Project cost · modeled example

Cost to Finish an 800 Sq Ft Basement, Itemized (2026 Baseline)

800 square feet of unfinished basement framed, insulated, wired, drywalled and floored, with one bedroom wall and no bathroom, itemized with crew hours.

Direct answer: Finishing 800 square feet of basement with one bedroom and no bathroom has a direct job cost of $38,044 for this basement in this example. At illustrative markups of 30% to 100%, that is a selling price of about $49,457 to $76,088. Direct job cost is labor and materials only, with no contractor overhead or profit, and is not a price: no contractor performs work at job cost. Permit and inspection fees are not included.
Clamp's Generate from description screen with the 800 sq ft basement finish described in plain words

Describe it

The estimate for the 800 sq ft basement finish in Clamp's builder: total $38,032.13, grouped into carpentry, drywall, electrical and the other trades

Every line, by trade

The basement finish in the Clamp app: described in plain words, then the draft at $38,032 job cost, every line grouped by trade. Sample data.

The job at a glance

One build, fully itemized, with crew hours.

BuildJob costLaborCrew hoursMaterialsIllustrative selling price
A. 800 sq ft, no bathroom$38,044$23,076336 to 417 h$11,218$49,457 to
$76,088

Dump fees and other costs ($3,750) are the same in every build and included in the job cost. Materials include allowances. Illustrative selling price is the job cost at a 30% to 100% markup; your price depends on your own overhead and profit. Labor hours are a planning range and include setup, daily cleanup and material runs; they are never a charge to the customer. Permit and inspection fees are not included; requirements vary by jurisdiction.

The build in detail

A. 800 sq ft, no bathroom: $38,044

Rigid foam goes on the poured walls and rim joist; 110 feet of exterior wall and a 20-foot bedroom wall are framed, with soffits around the ducts; three heat runs are extended; new circuits, 13 recessed lights, outlets and switches go in; walls and ceiling are drywalled and painted; LVP goes down throughout with two doors and trim. Labor is $23,076 of the $38,044 job cost, or 60.7%. It is about 336 to 417 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Overhead×1.30Established×1.50Full-Service×2.00
Permits & PM11 to 17 h$850$1,105$1,275$1,700
Demo & Prep2 to 6 h$340$442$510$680
Electrical29 to 44 h$4,950$6,435$7,425$9,900
HVAC11 to 23 h$1,091$1,418$1,637$2,182
Insulation14 to 30 h$935$1,216$1,403$1,870
Drywall68 to 117 h$4,585$5,961$6,877$9,170
Carpentry44 to 67 h$4,988$6,484$7,482$9,976
Flooring20 to 44 h$1,800$2,340$2,700$3,600
Painting45 to 63 h$3,537$4,598$5,305$7,074
Setup, cleanup and material runs24 to 74 hin the prices
All labor336 to 417 h$23,076$29,999$34,614$46,152

