Generator Installation Cost (2026): $14,897 to $22,919

What a contractor's cost is in 2026 to install a home standby generator or connect a portable one: price by size, what the site adds, clearances, fuel demand, the electrical rules, and labor hours.

Direct answer: In Clamp's catalog, a 22 kW standby generator with an automatic transfer switch, pad, feeder and gas line is $11,459 in job cost before markup and 38 person-hours. A gas meter upgrade takes it to $12,959. Connecting a portable through an interlock and a 50 amp inlet is $847. The ballpark price range for the 22 kW job is $14,897 to $22,919.

The assumptions

This model assumes

  • Natural gas, 200 amp service, pad, 25 ft feeder and 20 ft gas line unless stated
  • Job cost before markup: labor, equipment and materials, no tax
  • National prices with no regional adjustment
  • A $225 permit allowance on each generator job, not in the job cost shown
  • Prices from Clamp's catalog on November 11, 2026

The model, step by step

1Standby generators by size

Priced through Clamp's catalog on November 11, 2026 for a natural gas standby generator with an automatic transfer switch, a poured pad, 25 ft of feeder and 20 ft of gas line. Every price in this guide is job cost before markup: what the labor, equipment and materials cost you. These are national prices with no regional adjustment. Each job also carries a $225 permit allowance, except the generator-ready prep (none) and the propane tank job ($475).

Illustration in the style of Quick Clamp's sketch pad: an electric meter feeding a transfer switch and a panel, with a generator wired to the transfer switch and piped to the gas meter. Rows: Generator, 22 kW, natural gas. Transfer switch, 200 amp, automatic. Gas meter upgrade, Yes. Labor, 38 hours. Job cost before markup, $12,959.

Standby, whole house

Drawn for this guide in the style of Quick Clamp's sketch pad: the parts of a whole-house standby job. The pad has no generator tool, so this is an illustration with typed labels. Demo data.

Standby generator installed, job cost before markup
SizeJob costHours
14 kWAir-cooled$10,01538
18 kWAir-cooled$11,45938
22 kWAir-cooled$11,45938
26 kWAir-cooled$12,64138
28 kWAir-cooled$13,23238
30 kWLiquid-cooled$19,25938
38 kWLiquid-cooled$23,41938
48 kWLiquid-cooled$24,45938
The ballpark price range for the 22 kW job is $14,897 to $22,919. Clamp carries the 22 kW unit and its switch at $6,500, a discounted buy; the same Generac package lists at $7,229 at a national retailer. The starting battery is not included with the unit, and Clamp has no line for it.
2What moves a standby price

The size of the unit moves the price less than the site does. Where the generator sits relative to the electric meter, the panel and the gas meter decides the feeder, the gas run and the trench.

One 22 kW job, six sites
JobJob costHours
22 kW, as abovePad, 25 ft feeder, 20 ft gas$11,45938
No pad, no gas runBeside the meters$10,75334
Gas meter upgradeUtility swaps the meter$12,95938
Set 60 ft away75 ft feeder, 60 ft trench$13,35650
14 kW, critical loadsSubpanel, circuits moved$11,19046
Propane, new tank500 gallon tank set$15,46040

The choices

Gas meterThe utility's meter and regulator swap adds $1,500 in Clamp. Utilities set their own charge, and some take weeks.

DistanceA unit 60 ft out, with the feeder and gas trenched, is $13,356 and 50 hours.

Critical loadsA 14 kW unit with a critical loads panel is $11,190: the smaller unit saves $1,444 and moving the circuits adds $1,175, so it lands only $269 under the 22 kW whole-house job.

PropaneWith a new 500 gallon tank set, $15,460. Clamp carries a second permit allowance of $250 for the tank; whether one is required depends on the state and the tank size. Clamp's tank price runs above the installed prices we found.

Liquid-cooledAir-cooled home units top out at about 26 to 28 kW, depending on the maker. Larger units are liquid-cooled. A 30 kW job is $19,259.

One dealer publishes installed prices of about $13,500 for 14 kW, $15,500 for 18 kW, $16,600 for 22 kW and $17,700 for 26 kW, with the gas hookup and sales tax extra.
3Where it can sit

The fire code's general rule is 5 ft from openings and from walls that can burn. Makers fire-test their units to sit closer to a wall, and that reduced clearance belongs to the model that was tested.

Illustration in the style of Quick Clamp's sketch pad: a plan of a generator beside a house wall with a window, with its clear zone dashed. Rows: Behind the unit, 18 in. Front and both ends, 3 ft. Doors and windows, 5 ft. Source, Generac manual.

Where it can sit

Drawn for this guide in the style of Quick Clamp's sketch pad: Generac's clearances for its 10 to 28 kW units, from its January 2026 manual. Read the manual for the unit you are setting. Demo data.

Before you pour the pad

Wall18 in behind the unit in that manual. The reduction is for the wall, not for openings.

