$160
Partition Door Rough Opening8ea3 to 9 h$544$0$544
Porch Ceiling, Install Labor20sf1 to 2 h$95$0$95
Porch Ceiling MaterialLabor on: Porch Ceiling, Install Labor22sf$0$49$49
Porch Posts and Beam, Framing Labor7lf3 to 8 h$406$0$406
Porch Posts and Beam, MaterialsLabor on: Porch Posts and Beam, Framing Labor7lf$0$294$294
Roof Trusses and Roof Sheathing Materials (per roofing square)Labor on: Roof Truss Set and Brace (per roofing square)27.07square$0$13,129$13,129
Roof Truss Set and Brace (per roofing square)25.78square26 to 56 h$2,191$0$2,191
Base Shoe / Quarter Round Install22lfunder 1 h$30$0$30
Base Shoe / Quarter Round MaterialsLabor on: Base Shoe / Quarter Round Install24.2lf$0$30$30
Shower Curtain Rod AllowanceLabor on: Shower Curtain Rod Install Labor2ea$0$170$170
Shower Curtain Rod Install Labor2ea1 to 3 h$110$0$110
Soffit and Fascia Install213lf19 to 40 h$1,384$0$1,384
Stud Wall Framing MaterialsLabor on: Stud Wall Framing Install206.8lf$0$1,396$1,396
Baseboard and Casing Install682lf17 to 37 h$1,875$0$1,875
Trim MaterialsLabor on: Baseboard and Casing Install1124.2lf$0$2,361$2,361
Vanity Install Labor2ea6 to 14 h$850$0$850
Vanity Mirror Install (per unit)2ea1 to 3 h$130$0$130
Wall Sheathing MaterialsLabor on: Sheathing Install2147.2sf$0$2,040$2,040
Window Caulk & Flash MaterialsLabor on: Window Install14each$0$672$672
Window and Door Install ConsumablesLabor on: Exterior Door Install2ea$0$96$96
Window Exterior Trim MaterialsLabor on: Exterior Trim Install36lf$0$117$117
Window Install14ea18 to 40 h$2,730$0$2,730
Window Stool and Apron Stock (per window)Labor on: Window Stool and Apron Install14ea$0$308$308
Window Stool and Apron Install14ea5 to 12 h$588$0$588
Window Unit AllowanceLabor on: Window Install14each$0$4,200$4,200
Carpentry subtotal345 to 435 h$63,909
Carpentry subtotal345 to 435 h$63,909
Tile
Tile Grout Install Labor130sf2 to 6 h$228$0$228
Tile Grout MaterialsLabor on: Tile Grout Install Labor130sf$0$59$59
Bathroom Tile Install Labor130sf11 to 24 h$845$0$845
Bathroom Tile Material AllowanceLabor on: Bathroom Tile Install Labor143sf$0$358$358
Bath Tile Setting MaterialsLabor on: Bathroom Tile Install Labor143sf$0$122$122
Bathroom Tile Substrate MaterialsLabor on: Bathroom Tile Substrate Prep Labor130sf$0$194$194
Bathroom Tile Substrate Prep Labor130sf3 to 8 h$293$0$293
Tile Grout Sealer25sfunder 1 h$11$0$11
Tile Material AllowanceLabor on: Wall Tile Install25sf$0$162$162
Tile Setting MaterialsLabor on: Wall Tile Install25sf$0$46$46
Wall Tile Install25sf2 to 5 h$237$0$237
Tile subtotal24 to 38 h$2,555
Tile subtotal24 to 38 h$2,555
Flooring
Floor Transition Install2ea1 to 3 h$80$0$80
Floor Transition MaterialsLabor on: Floor Transition Install7ea$0$245$245
Floor Underlayment Materials1330sf$0$731$731
Flooring Install Consumables2ea$0$170$170
LVP/LVT Install1330sf24 to 51 h$2,793$0$2,793
LVP/LVT Material AllowanceLabor on: LVP/LVT Install1463sf$0$4,755$4,755
Flooring subtotal25 to 52 h$8,774
Flooring subtotal25 to 52 h$8,774
Painting
Interior Ceiling Paint Apply Labor1500sf9 to 20 h$840$0$840
Interior Door Paint (per door)11ea8 to 18 h$682$0$682
Interior Paint Apply Labor4080sf20 to 42 h$2,285$0$2,285
Paint Masking Setup Labor4080sf1 to 2 h$41$0$41
Premium Paint AllowanceLabor on: Interior Paint Apply Labor41.72gallon$0$2,003$2,003
Paint Prep Labor4200sf7 to 16 h$378$0$378
Paint Primer Application Labor5280.65sf11 to 24 h$1,162$0$1,162
Paint and Primer MaterialsLabor on: Paint Primer Application Labor17.54gallon$0$561$561
Paint Sundries Materials1ls$0$150$150
Trim Caulk and Filler MaterialsLabor on: Trim Paint Apply Labor1140lf$0$251$251
Trim Paint Apply Labor953lf22 to 46 h$1,668$0$1,668
Painting subtotal103 to 142 h$10,021
Painting subtotal103 to 142 h$10,021
Vanity & Fixtures
Cabinet Hardware (per piece)32ea$0$80$80
Cabinet Install Fasteners and ShimsLabor on: Cabinet Install Labor28lf$0$77$77
Cabinet Material AllowanceLabor on: Cabinet Install Labor20lf$0$3,600$3,600
Closet System AllowanceLabor on: Closet System Install35.2lf$0$1,584$1,584
Fixture Set MaterialsLabor on: Fixture Set Labor5ea$0$225$225
Laminate Countertop (per sf)Labor on: Vanity Install Labor15.2sf$0$182$182
Stone Countertop Fabrication40sf$0$0$1,120
Stone Countertop Install40sf$0$0$880
Stone Countertop Material AllowanceLabor on: Vanity Install Labor40sf$0$2,200$2,200
Vanity Cabinet AllowanceLabor on: Vanity Install Labor8lf$0$1,040$1,040
Vanity Mirror or Medicine Cabinet (per unit)Labor on: Vanity Mirror Install (per unit)2ea$0$110$110
Vanity & Fixtures subtotal$11,098
Vanity & Fixtures subtotal$11,098
Appliances
Dishwasher Unit AllowanceLabor on: Dishwasher Hookup Labor1ea$0$500$500
Dryer Vent MaterialsLabor on: Dryer Vent Install Labor11lf$0$47$47
Dryer Vent Termination Allowance1ea$0$35$35
Microwave Unit AllowanceLabor on: Microwave Install Labor1ea$0$250$250
Range Set and Connect1ea1 to 2 h$85$0$85
Range Unit AllowanceLabor on: Range Set and Connect1ea$0$700$700
Refrigerator Install Labor1ea1 to 2 h$85$0$85
Refrigerator Unit AllowanceLabor on: Refrigerator Install Labor1ea$0$900$900
Washer Box AllowanceLabor on: Washer Box Install Labor1ea$0$65$65
Appliances subtotal1 to 3 h$2,667
Appliances subtotal1 to 3 h$2,667
Exterior
Exterior Caulking and Sealing Labor146.2lf3 to 7 h$212$0$212
House Wrap Install Labor2115sf11 to 23 h$761$0$761
House Wrap MaterialsLabor on: House Wrap Install Labor2326.5sf$0$977$977
Soffit and Fascia MaterialsLabor on: Soffit and Fascia Install234.3lf$0$1,992$1,992
Vinyl Siding Install Labor1751sf27 to 57 h$3,239$0$3,239
Vinyl Siding MaterialsLabor on: Vinyl Siding Install Labor1926.1sf$0$5,971$5,971
Exterior subtotal47 to 80 h$13,152
Exterior subtotal47 to 80 h$13,152
Specialty
Sewer Line Install50lf$0$0$4,250
Temporary Utilities Setup2ea$0$0$2,100
Utility Locate Service1ea$0$0$450
Specialty subtotal$6,800
Specialty subtotal$6,800
Cleanup & Disposal
Construction Dumpster, per Haul4ea$0$0$2,600
Final Construction Clean (per sf)2076sf$0$0$934
Rough Clean, per Phase3ea12 to 49 h$2,100$0$2,100
Cleanup & Disposal subtotal12 to 49 h$5,634
Cleanup & Disposal subtotal12 to 49 h$5,634
General
Generic Install Consumables4ls$0$340$340
General subtotal$340
General subtotal$340
Roofing
Asphalt Shingle Install Labor25.78square26 to 56 h$4,640$0$4,640
Asphalt Shingle MaterialsLabor on: Asphalt Shingle Install Labor28.36square$0$4,963$4,963
Downspout Install Labor4ea1 to 5 h$220$0$220
Downspout MaterialsLabor on: Downspout Install Labor4ea$0$220$220
Drip Edge MaterialsLabor on: Asphalt Shingle Install Labor213.25lf$0$203$203
Gutter Install Labor117lf6 to 13 h$526$0$526
Gutter MaterialsLabor on: Gutter Install Labor128.7lf$0$708$708
Ice Water Shield Install Labor3.87sq2 to 5 h$139$0$139
Ice Water Shield MaterialsLabor on: Ice Water Shield Install Labor3.87sq$0$368$368
Ridge Vent Install Labor60.93lf1 to 3 h$119$0$119
Ridge Vent MaterialsLabor on: Ridge Vent Install Labor60.93lf$0$259$259
Synthetic Underlayment Install Labor25.78square5 to 11 h$773$0$773
Synthetic Underlayment Materials27.07square$0$406$406
Roofing subtotal51 to 82 h$13,544
Roofing subtotal51 to 82 h$13,544
Landscaping
Landscaping Allowance, New House1ea$0$3,000$3,000
Silt Fence Materials (per lf)Labor on: Silt Fence Install Labor293.7lf$0$250$250
Site Grading Labor4419sf5 to 12 h$972$0$972
Landscaping subtotal5 to 12 h$4,222
Landscaping subtotal5 to 12 h$4,222
DIRECT JOB COST1557 to 1848 h$261,875
DIRECT JOB COST1557 to 1848 h$261,875

