Mechanics liens · North Dakota

North Dakota Mechanics Lien Deadline (2026): 90 Days after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in North Dakota, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 90 days after last work. For a last day of work on Friday, November 20, 2026, record it by Thu, Feb 18, 2027 and sue by Mon, Feb 18, 2030. None. No early notice applies when the homeowner hired you directly.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in North Dakota

Record the lien

90 days after last work

Record within 90 days after all your work is done.

Sue to enforce it

3 years after recording

Sue within 3 years after recording. First give 10 days notice in person or 20 days by registered mail. A homeowner's demand cuts this to 30 days.

Notice to the homeowner

No notice needed

None. No early notice applies when the homeowner hired you directly. Send the homeowner written notice of intent to lien by certified mail at least 10 days before recording.

Homeowner rules

No special rule

None On jobs over $4,000 you need a state contractor license to sue, including to enforce your lien.

Source: N.D.C.C. 35-27-02, 35-27-13, 35-27-24, 35-27-25, 43-07-02 (Official ND session laws: 2023 (SB 2261, HB 1323, SB 2311) and 2009 (SB 2250 amending 35-27-25))

“within ninety days after all the person's contribution is done”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jun 11, 2026Jun 11, 2029
Jul 31, 2026Oct 29, 2026Oct 29, 2029
Nov 20, 2026Feb 18, 2027Feb 18, 2030

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Also check

North Dakota lien questions

How long do I have to file a mechanics lien in North Dakota?

Record within 90 days after all your work is done.

How long does a mechanics lien last in North Dakota?

Sue within 3 years after recording. First give 10 days notice in person or 20 days by registered mail. A homeowner's demand cuts this to 30 days.

Does a contractor need to send a notice before filing a lien in North Dakota?

None. No early notice applies when the homeowner hired you directly. Send the homeowner written notice of intent to lien by certified mail at least 10 days before recording.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.