Service space3 ft at the front and at both ends, and 5 ft clear above.

OpeningsDoors, windows and air intakes follow the adopted code. Local rules on intakes, lot lines and noise can ask for more.

Carbon monoxideExhaust can reach an opening that meets the clearance. Check where it will go.

Local zoning can bar a front yard or set a distance from the lot line. Check before the unit is ordered.
4Fuel: what the unit burns

Size the gas pipe and check the meter for the generator at full load, on top of everything else in the house. These are Generac's current air-cooled units.

Full-load fuel use, Generac's current units
SizeGas/hrLP/hr
14 kW14 kW on natural gas243 cu ft2.92 gal
18 kW17 kW on natural gas235 cu ft2.87 gal
22 kW21 kW on natural gas311 cu ft3.71 gal
26 kW24 kW on natural gas316 cu ft3.95 gal

Reading the table

The meterA 22 kW unit can ask for 311 cu ft an hour by itself. Add the furnace, water heater and range, and ask the utility whether the meter passes it.

Rated on propaneThe size on the box is the propane rating. On natural gas the 22 kW makes 21 kW.

Propane tanksTank sizes are water capacity. Under the 2017 propane code a 125 to 500 gallon tank sits 10 ft from the building, and its relief valve and fill connection 10 ft from the generator.

Older models burn more: Generac's previous 22 kW used 327 cu ft an hour. Use the specification sheet for the unit you are installing.
5Hooking up a portable

A power inlet on the outside wall, a cable to the panel, and an interlock that keeps the main and the generator breaker from being on together: $778 at 30 amps and $847 at 50, about 4 hours.

Illustration in the style of Quick Clamp's sketch pad: a portable generator outside, 20 ft from the house, corded to an inlet on the wall, with a cable to the panel inside. Rows: Inlet, 50 amp. Interlock, Made for the panel. Cable to the panel, 25 ft. Labor, 4 hours. Job cost before markup, $847.

Portable hookup

Drawn for this guide in the style of Quick Clamp's sketch pad: a portable generator's connection to the house. The pad has no inlet tool, so this is an illustration with typed labels. Demo data.

Portable generator connection, job cost before markup
JobJob costHours
30 amp inlet, interlock25 ft of cable$7784
50 amp inlet, interlock25 ft of cable$8474
50 amp, 60 ft runLonger cable$1,0184
Generator-ready prepConduit and spaces only$8935

Doing it right

The interlockUse the kit made for that panel, with its breaker and breaker retainer. Write the panel model and kit number on the estimate.

No backfeed cordsA cord with a plug on both ends is never acceptable. The safety commission warned against them again in March 2026.

The neutralA portable with its neutral bonded to the frame can trip its own GFCI on a house connection. Use transfer equipment that switches the neutral, or have the maker's authorized dealer convert the generator to a floating neutral.

SizeA 30 amp inlet is 7,200 W at 240 V and a 50 amp inlet is 12,000 W. The generator's running watts are the real limit.

Where it runsAt least 20 ft from the house, exhaust pointed away. An estimated 93 people died in 2022 from carbon monoxide where a generator was the only product involved.

The ballpark price range for the 50 amp hookup is $1,101 to $1,694.
6The rules in 2026

Checked on November 11, 2026. The electrical code is adopted state by state, and sometimes city by city, so the edition in force depends on where the job is.

What applies

Transfer equipmentEvery standby system needs transfer equipment that keeps the generator and the utility apart.

SizingWith automatic transfer, the generator carries the whole load it picks up, or the load a load-management system allows.

The 200 amp switchA 200 amp transfer switch matches a 200 amp service. A 22 kW generator makes about 92 amps.

Code editionThe 2026 edition is already in force in some states, including Massachusetts and Texas. Most others are on 2023 or 2020, a few are older, and some leave it to the city or county. Ask the inspector.

PermitsExpect an electrical permit and often a gas or plumbing permit; some places add zoning review.

Tax creditA home standby generator gets no federal residential clean energy credit, and that credit ended for spending after December 31, 2025.

A federal rule to limit carbon monoxide from portable generators has been proposed and is not in force.
7Hours

Clamp carries 38 person-hours on the standard job: 28 to set, wire and start the generator, 6 for the transfer switch, and about 4 for the gas line and the pad.

Against what installers publish

Site timeOne dealer describes one to two days on site for a standard install, without stating the crew.

What that meansTwo people for two days is 32 person-hours. Two for one day is 16. Clamp's 38 sits above that range.

StartupGenerac's manual calls for 20 to 30 minutes at full rated load, a fuel pressure check and a simulated outage. That time is inside the generator line.

Before the crew arrivesThe permit, the utility and the gas meter set the calendar. Weeks, not days.

No published study gives person-hours for this work. Track your own on the next three installs and adjust.
8The worked example: three ways to keep the lights on

A house with a 200 amp service and natural gas loses power a few times a year. Option A connects the owner's portable generator through a 50 amp inlet and an interlock: $847. Option B installs a 14 kW standby unit on a critical loads panel: $11,190 and 46 hours. Option C installs a 22 kW unit on the whole house with a gas meter upgrade: $12,959 and 38 hours.