C. 1,600 sf ranch, mid grade: $289,326

One finish tier up from the spec ranch: tiled and waterproofed baths, carpeted bedrooms, mid-grade windows, quartz counters, a 22x22 attached garage, a 6x10 covered porch and a 60 foot gravel driveway. Labor is $113,607 of the $289,326 job cost, or 39.3%. It is about 1681 to 1992 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Margin×1.25Mid-Range×1.30High-Margin×1.40
Permits & PM2 to 6 h$325$406$423$455
Sitework4 to 9 h$375$469$487$525
Masonry71 to 145 h$6,848$8,560$8,902$9,587
Plumbing79 to 105 h$7,915$9,894$10,289$11,081
Electrical181 to 248 h$19,729$24,661$25,648$27,621
HVAC87 to 133 h$8,960$11,200$11,648$12,544
Insulationunder 1 h$56$70$73$78
Drywall164 to 272 h$11,251$14,064$14,626$15,752
Carpentry374 to 467 h$29,893$37,366$38,861$41,850
Tile48 to 75 h$3,155$3,944$4,101$4,417
Flooring26 to 47 h$2,494$3,118$3,242$3,492
Painting111 to 153 h$7,586$9,483$9,862$10,620
Appliances1 to 3 h$170$212$221$238
Exterior47 to 79 h$4,166$5,207$5,416$5,832
Cleanup & Disposal12 to 49 h$2,100$2,625$2,730$2,940
Roofing52 to 84 h$6,552$8,190$8,518$9,173
Landscaping22 to 39 h$2,032$2,540$2,642$2,845
Setup, cleanup and material runs119 to 360 hin the prices
All labor1681 to 1992 h$113,607$142,009$147,689$159,050

