How Long to Install a Floor (2026): Hours and Days for Carpet, LVP, Hardwood, Tile and Concrete
One 300 sq ft room worked in nine floor types, from 12 person-hours for carpet to 60 for tile, plus the acclimation, cure and finish waits that decide when you get the room back.
The assumptions
This model assumes
- A 15x20 living room, 300 sq ft, old carpet coming out
- A sound, flat wood subfloor unless noted; an existing slab for polished concrete
- Person-hours for one installer; calendar days for a crew of two
- Prefinished hardwood unless the step says site-finished
- Planning allowances to check against your own logged hours
The model, step by step
A 15x20 living room, 300 sq ft, with old carpet coming up. Some work is the same whatever goes down.
Shared work, person-hours
Tear out carpet and pad3.0 h
Move furniture out and back2.0 h
Transitions at two doorways1.0 h
Baseboard off and back, 70 ft3.9 h, for hard floors
Underlayment1.2 h, for floating floors
Typical open-room rates for one installer, setting only.
| Floor | h per sq ft | Hours |
|---|---|---|
| Carpet | 0.015 | 4.5 |
| Laminate | 0.022 | 6.6 |
| Click LVP | 0.024 | 7.2 |
| Engineered, floating | 0.024 | 7.2 |
| Solid hardwood, prefinished | 0.032 | 9.6 |
| Sheet vinyl | 0.03 | 9.0 |
| Linoleum, sheet | 0.07 | 21.0 |
| Porcelain tile | 0.095 | 28.5 |
Install plus the shared work, plus 15% for setup, cleanup and material runs. Tile adds a backer or membrane, at Clamp's catalog rate.
| Floor | Typical | Range |
|---|---|---|
| Carpet | 12 | 7 to 17 |
| Laminate | 20 | 13 to 27 |
| Click LVP | 20 | 13 to 27 |
| Engineered, floating | 21 | 14 to 29 |
| Solid hardwood, prefinished | 24 | 15 to 34 |
| Sheet vinyl | 22 | 14 to 29 |
| Linoleum, sheet | 35 | 24 to 50 |
| Porcelain tile | 60 | 42 to 86 |
| Polished concrete | 26 | 19 to 33 |
Homeowners ask how long the room is out. That's set as much by waiting as by work.
| Floor | Usable |
|---|---|
| CarpetBefore: at least 24 h at 65 to 95 F | Same day |
| LaminateBefore: 48 to 96 h acclimation | Day 1 or 2 |
| Click LVPBefore: none to 48 h, per the brand | Day 1 or 2 |
| Prefinished hardwoodBefore: until its moisture matches the subfloor | Day 2 |
| Site-finished hardwoodFurniture 3 days after the last coat | About day 7 |
| Sheet vinylRolling loads wait for the adhesive | Day 2 |
| LinoleumBefore: 48 h; heavy loads wait 72 h | Day 4 |
| TileGrout the next day; heavy furniture later | Day 4 to 6 |
| Polished concreteWalk an hour after the guard; furniture next day | Day 3 |
The wait people miss most is before the work starts.
Hardwood
RuleNo fixed days. The wood is ready when its moisture is within the maker's range of the subfloor.
ExampleMohawk solid: at least 72 hours
Laminate and vinyl
LaminatePergo: 48 to 96 hours
Rigid LVPCOREtec: not required at 55 to 85 F
Concrete slabs
TestA probe test needs 24 hours to read, so two trips. A failed test can stop the job.
New slabMany makers want 60 to 90 days of cure first
Leveling
Self-levelerTile after about 6 hours, other floors after 16, for ARDEX K 15 at 70 F
A small room is mostly cuts: around the toilet, the vanity, the door jambs. Rates per foot climb fast.
| Situation | Multiply by |
|---|---|
| Room 80 to 200 sq ft | 1.5 |
| Room under 80 sq ft | 2.5 to 4 |
| Herringbone LVP or laminate | 1.3 to 1.5 |
| Herringbone wood or tile | 2 to 3 |
On an existing slab nothing goes down. The floor is ground, densified, polished and guarded in place.
