Mechanics liens · New Hampshire

New Hampshire Mechanics Lien Deadline (2026): 120 Days after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in New Hampshire, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 120 days after last work. For a last day of work on Friday, November 20, 2026, record it by Sat, Mar 20, 2027 and sue by Sat, Mar 20, 2027. None. No early notice applies when the homeowner hired you directly.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in New Hampshire

Record the lien

120 days after last work

Your lien arises automatically and lasts 120 days after your work. Nothing is recorded. Secure it by court attachment within those 120 days.

Sue to enforce it

120 days after last work

Sue and get a court-approved attachment of the property within 120 days after your work.

Notice to the homeowner

No notice needed

None. No early notice applies when the homeowner hired you directly.

Homeowner rules

No special rule

None

Source: RSA 447:2, 447:9, 447:10 (Official NH General Court RSA pages, chapter 447; latest amendment shown 2019)

“shall continue for 120 days after the services are performed”

New Hampshire statute RSA 447:2, 447:9, 447:10 (Official NH General Court RSA pages, chapter 447; latest amendment shown 2019)

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jul 11, 2026Jul 11, 2026
Jul 31, 2026Nov 28, 2026Nov 28, 2026
Nov 20, 2026Mar 20, 2027Mar 20, 2027

The suit deadline runs from the last day of work, not from when you record. Dates are calendar arithmetic and aren't moved off weekends or holidays.

New Hampshire lien questions

How long do I have to file a mechanics lien in New Hampshire?

Your lien arises automatically and lasts 120 days after your work. Nothing is recorded. Secure it by court attachment within those 120 days.

How long does a mechanics lien last in New Hampshire?

Sue and get a court-approved attachment of the property within 120 days after your work.

Does a contractor need to send a notice before filing a lien in New Hampshire?

None. No early notice applies when the homeowner hired you directly.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.