Every line item

Labor $113,607 + materials and allowances $138,190 + dump fees and other $37,529 = $289,326 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Permits & PM
Paving Crew Mobilization (per job)1ea2 to 6 h$325$0$325
Permits & PM subtotal2 to 6 h$325
Permits & PM subtotal2 to 6 h$325
Sitework
Silt Fence Install Labor268lf4 to 9 h$375$0$375
Excavation Equipment Rental1day$0$0$550
Foundation Excavation (Machine, Per Cubic Yard)63.1cubic_yard$0$0$1,010
Portable Toilet Rental (per month)6month$0$0$1,350
Site Survey and Building Staking (per project)1ea$0$0$1,200
Sitework subtotal4 to 9 h$4,485
Sitework subtotal4 to 9 h$4,485
Masonry
Concrete Flatwork Install Labor2144sf66 to 139 h$6,646$0$6,646
Concrete Flatwork MaterialsLabor on: Concrete Flatwork Install Labor2358.4sf$0$12,382$12,382
Slab Thickened Edge (per lf)234lf$0$0$4,914
Stone Install Consumables1ea$0$135$135
Under-Slab Rigid Insulation Lay (per sf)336sf3 to 7 h$202$0$202
Under-Slab Vapor Retarder (per sf)2084sf$0$0$1,146
Masonry subtotal71 to 145 h$25,425
Masonry subtotal71 to 145 h$25,425
Plumbing
Alcove tub (tub only, no surround)Labor on: Fixture Set Labor2ea$0$1,100$1,100
Dishwasher Hookup Labor1ea1 to 3 h$185$0$185
DWV Install Labor22lf7 to 15 h$792$0$792
Expansion Tank AllowanceLabor on: Expansion Tank Service Labor1ea$0$75$75
Expansion Tank Service Labor1ea1 to 2 h$110$0$110
Faucet AllowanceLabor on: Fixture Set Labor1ea$0$225$225
Kitchen Sink AllowanceLabor on: Fixture Set Labor1ea$0$360$360
Lavatory Sink AllowanceLabor on: Fixture Set Labor2ea$0$450$450
Toilet AllowanceLabor on: Fixture Set Labor2ea$0$650$650
Fixture Set Labor7ea11 to 24 h$1,365$0$1,365
Hose Bib Fixture AllowanceLabor on: Fixture Set Labor2ea$0$76$76
Lavatory faucet allowanceLabor on: Fixture Set Labor2ea$0$400$400
DWV MaterialsLabor on: DWV Install Labor62.6lf$0$391$391
Plumbing Main Lines, New House (per sf)1600sf$0$0$6,800
Rough Plumbing ConsumablesLabor on: Plumbing Rough-In Per Fixture7ea$0$294$294
Plumbing Rough-In Per Fixture7ea18 to 38 h$2,800$0$2,800
Supply Pipe MaterialsLabor on: Supply Line Install Labor97.4lf$0$341$341
Sewer Cleanout Assembly AllowanceLabor on: Sewer Cleanout Install Labor1ea$0$95$95
Sewer Cleanout Install Labor1ea2 to 5 h$385$0$385
Shower valve trim allowanceLabor on: Shower/Tub Valve Set2ea$0$520$520
Shower/Tub Valve Set2ea4 to 10 h$650$0$650
Shower Valve Rough-In Body AllowanceLabor on: Shower/Tub Valve Set2ea$0$330$330
Shutoff Valve Install2ea1 to 2 h$116$0$116
Supply Line Install Labor43lf2 to 7 h$258$0$258
Alcove tub setting materialsLabor on: Fixture Set Labor2ea$0$130$130
Tub Waste and Overflow KitLabor on: Fixture Set Labor2ea$0$130$130
Washer Box Install Labor1ea1 to 3 h$230$0$230
Tank Water Heater AllowanceLabor on: Tank Water Heater Install1ea$0$750$750
Water Heater Connection KitLabor on: Tank Water Heater Install1ea$0$63$63
Tank Water Heater Install1ea1 to 4 h$297$0$297
Water Service Pipe Install Labor50lf2 to 6 h$212$0$212
Water Service Pipe MaterialsLabor on: Water Service Pipe Install Labor52.5lf$0$289$289
Water Service Pressure Test Labor1ea1 to 3 h$190$0$190
Water Service Trenching Labor50lf3 to 8 h$325$0$325
Plumbing subtotal79 to 105 h$21,384
Plumbing subtotal79 to 105 h$21,384
Electrical
Bath Fan Duct Install Labor16lf1 to 2 h$76$0$76
Bath Fan Duct MaterialsLabor on: Bath Fan Duct Install Labor18.4lf$0$51$51
Bath Fan Electrical Hookup Labor2each1 to 3 h$200$0$200
Bath Fan Termination Install Labor2each1 to 4 h$220$0$220
Bath Fan Termination MaterialsLabor on: Bath Fan Termination Install Labor2each$0$90$90
Bath Fan Housing Install Labor2each2 to 6 h$380$0$380
Bath Fan Testing & Commissioning2eachunder 1 h$60$0$60
Electrical Box ExtenderLabor on: Outlet Integration Labor2ea$0$7$7
Branch Circuit Install21ea43 to 91 h$5,670$0$5,670
New Branch Circuit (labor)2ea2 to 5 h$480$0$480
Dedicated Appliance Circuit1ea2 to 5 h$275$0$275
Dedicated Circuit Breaker AllowanceLabor on: Branch Circuit Install6ea$0$120$120
240V Outlet Install1ea1 to 4 h$235$0$235
Underground Electric Service Lateral (per lf)50lf$0$0$1,400
Electrical Box and Device MaterialsLabor on: Electrical Rough-In Per Device97ea$0$824$824
Electrical Rough ConsumablesLabor on: Electrical Rough-In Per Device28ea$0$182$182
Electrical Rough-In Per Device97ea37 to 79 h$4,074$0$4,074
Garage Door Opener (per opener)Labor on: Garage Door Opener Install Labor1ea$0$325$325
GFCI/AFCI Device Install6ea1 to 5 h$288$0$288
Gfci Unit AllowanceLabor on: GFCI/AFCI Device Install8ea$0$160$160
HVAC Condenser DisconnectLabor on: Air Source Heat Pump Install1ea$0$35$35
Light Fixture AllowanceLabor on: Light Fixture Install14ea$0$1,900$1,900
Light Fixture Install19ea10 to 22 h$1,615$0$1,615
Lighting Dimmer AllowanceLabor on: Outlet/Switch Install1ea$0$28$28
Meter Socket AllowanceLabor on: Service Meter and Riser Install1ea$0$150$150
NM Cable 10/3 (30 A, 240 V)Labor on: Branch Circuit Install184lf$0$340$340
Outlet Integration Labor1ea1 to 3 h$185$0$185
Outlet/Switch Install72ea11 to 25 h$2,160$0$2,160
Outlet Unit AllowanceLabor on: Outlet/Switch Install49ea$0$220$220
Recessed Can AllowanceLabor on: Recessed Light, New Work (open ceiling)23ea$0$874$874
Recessed Light, New Work (open ceiling)18ea7 to 16 h$936$0$936
Romex Wire MaterialsLabor on: Electrical Rough-In Per Device2899.6lf$0$2,320$2,320
Service Meter and Riser Install1ea4 to 10 h$1,200$0$1,200
Service Panel AllowanceLabor on: Service Panel Install Labor1ea$0$950$950
Service Panel Install Labor1ea5 to 13 h$1,450$0$1,450
Smoke / CO Detector AllowanceLabor on: Smoke/CO Detector Install5ea$0$275$275
Smoke/CO Detector Install5ea1 to 4 h$225$0$225
Switch Unit AllowanceLabor on: Outlet/Switch Install25ea$0$112$112
Temporary Power Service (per month)6month$0$0$990
Electrical subtotal181 to 248 h$31,082
Electrical subtotal181 to 248 h$31,082
HVAC
Appliance Vent Termination1ea1 to 3 h$195$0$195
Backup Strip Heat AllowanceLabor on: Backup Strip Heat Install Labor1ea$0$275$275
Backup Strip Heat Install Labor1ea1 to 4 h$225$0$225
Bathroom Exhaust Fan Unit AllowanceLabor on: Bath Fan Housing Install Labor2ea$0$430$430
Condensate Drain Install1ea1 to 3 h$150$0$150
Dryer Vent Install Labor10lf1 to 3 h$165$0$165
Ducted Heat Pump System Equipment (per system)Labor on: Air Source Heat Pump Install1ea$0$4,333$4,333
Ductwork Install295lf38 to 80 h$3,687$0$3,687
Ductwork MaterialsLabor on: Ductwork Install309.75lf$0$2,401$2,401
Air Source Heat Pump Install1ea14 to 31 h$2,850$0$2,850
HVAC Commissioning and Balance1ea1 to 5 h$340$0$340
HVAC Install Consumables1ea$0$285$285
HVAC Load Calculation Labor1ea2 to 6 h$340$0$340
Radiant Underslab Insulation Board (per sf)Labor on: Under-Slab Rigid Insulation Lay (per sf)352.8sf$0$635$635
Range hood exhaust duct install10lf1 to 4 h$95$0$95
Range hood exhaust duct materialsLabor on: Range hood exhaust duct install10lf$0$115$115
Refrigerant Line Set Install30lf1 to 4 h$255$0$255
Refrigerant Line MaterialsLabor on: Refrigerant Line Set Install34.5lf$0$293$293
Register Boot AllowanceLabor on: Ductwork Install17ea$0$544$544
Register and Grille Install17ea1 to 4 h$238$0$238
Return Duct Install Labor60lf2 to 6 h$330$0$330
Return Duct MaterialsLabor on: Return Duct Install Labor60lf$0$570$570
Standard Thermostat Install1ea1 to 2 h$90$0$90
Thermostat Unit AllowanceLabor on: Standard Thermostat Install1ea$0$200$200
HVAC subtotal87 to 133 h$19,041
HVAC subtotal87 to 133 h$19,041
Insulation
Air Sealing Package, New House1600sf$0$0$1,200
Attic Blown Insulation, Installed (per sf at R-49)1600sf$0$0$2,640
Bath Fan Air Sealing Labor2eachunder 1 h$56$0$56
Wall Batt Insulation, Installed (per sf)1077sf$0$0$1,131
Insulation subtotalunder 1 h$5,027
Insulation subtotalunder 1 h$5,027
Drywall
Drywall Finish Labor6118sf81 to 169 h$7,403$0$7,403
Drywall Hang Labor5920sf57 to 120 h$3,670$0$3,670
Drywall Sheets MaterialsLabor on: Drywall Hang Labor6512sf$0$4,884$4,884
Type X Drywall Hang, Fire-Rated (per sf)198sf2 to 6 h$178$0$178
Type X Fire-Rated Drywall Materials (per sf)Labor on: Type X Drywall Hang, Fire-Rated (per sf)217.8sf$0$148$148
Drywall subtotal164 to 272 h$16,283
Drywall subtotal164 to 272 h$16,283
Carpentry
Bathroom Accessory AllowanceLabor on: Bathroom Accessory Install Labor6ea$0$288$288
Bathroom Accessory Install Labor6ea1 to 4 h$168$0$168
Cabinet Fillers, End Panels and Toe KickLabor on: Cabinet Install Labor12lf$0$660$660
Cabinet Install Labor21lf11 to 24 h$1,102$0$1,102
Closet System Install32lf8 to 18 h$1,344$0$1,344
Door Lock Hardware AllowanceLabor on: Exterior Door Install2each$0$190$190
Door/Window Unit AllowanceLabor on: Exterior Door Install2ea$0$2,200$2,200
Engineered Beam Material AllowanceLabor on: Engineered Beam Install1ea$0$1,204$1,204
Exterior Door Install2ea4 to 10 h$1,000$0$1,000
Exterior Trim Install36lf1 to 4 h$153$0$153
Exterior Wall Framing MaterialsLabor on: Stud Wall Framing Install254.36lf$0$3,434$3,434