The passes
GrindMetal diamonds, about 3 passes, to the exposure you want
DensifyA silicate soaked in after the coarse grits
PolishResin diamonds, about 4 passes, to 400 or 800 grit
GuardOne to three thin coats, burnished
The hours
RoomAbout 26 person-hours, 19 to 33
EdgesA hand grinder along every wall, 4 to 8 hours of it
AddsOld glue or coatings 3 to 6 hours; deeper aggregate 6 to 12
Sanding and finishing on site adds days, mostly drying between coats.
One room, waterborne finish
SandThree passes, then edges
CoatsStain if used, then 3 coats a few hours apart
WalkMay be walked on after 24 hours
FurnitureAbout 3 days after the last coat
RugsAfter full cure, 3 to 7 days by product
Oil-based finish
PaceAbout one coat a day
TotalRoughly 5 to 7 days for the room

Hours on every line

Hours logged by role
In Clamp, an estimate with labor hours on each assembly, including flooring demo, and hours logged on a job by role. Demo data.
What it means
Your hours, line by line
Clamp shows person-hours on each labor line of an estimate, from its labor hours catalog, or a rough figure from the line's dollars when the catalog has no match. Its remodel LVP rate is 0.04 h per sq ft, a small-room rate, so set your own hours on the line for an open room. Log hours on site by role and see them against the estimate on the job's costs card.
On your next few flooring jobs, log the hours by task: tear-out, prep, install, trim. Your own rates will beat any table here within a month.
Questions
How long does it take to install flooring?
For a 300 sq ft room, about 12 person-hours for carpet, 20 for LVP, 24 for prefinished hardwood and 60 for tile, from tear-out to trim. With two installers, carpet and LVP are done in a day; tile takes 4 to 6 days with grout and cure. Planning estimates.
How long does it take to install hardwood floors?
With two installers, prefinished hardwood in a 300 sq ft room is one to two days on site, after the boards acclimate to the room's moisture, which has no fixed number of days. Sanding and finishing on site adds about 3 to 5 days.
Does LVP need to acclimate?
It depends on the brand. COREtec says acclimation isn't required, as long as the room is 55 to 85 F. Pergo's click vinyl asks for at least 48 hours. Follow the box.
How long does carpet installation take?
About 12 person-hours for a 300 sq ft room, tear-out included, so one day for two installers. The carpet should sit at least 24 hours at 65 to 95 F before it goes in.
How long does it take to polish a concrete floor?
About 26 person-hours for a 300 sq ft room on an existing slab, over 2 days with a crew of two. The guard takes foot traffic about an hour after the final burnish; furniture goes back the next day. A new slab waits 28 days first.
Sources & provenance
- How to Track Time on a Job (Clamp) Clamp Research
- NWFA Installation Guidelines National Wood Flooring Association (research)
- Acclimation: environmental conditions before, during and after installation Hardwood Floors magazine (NWFA) (research)
- Mohawk solid hardwood installation instructions Mohawk (research)
- Pergo laminate installation instructions Pergo (research)
- Pergo click vinyl installation instructions Pergo (research)
- COREtec Scratchless installation instructions COREtec (research)
- CRI 105, Standard for Installation of Residential Carpet Carpet and Rug Institute (research)
- Forbo glue-down general installation guidelines Forbo Flooring (research)
- Forbo Marmoleum residential installation manual Forbo Flooring (research)
- 24-hour ASTM F2170 test results Wagner Meters (research)
- ARDEX K 15 self-leveling underlayment ARDEX (research)
- Polyblend Plus grout technical data Custom Building Products (research)
- Bona Mega technical data Bona (research)
- Bona Traffic HD technical data Bona (research)
- Consolideck LSGuard product data PROSOCO (research)
- Husqvarna grinder relative production rates Runyon Surface Prep (research)
- Polished Concrete Lessons Learned, Quality Bulletin 31 AECOM Hunt (research)
- Polished concrete levels Concrete Network (research)