Ohio Mechanics Lien Deadline (2026): 60 Days after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Ohio, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 60 days after last work. For a last day of work on Friday, November 20, 2026, record it by Tue, Jan 19, 2027 and sue by Wed, Jan 19, 2033. None. The notice of commencement is the homeowner's filing and generally not required on home construction.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Ohio

Record the lien

60 days after last work

For a one- or two-family home or condo, file within 60 days of last labor or materials, 75 for other property. Serve the homeowner within 30 days of filing.

Sue to enforce it

6 years after recording

The lien lasts 6 years after filing. If the homeowner gives notice to sue, you must sue within 60 days or the lien is void.

Notice to the homeowner

No notice needed

None. The notice of commencement is the homeowner's filing and generally not required on home construction.

Homeowner rules

Check first

On a home the owner lives in, all liens together can't exceed what the homeowner still owes you. If the homeowner paid you in full before getting your lien, there is no lien.

Source: R.C. 1311.011, 1311.04, 1311.06, 1311.07, 1311.11, 1311.13 (Official Ohio Revised Code site: 1311.06 authenticated (eff. 1/30/2014), 1311.13 (eff. 3/30/2007), chapter 1311 page)

“within sixty days from the date on which the last labor or work”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026May 12, 2026May 12, 2032
Jul 31, 2026Sep 29, 2026Sep 29, 2032
Nov 20, 2026Jan 19, 2027Jan 19, 2033

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Ohio lien questions

How long do I have to file a mechanics lien in Ohio?

For a one- or two-family home or condo, file within 60 days of last labor or materials, 75 for other property. Serve the homeowner within 30 days of filing.

How long does a mechanics lien last in Ohio?

The lien lasts 6 years after filing. If the homeowner gives notice to sue, you must sue within 60 days or the lien is void.

Does a contractor need to send a notice before filing a lien in Ohio?

None. The notice of commencement is the homeowner's filing and generally not required on home construction.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.