Fire-Rated Self-Closing Door Unit (each)Labor on: Interior Door Install1ea$0$475$475
Firestop at a Penetration (each)4ea1 to 3 h$96$0$96
Engineered Beam Install1ea5 to 12 h$1,204$0$1,204
Framing Fasteners and HardwareLabor on: Stud Wall Framing Install342lf$0$376$376
Sheathing Install4575sf35 to 75 h$5,032$0$5,032
Stud Wall Framing Install442.25lf57 to 120 h$4,422$0$4,422
Garage Door Install (per door)1ea6 to 14 h$595$0$595
Garage Door Opener Install Labor1ea2 to 5 h$165$0$165
Garage Door Unit (per door)Labor on: Garage Door Install (per door)1ea$0$1,980$1,980
Interior Door Hardware AllowanceLabor on: Interior Door Install12each$0$900$900
Interior Door Install12ea18 to 39 h$2,240$0$2,240
Interior Door Slab AllowanceLabor on: Interior Door Install11each$0$2,035$2,035
Door Threshold Transition Labor5each1 to 4 h$160$0$160
Microwave Install Labor1ea2 to 5 h$160$0$160
Partition Door Rough Opening9ea4 to 10 h$612$0$612
Porch Ceiling, Install Labor60sf2 to 5 h$285$0$285
Porch Ceiling MaterialLabor on: Porch Ceiling, Install Labor66sf$0$148$148
Porch Posts and Beam, Framing Labor12lf6 to 13 h$696$0$696
Porch Posts and Beam, MaterialsLabor on: Porch Posts and Beam, Framing Labor12lf$0$504$504
Roof Trusses and Roof Sheathing Materials (per roofing square)Labor on: Roof Truss Set and Brace (per roofing square)27.69square$0$13,430$13,430
Roof Truss Set and Brace (per roofing square)26.37square27 to 57 h$2,241$0$2,241
Base Shoe / Quarter Round Install23lfunder 1 h$31$0$31
Base Shoe / Quarter Round MaterialsLabor on: Base Shoe / Quarter Round Install25.3lf$0$32$32
Shower Curtain Rod AllowanceLabor on: Shower Curtain Rod Install Labor2ea$0$170$170
Shower Curtain Rod Install Labor2ea1 to 3 h$110$0$110
Soffit and Fascia Install216lf19 to 41 h$1,404$0$1,404
Stud Wall Framing MaterialsLabor on: Stud Wall Framing Install220lf$0$1,485$1,485
Baseboard and Casing Install729lf19 to 42 h$2,107$0$2,107
Trim MaterialsLabor on: Baseboard and Casing Install1175.9lf$0$3,069$3,069
Vanity Install Labor2ea6 to 14 h$850$0$850
Vanity Mirror Install (per unit)2ea1 to 3 h$130$0$130
Wall Sheathing MaterialsLabor on: Sheathing Install2131.8sf$0$2,025$2,025
Window Caulk & Flash MaterialsLabor on: Window Install15each$0$720$720
Window and Door Install ConsumablesLabor on: Exterior Door Install2ea$0$96$96
Window Exterior Trim MaterialsLabor on: Exterior Trim Install36lf$0$117$117
Window Install15ea20 to 43 h$2,925$0$2,925
Window Stool and Apron Stock (per window)Labor on: Window Stool and Apron Install15ea$0$600$600
Window Stool and Apron Install15ea6 to 14 h$661$0$661
Window Unit AllowanceLabor on: Window Install15each$0$4,500$4,500
Carpentry subtotal374 to 467 h$70,531
Carpentry subtotal374 to 467 h$70,531
Tile
Tile Grout Install Labor250sf5 to 12 h$438$0$438
Tile Grout MaterialsLabor on: Tile Grout Install Labor250sf$0$113$113
Bathroom Tile Install Labor250sf21 to 45 h$1,625$0$1,625
Bathroom Tile Material AllowanceLabor on: Bathroom Tile Install Labor143sf$0$644$644
Bath Tile Setting MaterialsLabor on: Bathroom Tile Install Labor275sf$0$234$234
Bathroom Tile Substrate MaterialsLabor on: Bathroom Tile Substrate Prep Labor250sf$0$373$373
Bathroom Tile Substrate Prep Labor250sf7 to 16 h$563$0$563
Tile Waterproofing Install Labor120sf2 to 7 h$270$0$270
Bath Tile Waterproofing MaterialsLabor on: Tile Waterproofing Install Labor120sf$0$234$234
Bathroom wall tile material allowanceLabor on: Bathroom Tile Install Labor132sf$0$858$858
Tile Grout Sealer26sfunder 1 h$12$0$12
Tile Material AllowanceLabor on: Wall Tile Install26sf$0$169$169
Tile Setting MaterialsLabor on: Wall Tile Install26sf$0$48$48
Wall Tile Install26sf2 to 6 h$247$0$247
Tile subtotal48 to 75 h$5,828
Tile subtotal48 to 75 h$5,828
Flooring
Carpet Material AllowanceLabor on: Carpet Install495sf$0$1,609$1,609
Floor Transition Install2ea1 to 3 h$80$0$80
Floor Transition MaterialsLabor on: Floor Transition Install7ea$0$245$245
Floor Underlayment Materials978sf$0$538$538
Carpet Install450sf4 to 10 h$360$0$360
Flooring Install ConsumablesLabor on: Carpet Install3ea$0$255$255
LVP/LVT Install978sf17 to 37 h$2,054$0$2,054
LVP/LVT Material AllowanceLabor on: LVP/LVT Install1075.8sf$0$3,496$3,496
Flooring subtotal26 to 47 h$8,637
Flooring subtotal26 to 47 h$8,637
Painting
Interior Ceiling Paint Apply Labor1600sf9 to 21 h$896$0$896
Interior Door Paint (per door)11ea9 to 19 h$716$0$716
Interior Paint Apply Labor4350sf21 to 45 h$2,436$0$2,436
Paint Masking Setup Labor4350sf1 to 2 h$43$0$43
Premium Paint AllowanceLabor on: Interior Paint Apply Labor44.21gallon$0$2,122$2,122
Paint Prep Labor4478sf8 to 17 h$403$0$403
Paint Primer Application Labor5639.25sf12 to 26 h$1,241$0$1,241
Paint and Primer MaterialsLabor on: Paint Primer Application Labor18.75gallon$0$600$600
Paint Sundries Materials1ls$0$150$150
Trim Caulk and Filler MaterialsLabor on: Trim Paint Apply Labor1193lf$0$262$262
Trim Paint Apply Labor1006lf24 to 51 h$1,851$0$1,851
Painting subtotal111 to 153 h$10,720
Painting subtotal111 to 153 h$10,720
Vanity & Fixtures
Cabinet Hardware (per piece)34ea$0$221$221
Cabinet Install Fasteners and ShimsLabor on: Cabinet Install Labor29lf$0$80$80
Cabinet Material AllowanceLabor on: Cabinet Install Labor21lf$0$7,560$7,560
Closet System AllowanceLabor on: Closet System Install35.2lf$0$3,168$3,168
Fixture Set MaterialsLabor on: Fixture Set Labor5ea$0$225$225
Stone Countertop Fabrication57.2sf$0$0$1,602
Stone Countertop Install57.2sf$0$0$1,258
Stone Countertop Material AllowanceLabor on: Vanity Install Labor57.2sf$0$2,949$2,949
Vanity Cabinet AllowanceLabor on: Vanity Install Labor8lf$0$2,280$2,280
Vanity Mirror or Medicine Cabinet (per unit)Labor on: Vanity Mirror Install (per unit)2ea$0$300$300
Vanity & Fixtures subtotal$19,643
Vanity & Fixtures subtotal$19,643
Appliances
Dishwasher Unit AllowanceLabor on: Dishwasher Hookup Labor1ea$0$850$850
Dryer Vent MaterialsLabor on: Dryer Vent Install Labor11lf$0$47$47
Dryer Vent Termination Allowance1ea$0$35$35
Microwave Unit AllowanceLabor on: Microwave Install Labor1ea$0$600$600
Range Set and Connect1ea1 to 2 h$85$0$85
Range Unit AllowanceLabor on: Range Set and Connect1ea$0$1,250$1,250
Refrigerator Install Labor1ea1 to 2 h$85$0$85
Refrigerator Unit AllowanceLabor on: Refrigerator Install Labor1ea$0$1,600$1,600
Washer Box AllowanceLabor on: Washer Box Install Labor1ea$0$65$65
Appliances subtotal1 to 3 h$4,617
Appliances subtotal1 to 3 h$4,617
Exterior
Exterior Caulking and Sealing Labor146.92lf3 to 7 h$213$0$213
House Wrap Install Labor2106sf10 to 23 h$758$0$758
House Wrap MaterialsLabor on: House Wrap Install Labor2316.6sf$0$973$973
Soffit and Fascia MaterialsLabor on: Soffit and Fascia Install237.6lf$0$2,020$2,020
Vinyl Siding Install Labor1727sf26 to 56 h$3,195$0$3,195
Vinyl Siding MaterialsLabor on: Vinyl Siding Install Labor1899.7sf$0$5,889$5,889
Exterior subtotal47 to 79 h$13,048
Exterior subtotal47 to 79 h$13,048
Specialty
Sewer Line Install50lf$0$0$4,250
Temporary Utilities Setup2ea$0$0$2,100
Utility Locate Service1ea$0$0$450
Specialty subtotal$6,800
Specialty subtotal$6,800
Cleanup & Disposal
Construction Dumpster, per Haul4ea$0$0$2,600
Final Construction Clean (per sf)2084sf$0$0$938
Rough Clean, per Phase3ea12 to 49 h$2,100$0$2,100
Cleanup & Disposal subtotal12 to 49 h$5,638
Cleanup & Disposal subtotal12 to 49 h$5,638
General
Generic Install Consumables4ls$0$340$340
General subtotal$340
General subtotal$340
Roofing
Asphalt Shingle Install Labor26.37square27 to 57 h$4,747$0$4,747
Asphalt Shingle MaterialsLabor on: Asphalt Shingle Install Labor29.01square$0$5,077$5,077
Downspout Install Labor4ea1 to 5 h$220$0$220
Downspout MaterialsLabor on: Downspout Install Labor4ea$0$220$220
Drip Edge MaterialsLabor on: Asphalt Shingle Install Labor215.68lf$0$205$205
Gutter Install Labor118lf6 to 13 h$531$0$531
Gutter MaterialsLabor on: Gutter Install Labor129.8lf$0$714$714
Ice Water Shield Install Labor3.96sq2 to 5 h$143$0$143
Ice Water Shield MaterialsLabor on: Ice Water Shield Install Labor3.96sq$0$376$376
Ridge Vent Install Labor61.62lf1 to 3 h$120$0$120
Ridge Vent MaterialsLabor on: Ridge Vent Install Labor61.62lf$0$262$262
Synthetic Underlayment Install Labor26.37square5 to 11 h$791$0$791
Synthetic Underlayment Materials27.69square$0$415$415
Roofing subtotal52 to 84 h$13,821
Roofing subtotal52 to 84 h$13,821
Landscaping
Compacted Gravel Base (per sf)720sf$0$612$612
Gravel Path Spread and Compact (per sf)720sf14 to 30 h$1,044$0$1,044
Gravel Path Surface (per sf)Labor on: Gravel Path Spread and Compact (per sf)720sf$0$756$756
Landscaping Allowance, New House1ea$0$3,000$3,000
Silt Fence Materials (per lf)Labor on: Silt Fence Install Labor294.8lf$0$251$251
Site Grading Labor4489sf5 to 13 h$988$0$988
Landscaping subtotal22 to 39 h$6,651
Landscaping subtotal22 to 39 h$6,651
DIRECT JOB COST1681 to 1992 h$289,326
DIRECT JOB COST1681 to 1992 h$289,326