Option C, 22 kW whole house: ballpark price range
$16,847 to $25,919
Job cost before markup: option A $847, option B $11,190, option C $12,959
Option C $12,959
Option B $11,190
$1,769 more, whole house
Option C line items, $12,959 job cost before markup
LineJob costHours
22 kW unit and switch1 ea$6,500
Set and wire the generator1 ea$3,20028.0
Gas meter upgrade1 ea$1,500
Install the transfer switch1 ea$8506.0
Gas line, labor20 lf$3803.6
Gas line, pipe20 lf$170
Feeder cable28.75 lf$122
Pad, concrete16 sf$84
Conduit25 lf$81
Pad, labor16 sf$720.8
Clamp's Generate from description screen with the standby generator job typed in

The job

The standby generator estimate in Clamp at $12,959 job cost, by trade

Every line priced

The job in Clamp, and the estimate it prices: $12,959 at job cost, by trade. Recreations of the Clamp app with demo data.

Option B is close to option C because moving circuits to a critical loads panel takes a day. On a 200 amp service, the whole-house switch is often the simpler job. No battery, surge protector or maintenance plan is in these prices.

What it means

What to doWalk the route from the meters to the pad before you price. Ask the gas utility about the meter. Read the manual for the unit's clearances. For a portable, use the interlock made for the panel.
The example house, option C: $16,847 to $25,919 ballpark price range on $12,959 job cost before markup.

Every generator job, line by line

Clamp reads the size, the fuel, the transfer arrangement, the runs, the trench and the meter upgrade from the words, and prices the unit, the switch, the pad, the gas line and the permit, with labor hours on each line.

The generator is a known price. The site is the estimate.

Questions

How much does it cost to install a whole house generator?

In Clamp's catalog a 22 kW natural gas standby generator with a 200 amp automatic transfer switch, a pad, 25 ft of feeder and 20 ft of gas line is $11,459 in job cost before markup, plus a $225 permit. The ballpark price range is $14,897 to $22,919. Generac advertises $8,000 to $16,000 installed.

How much does a generator interlock kit cost to install?

An interlock, a power inlet and 25 ft of cable is $778 at 30 amps and $847 at 50 amps in job cost before markup in Clamp's catalog, about 4 hours. The ballpark price range at 50 amps is $1,101 to $1,694.

How long does it take to install a standby generator?

One dealer describes one to two days on site. Clamp carries 38 person-hours for a standard air-cooled install. The permit, the utility and any gas meter upgrade take weeks before that.

How close to the house can a standby generator be?

It depends on the model. Generac's current manual for its 10 to 28 kW units allows 18 in behind the unit, with 3 ft at the front and both ends and 5 ft above. Doors, windows and air intakes follow the adopted code, which generally means 5 ft.

Is there a tax credit for a home generator in 2026?

No residential clean energy credit applies to a home standby generator, and the IRS says that credit ended for expenditures made after December 31, 2025.

Related

Sources & provenance

  1. Clamp's catalog, priced by script Clamp (research)
  2. Articles 702, 705, 706 and 710: optional standby systems North Carolina Office of State Fire Marshal (official source)
  3. Panelboard application guide UL Solutions (official source)
  4. CPSC warns consumers to stop using male-to-male extension cords US Consumer Product Safety Commission (official source)
  5. CPSC warns of generator, carbon monoxide and fire hazards ahead of hurricane season US Consumer Product Safety Commission (official source)
  6. Non-fire carbon monoxide deaths associated with the use of consumer products: 2022 annual estimates US Consumer Product Safety Commission (official source)
  7. Why does the generator GFCI breaker trip on some generators when used with a transfer switch? Generac (research)
  8. Air-cooled home standby generators 10 to 28 kW installation manual (A0004332575, Rev. D) Generac (research)
  9. 10 to 18 kW air-cooled standby generator specification sheet (A0005151081, Rev. C) Generac (research)
  10. 22 to 28 kW air-cooled standby generator specification sheet (A0005151077, Rev. B) Generac (research)
  11. Placing LP-gas containers fact sheet National Fire Protection Association (official source)
  12. Massachusetts Electrical Code Commonwealth of Massachusetts (official source)
  13. Commission adopts rules: electricians Texas Department of Licensing and Regulation (official source)
  14. FAQs for modification of sections 25C, 25D, 25E, 30C, 30D, 45L, 45W and 179D under Public Law 119-21 IRS (official source)
  15. Generac 7325 home standby generator, product page Ace Hardware (research)
  16. Backup generator installation Generac (research)
  17. Whole house generator cost Wolf River Electric (research)
Changes: Nov 11, 2026: Published: standby generators and portable generator connections, priced from Clamp's catalog with labor hours.