Every line item

Labor $23,076 + materials and allowances $11,218 + dump fees and other $3,750 = $38,044 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Permits & PM
Layout & Design Labor4hr2 to 6 h$260$0$260
Final Cleanup & Walkthrough1ea3 to 9 h$300$0$300
Final Punch Walk Labor1ea2 to 6 h$290$0$290
Permits & PM subtotal11 to 17 h$850
Permits & PM subtotal11 to 17 h$850
Demo & Prep
Haul-Off Per Load2ea$0$0$450
Floor Protection Setup Labor800sfunder 1 h$40$0$40
Site Protection, One Room (per job)1ea2 to 5 h$300$0$300
Demo & Prep subtotal2 to 6 h$790
Demo & Prep subtotal2 to 6 h$790
Electrical
New Branch Circuit (labor)5ea9 to 21 h$2,125$0$2,125
Dedicated Circuit Breaker AllowanceLabor on: New Branch Circuit (labor)5ea$0$313$313
Electrical Box and Device MaterialsLabor on: Electrical Rough-In Per Device16ea$0$136$136
Electrical Rough-In Per Device8ea3 to 7 h$440$0$440
Add Outlet or Switch Box (rough-in)4ea3 to 7 h$740$0$740
Outlet/Switch Install7ea1 to 4 h$455$0$455
Outlet Unit AllowanceLabor on: Outlet/Switch Install12ea$0$58$58
Recessed Can AllowanceLabor on: Recessed Light, New Work (open ceiling)13ea$0$494$494
Recessed Light, New Work (open ceiling)13ea5 to 11 h$1,105$0$1,105
Romex Wire MaterialsLabor on: Electrical Rough-In Per Device362.25lf$0$290$290
Smoke / CO Detector AllowanceLabor on: Smoke/CO Detector Install1ea$0$55$55
Smoke/CO Detector Install1eaunder 1 h$85$0$85
Switch Unit AllowanceLabor on: Outlet/Switch Install4ea$0$8$8
Electrical subtotal29 to 44 h$6,304
Electrical subtotal29 to 44 h$6,304
HVAC
Ductwork Install75lf9 to 21 h$863$0$863
Ductwork MaterialsLabor on: Ductwork Install75lf$0$581$581
Register Boot AllowanceLabor on: Ductwork Install5ea$0$175$175
Register and Grille Install5eaunder 1 h$100$0$100
Return Duct Install Labor15lf1 to 2 h$128$0$128
Return Duct MaterialsLabor on: Return Duct Install Labor15lf$0$143$143
HVAC subtotal11 to 23 h$1,990
HVAC subtotal11 to 23 h$1,990
Insulation
Rigid Foam on Masonry Wall, Installed (per sf)880sf$0$0$3,300
Rim Joist Insulation Install (per lf)110lf14 to 30 h$935$0$935
Rim Joist Rigid Foam (per lf)Labor on: Rim Joist Insulation Install (per lf)110lf$0$176$176
Insulation subtotal14 to 30 h$4,411
Insulation subtotal14 to 30 h$4,411
Drywall
Drywall Access Patch (per opening)1eaunder 1 h$85$0$85
Drywall Finish Labor2000sf38 to 81 h$3,000$0$3,000
Drywall Hang Labor2000sf20 to 44 h$1,500$0$1,500
Drywall Sheets MaterialsLabor on: Drywall Hang Labor2200sf$0$1,650$1,650
Drywall subtotal68 to 117 h$6,235
Drywall subtotal68 to 117 h$6,235
Carpentry
Framing Fasteners and HardwareLabor on: Stud Wall Framing Install30lf$0$33$33
Stud Wall Framing Install130lf16 to 36 h$2,145$0$2,145
Interior Door Hardware AllowanceLabor on: Interior Door Install2each$0$170$170
Interior Door Install2ea2 to 7 h$450$0$450
Interior Door Slab AllowanceLabor on: Interior Door Install2each$0$165$165
Door Threshold Transition Labor1eachunder 1 h$75$0$75
Partition Door Rough Opening2ea1 to 3 h$210$0$210
Soffit / Bulkhead Framing and Drywall Labor40lf7 to 17 h$960$0$960
Soffit / Bulkhead MaterialsLabor on: Soffit / Bulkhead Framing and Drywall Labor40lf$0$340$340
Stud Wall Framing MaterialsLabor on: Stud Wall Framing Install143lf$0$965$965
Baseboard and Casing Install270lf7 to 15 h$1,148$0$1,148
Trim MaterialsLabor on: Baseboard and Casing Install365lf$0$766$766
Carpentry subtotal44 to 67 h$7,427
Carpentry subtotal44 to 67 h$7,427
Flooring
Floor Transition MaterialsLabor on: Door Threshold Transition Labor1ea$0$35$35
Floor Underlayment Materials800sf$0$440$440
Flooring Install Consumables1ea$0$85$85
LVP/LVT Install800sf20 to 44 h$1,800$0$1,800
LVP/LVT Material AllowanceLabor on: LVP/LVT Install880sf$0$3,080$3,080
Flooring subtotal20 to 44 h$5,440
Flooring subtotal20 to 44 h$5,440
Painting
Interior Ceiling Paint Apply Labor800sf5 to 13 h$768$0$768
Interior Door Paint (per door)2ea1 to 4 h$210$0$210
Interior Paint Apply Labor1200sf10 to 22 h$864$0$864
Paint Masking Setup Labor1200sfunder 1 h$48$0$48
Premium Paint AllowanceLabor on: Interior Paint Apply Labor13.42gallon$0$644$644
Paint Prep Labor2000sf6 to 14 h$440$0$440
Paint Primer Application Labor2000sf4 to 9 h$600$0$600
Paint and Primer MaterialsLabor on: Paint Primer Application Labor6gallon$0$192$192
Paint Sundries Materials1ls$0$150$150
Trim Caulk and Filler MaterialsLabor on: Trim Paint Apply Labor338lf$0$74$74
Trim Paint Apply Labor270lf6 to 13 h$607$0$607
Painting subtotal45 to 63 h$4,597
Painting subtotal45 to 63 h$4,597
DIRECT JOB COST336 to 417 h$38,044
DIRECT JOB COST336 to 417 h$38,044

Methodology & reproducibility

One reviewed snapshot for this build. The build is frozen from its own estimate run and priced by the published pricer.

Direct cost equals the sum of each row’s rounded quantity × (labor + material + other). Amounts are shown in whole dollars; every column adds to its total.

Scope selection, prose accuracy, arithmetic and provenance mapping reviewed; not independent market-rate verification.

Questions

Why does this cost more per square foot than the ads say?

A basement finish is mostly wall and ceiling surface, not floor. 800 square feet of floor here means about 2,000 square feet of drywall to hang, finish and paint, plus framing, insulation and electrical. Per-square-foot ads usually assume less of each.

What would a bathroom add?

A full bathroom is its own scope: a drain trench or ejector, a shower, vanity and toilet, ventilation and tile. It is excluded here and usually adds a five-figure amount by itself.

Is the markup on top of this?

Yes. Direct job cost is what the finish costs a contractor to perform. The markup table shows what it sells for at illustrative markups of 30% to 100%.

Related

Sources & provenance

  1. 800 sq ft, no bathroom reviewed snapshot Clamp Research
Changes: Oct 12, 2026: Initial publication: reviewed snapshot frozen from a fresh estimate run, priced on the current baseline.; Oct 12, 2026: Added the app screenshot pair: the job described, then the draft by trade.