D. 2,400 sf two-story: $452,741

Four bedrooms and three baths over a full unfinished basement, a three-car garage, an 8x18 porch, fiber cement siding, a semi-custom quartz kitchen and gas heat. Labor is $189,016 of the $452,741 job cost, or 41.7%. It is about 2965 to 3505 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Margin×1.25Mid-Range×1.30High-Margin×1.40
Sitework11 to 20 h$1,030$1,288$1,339$1,442
Masonry286 to 456 h$17,645$22,056$22,939$24,703
Plumbing115 to 151 h$11,863$14,829$15,422$16,608
Electrical250 to 342 h$26,752$33,440$34,778$37,453
HVAC134 to 202 h$11,783$14,729$15,318$16,496
Insulation18 to 37 h$1,316$1,645$1,711$1,843
Drywall245 to 406 h$16,884$21,105$21,949$23,638
Carpentry905 to 1094 h$71,011$88,764$92,314$99,415
Tile69 to 107 h$4,513$5,641$5,867$6,318
Flooring38 to 70 h$3,760$4,700$4,888$5,264
Painting162 to 223 h$11,128$13,910$14,466$15,579
Appliances1 to 3 h$170$212$221$238
Exterior22 to 43 h$1,468$1,835$1,908$2,055
Cleanup & Disposal12 to 49 h$2,100$2,625$2,730$2,940
Roofing52 to 84 h$6,600$8,250$8,580$9,240
Landscaping5 to 13 h$993$1,241$1,291$1,390
Setup, cleanup and material runs210 to 633 hin the prices
All labor2965 to 3505 h$189,016$236,270$245,721$264,622

Every line item

Labor $189,016 + materials and allowances $209,281 + dump fees and other $54,444 = $452,741 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Sitework
Construction Entrance, Stabilized Stone1ea$0$0$2,400
Silt Fence Install Labor269lf4 to 9 h$377$0$377
Excavation Equipment Rental1day$0$0$550
Two-Story Footing Upsize Labor145lf5 to 12 h$653$0$653
Foundation Excavation (Machine, Per Cubic Yard)461.91cubic_yard$0$0$7,391
Portable Toilet Rental (per month)7month$0$0$1,575
Site Survey and Building Staking (per project)1ea$0$0$1,200
Sitework subtotal11 to 20 h$14,146
Sitework subtotal11 to 20 h$14,146
Masonry
Concrete Flatwork Install Labor2160sf67 to 140 h$6,696$0$6,696
Concrete Flatwork MaterialsLabor on: Concrete Flatwork Install Labor2376sf$0$12,474$12,474
Concrete Footing Install Labor243lf37 to 79 h$2,552$0$2,552
Concrete Footing MaterialsLabor on: Concrete Footing Install Labor267.3lf$0$3,876$3,876
Foundation Dampproofing, Spray Applied1015sf$0$0$1,269
Foundation Pour Labor37.32cubic_yard135 to 283 h$8,397$0$8,397
Foundation Pour MaterialsLabor on: Foundation Pour Labor41.05cubic_yard$0$11,699$11,699
Stone Install Consumables1ea$0$135$135
Under-Slab Vapor Retarder (per sf)2016sf$0$0$1,109
Masonry subtotal286 to 456 h$48,207
Masonry subtotal286 to 456 h$48,207
Plumbing
Alcove tub (tub only, no surround)Labor on: Fixture Set Labor3ea$0$1,650$1,650
Appliance Vent Pipe MaterialsLabor on: Combustion Vent Install29.7lf$0$431$431
Dishwasher Hookup Labor1ea1 to 3 h$185$0$185
DWV Install Labor22lf7 to 15 h$792$0$792
Expansion Tank AllowanceLabor on: Expansion Tank Service Labor1ea$0$75$75
Expansion Tank Service Labor1ea1 to 2 h$110$0$110
Exterior Footing Drain (per lf)145lf$0$0$2,030
Faucet AllowanceLabor on: Fixture Set Labor1ea$0$225$225
Kitchen Sink AllowanceLabor on: Fixture Set Labor1ea$0$360$360
Lavatory Sink AllowanceLabor on: Fixture Set Labor3ea$0$675$675
Toilet AllowanceLabor on: Fixture Set Labor3ea$0$975$975
Fixture Set Labor9ea14 to 31 h$1,755$0$1,755
Gas Appliance Set and Connect2ea2 to 6 h$370$0$370
Gas Line Install Labor50lf5 to 12 h$700$0$700
Gas Line MaterialsLabor on: Gas Line Install Labor55lf$0$468$468
Gas Pressure Test Labor1ea1 to 2 h$135$0$135
Natural Gas Service Line (per lf)50lf$0$0$1,400
Hose Bib Fixture AllowanceLabor on: Fixture Set Labor2ea$0$76$76
Lavatory faucet allowanceLabor on: Fixture Set Labor3ea$0$600$600
DWV MaterialsLabor on: DWV Install Labor82.4lf$0$515$515
Plumbing Main Lines, New House (per sf)2400sf$0$0$10,200
Rough Plumbing ConsumablesLabor on: Plumbing Rough-In Per Fixture10ea$0$420$420
Plumbing Rough-In Per Fixture10ea26 to 54 h$4,000$0$4,000
Supply Pipe MaterialsLabor on: Supply Line Install Labor123.8lf$0$433$433
Sewer Cleanout Assembly AllowanceLabor on: Sewer Cleanout Install Labor1ea$0$95$95
Sewer Cleanout Install Labor1ea2 to 5 h$385$0$385
Shower valve trim allowanceLabor on: Shower/Tub Valve Set3ea$0$780$780
Shower/Tub Valve Set3ea6 to 15 h$975$0$975
Shower Valve Rough-In Body AllowanceLabor on: Shower/Tub Valve Set3ea$0$495$495
Shutoff Valve Install2ea1 to 2 h$116$0$116
Sump Crock, New Basement (before the slab)1ea1 to 3 h$325$0$325
Sump Discharge Line (per lf)20lf$0$0$280
Sump Pump Install1ea2 to 6 h$375$0$375
Sump Pump Unit AllowanceLabor on: Sump Pump Install1ea$0$280$280
Supply Line Install Labor43lf2 to 7 h$258$0$258
Alcove tub setting materialsLabor on: Fixture Set Labor3ea$0$195$195
Tub Waste and Overflow KitLabor on: Fixture Set Labor3ea$0$195$195
Washer Box Install Labor1ea1 to 3 h$230$0$230
Tank Water Heater AllowanceLabor on: Tank Water Heater Install1ea$0$750$750
Water Heater Connection KitLabor on: Tank Water Heater Install1ea$0$105$105
Tank Water Heater Install1ea2 to 6 h$425$0$425
Water Service Pipe Install Labor50lf2 to 6 h$212$0$212
Water Service Pipe MaterialsLabor on: Water Service Pipe Install Labor52.5lf$0$289$289
Water Service Pressure Test Labor1ea1 to 3 h$190$0$190
Water Service Trenching Labor50lf3 to 8 h$325$0$325
Plumbing subtotal115 to 151 h$35,860
Plumbing subtotal115 to 151 h$35,860
Electrical
Bath Fan Duct Install Labor24lf1 to 3 h$114$0$114
Bath Fan Duct MaterialsLabor on: Bath Fan Duct Install Labor27.6lf$0$76$76
Bath Fan Electrical Hookup Labor3each2 to 5 h$300$0$300
Bath Fan Termination Install Labor3each2 to 6 h$330$0$330
Bath Fan Termination MaterialsLabor on: Bath Fan Termination Install Labor3each$0$135$135
Bath Fan Housing Install Labor3each4 to 9 h$570$0$570
Bath Fan Testing & Commissioning3each1 to 2 h$90$0$90
Electrical Box ExtenderLabor on: Outlet Integration Labor2ea$0$7$7
Branch Circuit Install25ea52 to 108 h$6,750$0$6,750
New Branch Circuit (labor)3ea3 to 8 h$720$0$720
Dedicated Appliance Circuit1ea2 to 5 h$275$0$275
Dedicated Circuit Breaker AllowanceLabor on: Branch Circuit Install7ea$0$132$132
240V Outlet Install1ea1 to 4 h$235$0$235
Underground Electric Service Lateral (per lf)50lf$0$0$1,400
Electrical Box and Device MaterialsLabor on: Electrical Rough-In Per Device151ea$0$1,284$1,284
Electrical Rough ConsumablesLabor on: Electrical Rough-In Per Device35ea$0$228$228
Electrical Rough-In Per Device153ea59 to 124 h$6,426$0$6,426
Garage Door Opener (per opener)Labor on: Garage Door Opener Install Labor2ea$0$650$650
GFCI/AFCI Device Install6ea1 to 5 h$288$0$288
Gfci Unit AllowanceLabor on: GFCI/AFCI Device Install9ea$0$180$180
HVAC Condenser Disconnect1ea$0$35$35
Light Fixture AllowanceLabor on: Light Fixture Install23ea$0$2,550$2,550
Light Fixture Install31ea17 to 36 h$2,635$0$2,635
Lighting Dimmer AllowanceLabor on: Outlet/Switch Install1ea$0$28$28
Meter Socket AllowanceLabor on: Service Meter and Riser Install1ea$0$150$150
NM Cable 10/3 (30 A, 240 V)Labor on: Branch Circuit Install92lf$0$170$170
Outlet Integration Labor1ea1 to 3 h$185$0$185
Outlet/Switch Install114ea18 to 39 h$3,420$0$3,420
Outlet Unit AllowanceLabor on: Outlet/Switch Install80ea$0$360$360
Recessed Can AllowanceLabor on: Recessed Light, New Work (open ceiling)35ea$0$1,330$1,330
Recessed Light, New Work (open ceiling)27ea10 to 23 h$1,404$0$1,404
Romex Wire MaterialsLabor on: Electrical Rough-In Per Device4962.2lf$0$3,970$3,970
Service Meter and Riser Install1ea4 to 10 h$1,200$0$1,200
Service Panel AllowanceLabor on: Service Panel Install Labor1ea$0$950$950
Service Panel Install Labor1ea5 to 13 h$1,450$0$1,450
Smoke / CO Detector AllowanceLabor on: Smoke/CO Detector Install8ea$0$440$440
Smoke/CO Detector Install8ea2 to 6 h$360$0$360
Switch Unit AllowanceLabor on: Outlet/Switch Install37ea$0$166$166
Temporary Power Service (per month)7month$0$0$1,155
Electrical subtotal250 to 342 h$42,148
Electrical subtotal250 to 342 h$42,148
HVAC
AC Condenser Install1ea10 to 21 h$1,045$0$1,045
Air Handler Install1ea1 to 4 h$325$0$325
Appliance Vent Termination1ea1 to 3 h$195$0$195
Bathroom Exhaust Fan Unit AllowanceLabor on: Bath Fan Housing Install Labor3ea$0$645$645
Combustion Vent Install27lf7 to 15 h$864$0$864
Condensate Drain Install1ea1 to 3 h$150$0$150
Dryer Vent Install Labor10lf1 to 3 h$165$0$165
Ductwork Install452lf58 to 123 h$5,650$0$5,650
Ductwork MaterialsLabor on: Ductwork Install474.6lf$0$3,678$3,678
Evaporator Coil AllowanceLabor on: Air Handler Install1ea$0$800$800
Furnace Install Labor1ea13 to 28 h$1,479$0$1,479
HVAC Commissioning and Balance1ea1 to 5 h$340$0$340
HVAC Install Consumables1ea$0$285$285
HVAC Load Calculation Labor1ea2 to 6 h$340$0$340
Range hood exhaust duct install10lf1 to 4 h$95$0$95
Range hood exhaust duct materialsLabor on: Range hood exhaust duct install10lf$0$115$115
Refrigerant Line Set Install30lf1 to 4 h$255$0$255
Refrigerant Line MaterialsLabor on: Refrigerant Line Set Install34.5lf$0$293$293
Register Boot AllowanceLabor on: Ductwork Install27ea$0$864$864
Register and Grille Install27ea2 to 7 h$378$0$378
Return Duct Install Labor75lf3 to 7 h$412$0$412
Return Duct MaterialsLabor on: Return Duct Install Labor75lf$0$712$712
Standard Thermostat Install1ea1 to 2 h$90$0$90
Thermostat Unit AllowanceLabor on: Standard Thermostat Install1ea$0$200$200
HVAC subtotal134 to 202 h$19,375
HVAC subtotal134 to 202 h$19,375
Insulation
Air Sealing Package, New House2400sf$0$0$1,800
Attic Blown Insulation, Installed (per sf at R-49)1200sf$0$0$1,980
Bath Fan Air Sealing Labor3each1 to 2 h$84$0$84
Rim Joist Insulation Install (per lf)145lf16 to 36 h$1,232$0$1,232
Rim Joist Rigid Foam (per lf)Labor on: Rim Joist Insulation Install (per lf)145lf$0$232$232
Wall Batt Insulation, Installed (per sf)1948sf$0$0$2,045
Insulation subtotal18 to 37 h$7,373
Insulation subtotal18 to 37 h$7,373
Drywall
Drywall Finish Labor9137sf121 to 253 h$11,147$0$11,147
Drywall Hang Labor8880sf86 to 180 h$5,506$0$5,506
Drywall Sheets MaterialsLabor on: Drywall Hang Labor9768sf$0$7,326$7,326
Type X Drywall Hang, Fire-Rated (per sf)257sf3 to 7 h$231$0$231
Type X Fire-Rated Drywall Materials (per sf)Labor on: Type X Drywall Hang, Fire-Rated (per sf)282.7sf$0$192$192
Drywall subtotal245 to 406 h$24,402
Drywall subtotal245 to 406 h$24,402
Carpentry
Floor System Framing Labor2400sf78 to 162 h$8,400$0$8,400
Floor System Framing MaterialsLabor on: Floor System Framing Labor2520sf$0$11,340$11,340
Bathroom Accessory AllowanceLabor on: Bathroom Accessory Install Labor9ea$0$432$432
Bathroom Accessory Install Labor9ea2 to 5 h$252$0$252
Cabinet Fillers, End Panels and Toe KickLabor on: Cabinet Install Labor12lf$0$660$660
Cabinet Install Labor26lf14 to 30 h$1,365$0$1,365
Closet System Install40lf10 to 22 h$1,680$0$1,680
Door Lock Hardware AllowanceLabor on: Exterior Door Install2each$0$190$190
Door/Window Unit AllowanceLabor on: Exterior Door Install2ea$0$2,200$2,200
Engineered Beam Material AllowanceLabor on: Engineered Beam Install2ea$0$1,913$1,913
Exterior Door Install2ea4 to 10 h$1,000$0$1,000
Exterior Trim Install745.25lf33 to 70 h$3,167$0$3,167
Exterior Wall Framing MaterialsLabor on: Stud Wall Framing Install406.09lf$0$5,482$5,482
Fiber Cement Siding Install Labor2837sf88 to 184 h$9,646$0$9,646
Fire-Rated Self-Closing Door Unit (each)Labor on: Interior Door Install1ea$0$475$475
Firestop at a Penetration (each)4ea1 to 3 h$96$0$96
Engineered Beam Install2ea8 to 19 h$1,913$0$1,913
Framing Fasteners and HardwareLabor on: Stud Wall Framing Install510lf$0$561$561
Header Installation4ea13 to 27 h$640$0$640
Sheathing Install5896sf45 to 96 h$6,486$0$6,486
Stud Wall Framing Install686.75lf89 to 186 h$6,868$0$6,868
Garage Door Install (per door)2ea10 to 23 h$1,020$0$1,020
Garage Door Opener Install Labor2ea4 to 10 h$330$0$330
Garage Door Unit (per door)Labor on: Garage Door Install (per door)2ea$0$3,080$3,080
Interior Door Hardware AllowanceLabor on: Interior Door Install15each$0$1,125$1,125
Interior Door Install15ea23 to 49 h$2,791$0$2,791
Interior Door Slab AllowanceLabor on: Interior Door Install14each$0$2,590$2,590
Door Threshold Transition Labor7each2 to 5 h$224$0$224
Microwave Install Labor1ea2 to 5 h$160$0$160
Partition Door Rough Opening13ea6 to 14 h$884$0$884
Porch Ceiling, Install Labor144sf4 to 11 h$684$0$684
Porch Ceiling MaterialLabor on: Porch Ceiling, Install Labor158.4sf$0$356$356
Porch Posts and Beam, Framing Labor19lf9 to 21 h$1,102$0$1,102
Porch Posts and Beam, MaterialsLabor on: Porch Posts and Beam, Framing Labor19lf$0$798$798
Roof Trusses and Roof Sheathing Materials (per roofing square)Labor on: Roof Truss Set and Brace (per roofing square)27.9square$0$13,531$13,531
Roof Truss Set and Brace (per roofing square)26.57square27 to 58 h$2,258$0$2,258
Base Shoe / Quarter Round Install30lfunder 1 h$40$0$40
Base Shoe / Quarter Round MaterialsLabor on: Base Shoe / Quarter Round Install33lf$0$41$41
Shower Curtain Rod AllowanceLabor on: Shower Curtain Rod Install Labor3ea$0$255$255
Shower Curtain Rod Install Labor3ea1 to 4 h$165$0$165
Soffit and Fascia Install216lf19 to 41 h$1,404$0$1,404
Balustrade Material AllowanceLabor on: Balustrade Install Labor24lf$0$432$432
Balustrade Install Labor24lf11 to 25 h$912$0$912
Stair Finish System Labor2each14 to 30 h$3,600$0$3,600
Stair Finish System MaterialsLabor on: Stair Finish System Labor2each$0$330$330
Handrail Material AllowanceLabor on: Handrail Install Labor24lf$0$504$504
Handrail Install Labor24lf6 to 13 h$528$0$528
Newel Post Material AllowanceLabor on: Newel Post Install Labor2each$0$370$370
Newel Post Install Labor2each3 to 7 h$400$0$400
Stair Riser Install Labor29each7 to 16 h$725$0$725
Stair Riser Material AllowanceLabor on: Stair Riser Install Labor29each$0$348$348
Stair Stringer Fabrication6ea5 to 13 h$630$0$630
Stair Stringer MaterialsLabor on: Stair Stringer Fabrication6each$0$510$510
Stair Tread Install Labor27each17 to 37 h$1,755$0$1,755
Stair Tread Material AllowanceLabor on: Stair Tread Install Labor27each$0$890$890
Stud Wall Framing MaterialsLabor on: Stud Wall Framing Install330lf$0$2,227$2,227
Baseboard and Casing Install1092lf29 to 62 h$3,156$0$3,156
Trim MaterialsLabor on: Baseboard and Casing Install1677.2lf$0$4,428$4,428
Vanity Install Labor3ea9 to 21 h$1,275$0$1,275
Vanity Mirror Install (per unit)3ea1 to 4 h$195$0$195
Wall Sheathing MaterialsLabor on: Sheathing Install3562.9sf$0$3,385$3,385
Window Caulk & Flash MaterialsLabor on: Window Install22each$0$1,056$1,056
Window and Door Install ConsumablesLabor on: Exterior Door Install2ea$0$96$96
Window Exterior Trim MaterialsLabor on: Exterior Trim Install36lf$0$117$117
Window Install22ea29 to 62 h$4,290$0$4,290
Window Stool and Apron Stock (per window)Labor on: Window Stool and Apron Install22ea$0$880$880
Window Stool and Apron Install22ea9 to 20 h$970$0$970
Window Unit AllowanceLabor on: Window Install22each$0$6,600$6,600
Carpentry subtotal905 to 1094 h$138,213
Carpentry subtotal905 to 1094 h$138,213
Tile
Tile Grout Install Labor360sf7 to 17 h$630$0$630
Tile Grout MaterialsLabor on: Tile Grout Install Labor360sf$0$162$162
Bathroom Tile Install Labor360sf31 to 65 h$2,340$0$2,340
Bathroom Tile Material AllowanceLabor on: Bathroom Tile Install Labor198sf$0$891$891
Bath Tile Setting MaterialsLabor on: Bathroom Tile Install Labor396sf$0$337$337
Bathroom Tile Substrate MaterialsLabor on: Bathroom Tile Substrate Prep Labor360sf$0$536$536
Bathroom Tile Substrate Prep Labor360sf10 to 22 h$810$0$810
Tile Waterproofing Install Labor180sf4 to 10 h$405$0$405
Bath Tile Waterproofing MaterialsLabor on: Tile Waterproofing Install Labor180sf$0$351$351
Bathroom wall tile material allowanceLabor on: Bathroom Tile Install Labor198sf$0$1,287$1,287
Tile Grout Sealer33sfunder 1 h$15$0$15
Tile Material AllowanceLabor on: Wall Tile Install33sf$0$214$214
Tile Setting MaterialsLabor on: Wall Tile Install33sf$0$61$61
Wall Tile Install33sf3 to 7 h$313$0$313
Tile subtotal69 to 107 h$8,352
Tile subtotal69 to 107 h$8,352
Flooring
Carpet Material AllowanceLabor on: Carpet Install739.2sf$0$2,402$2,402
Floor Transition Install2ea1 to 3 h$80$0$80
Floor Transition MaterialsLabor on: Floor Transition Install9ea$0$315$315
Floor Underlayment Materials1496sf$0$823$823
Carpet Install672sf6 to 15 h$538$0$538
Flooring Install ConsumablesLabor on: Carpet Install3ea$0$255$255
LVP/LVT Install1496sf27 to 57 h$3,142$0$3,142
LVP/LVT Material AllowanceLabor on: LVP/LVT Install1645.6sf$0$5,348$5,348
Flooring subtotal38 to 70 h$12,903
Flooring subtotal38 to 70 h$12,903
Painting
Interior Ceiling Paint Apply Labor2400sf14 to 31 h$1,344$0$1,344
Interior Door Paint (per door)14ea11 to 24 h$911$0$911
Interior Paint Apply Labor6510sf32 to 67 h$3,646$0$3,646
Paint Masking Setup Labor6510sf1 to 2 h$65$0$65
Premium Paint AllowanceLabor on: Interior Paint Apply Labor65.24gallon$0$3,132$3,132
Paint Prep Labor6702sf11 to 25 h$603$0$603
Paint Primer Application Labor8496.15sf18 to 39 h$1,869$0$1,869
Paint and Primer MaterialsLabor on: Paint Primer Application Labor28.25gallon$0$904$904
Paint Sundries Materials1ls$0$150$150
Trim Caulk and Filler MaterialsLabor on: Trim Paint Apply Labor1700lf$0$374$374
Trim Paint Apply Labor1462lf35 to 74 h$2,690$0$2,690
Painting subtotal162 to 223 h$15,688
Painting subtotal162 to 223 h$15,688
Vanity & Fixtures
Cabinet Hardware (per piece)42ea$0$273$273
Cabinet Install Fasteners and ShimsLabor on: Cabinet Install Labor37lf$0$102$102
Cabinet Material AllowanceLabor on: Cabinet Install Labor26lf$0$9,360$9,360
Closet System AllowanceLabor on: Closet System Install44lf$0$3,960$3,960
Fixture Set MaterialsLabor on: Fixture Set Labor7ea$0$315$315
Laminate Countertop (per sf)Labor on: Vanity Install Labor20.9sf$0$418$418
Stone Countertop Fabrication52sf$0$0$1,456
Stone Countertop Install52sf$0$0$1,144
Stone Countertop Material AllowanceLabor on: Vanity Install Labor52sf$0$2,860$2,860
Vanity Cabinet AllowanceLabor on: Vanity Install Labor11lf$0$3,135$3,135
Vanity Mirror or Medicine Cabinet (per unit)Labor on: Vanity Mirror Install (per unit)3ea$0$450$450
Vanity & Fixtures subtotal$23,473
Vanity & Fixtures subtotal$23,473
Appliances
Dishwasher Unit AllowanceLabor on: Dishwasher Hookup Labor1ea$0$850$850
Dryer Vent MaterialsLabor on: Dryer Vent Install Labor11lf$0$47$47
Dryer Vent Termination Allowance1ea$0$35$35
Microwave Unit AllowanceLabor on: Microwave Install Labor1ea$0$600$600
Range Set and Connect1ea1 to 2 h$85$0$85
Range Unit AllowanceLabor on: Range Set and Connect1ea$0$1,250$1,250
Refrigerator Install Labor1ea1 to 2 h$85$0$85
Refrigerator Unit AllowanceLabor on: Refrigerator Install Labor1ea$0$1,600$1,600
Washer Box AllowanceLabor on: Washer Box Install Labor1ea$0$65$65
Appliances subtotal1 to 3 h$4,617
Appliances subtotal1 to 3 h$4,617
Exterior
Exterior Caulking and Sealing Labor172.48lf3 to 8 h$250$0$250
Exterior Trim Materials, Fiber CementLabor on: Exterior Trim Install780.18lf$0$2,536$2,536
Fiber Cement Siding Material AllowanceLabor on: Fiber Cement Siding Install Labor3120.7sf$0$10,298$10,298
House Wrap Install Labor3384sf17 to 37 h$1,218$0$1,218
House Wrap MaterialsLabor on: House Wrap Install Labor3722.4sf$0$1,563$1,563
Siding Staging Rental3.78week$0$0$3,213
Soffit and Fascia MaterialsLabor on: Soffit and Fascia Install237.6lf$0$2,020$2,020
Exterior subtotal22 to 43 h$21,098
Exterior subtotal22 to 43 h$21,098
Specialty
Sewer Line Install50lf$0$0$4,250
Temporary Utilities Setup2ea$0$0$2,100
Utility Locate Service1ea$0$0$450
Specialty subtotal$6,800
Specialty subtotal$6,800
Cleanup & Disposal
Construction Dumpster, per Haul4ea$0$0$2,600
Final Construction Clean (per sf)3216sf$0$0$1,447
Rough Clean, per Phase3ea12 to 49 h$2,100$0$2,100
Cleanup & Disposal subtotal12 to 49 h$6,147
Cleanup & Disposal subtotal12 to 49 h$6,147
General
Generic Install Consumables5ls$0$425$425
General subtotal$425
General subtotal$425
Equipment
AC Condenser AllowanceLabor on: AC Condenser Install1ea$0$2,933$2,933
Furnace Unit AllowanceLabor on: Furnace Install Labor1ea$0$2,415$2,415
Equipment subtotal$5,348
Equipment subtotal$5,348
Roofing
Asphalt Shingle Install Labor26.57square27 to 58 h$4,783$0$4,783
Asphalt Shingle MaterialsLabor on: Asphalt Shingle Install Labor29.23square$0$5,115$5,115
Downspout Install Labor4ea1 to 5 h$220$0$220
Downspout MaterialsLabor on: Downspout Install Labor4ea$0$220$220
Drip Edge MaterialsLabor on: Asphalt Shingle Install Labor216.49lf$0$206$206
Gutter Install Labor119lf6 to 13 h$535$0$535
Gutter MaterialsLabor on: Gutter Install Labor130.9lf$0$720$720
Ice Water Shield Install Labor3.99sq2 to 5 h$144$0$144
Ice Water Shield MaterialsLabor on: Ice Water Shield Install Labor3.99sq$0$379$379
Ridge Vent Install Labor61.86lf1 to 3 h$121$0$121
Ridge Vent MaterialsLabor on: Ridge Vent Install Labor61.86lf$0$263$263
Synthetic Underlayment Install Labor26.57square5 to 11 h$797$0$797
Synthetic Underlayment Materials27.9square$0$418$418
Roofing subtotal52 to 84 h$13,921
Roofing subtotal52 to 84 h$13,921
Landscaping
Landscaping Allowance, New House1ea$0$3,000$3,000
Silt Fence Materials (per lf)Labor on: Silt Fence Install Labor295.9lf$0$252$252
Site Grading Labor4512sf5 to 13 h$993$0$993
Landscaping subtotal5 to 13 h$4,245
Landscaping subtotal5 to 13 h$4,245
DIRECT JOB COST2965 to 3505 h$452,741
DIRECT JOB COST2965 to 3505 h$452,741

Methodology & reproducibility

4 snapshots, one per build. Each build is frozen from its own estimate run with the same old work, system type and takeoff pinned, so the builds differ only in what is being built.

Direct cost equals the sum of each row’s rounded quantity × (labor + material + other). Amounts are shown in whole dollars; every column adds to its total.

Scope selection, prose accuracy, arithmetic and provenance mapping reviewed; not independent market-rate verification.

Questions

How much does it cost to build a house in 2026?

In these four builds, direct job cost runs from $191,610 for a 1,050 sf two-bedroom cottage to $452,741 for a 2,400 sf four-bedroom two-story over a full unfinished basement. That is about $175 to $189 per finished square foot before land, permits and the builder's markup.

What is the cost per square foot?

About $182 for the 1,050 sf cottage, $175 for the 1,500 sf ranch, $181 for the 1,600 sf ranch and $189 for the 2,400 sf two-story, computed from each build's direct job cost over its finished area. Small houses carry the kitchen, baths and mechanicals over fewer feet, which is why the cottage is not the cheapest per foot.

What is the difference between the 1,500 and 1,600 sf ranches?

$27,451, which is one finish tier plus 100 feet and the site items. The 1,500 sf build is a builder-grade spec: LVP everywhere, fiberglass tub showers, cover over the front door only, and no driveway was stated or priced. The 1,600 sf build is mid grade: tiled and waterproofed baths, carpeted bedrooms, mid-grade windows, a 6x10 covered porch and a 60 foot gravel driveway.

Why is the two-story the most expensive per square foot?

The 2,400 sf build carries a full unfinished basement, a three-car garage, a third bath, fiber cement siding and a gas furnace, water heater and service line. Those add cost without adding finished feet.

What markup do builders actually use?

Lower than remodelers. NAHB's average builder ran a 20.7% gross margin with 8.7% net profit in its latest study, and Markup & Profit's published new-home range is 21 to 29% plus gross margin. Those convert to markups of about 26% to 41% on job cost, which is why this page illustrates 25% to 40% instead of remodeling markups.

What do these numbers leave out?

The lot, financing, permit, impact and tap fees, builder's risk insurance, a warranty reserve, and the builder's overhead and profit. Direct job cost is what the work costs to perform; the markup table shows illustrative selling prices.

How much of a new house is labor?

Labor runs $81,167 on the cottage, $106,610 on the 1,500 sf ranch, $113,607 on the 1,600 sf ranch and $189,016 on the two-story, with subcontract and materials priced on their own lines.

Related

Sources & provenance

  1. Builders' Profit Margins Improved in 2023 (Cost of Doing Business Study, 2025 Edition) National Association of Home Builders (research)
  2. Markup & Profit: A Contractor's Guide, Revisited Michael C. Stone (book)
  3. 1,050 sf cottage reviewed snapshot Clamp Research
  4. 1,500 sf spec ranch, builder grade reviewed snapshot Clamp Research
  5. 1,600 sf ranch, mid grade reviewed snapshot Clamp Research
  6. 2,400 sf two-story reviewed snapshot Clamp Research
Changes: Oct 11, 2026: Initial publication: reviewed snapshots frozen from saved estimate runs, priced on the current baseline.; Oct 11, 2026: Markup illustrations changed to builder markups of 25% to 40%, from NAHB and Markup & Profit new-home margins.; Oct 11, 2026: Builder-grade vs mid-grade labels on the two ranches, with the difference itemized; line items open with trade subtotals and hours.