Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.
The rule in Wyoming
150 days after last work
File within 150 days after your last work or materials or substantial completion, whichever is first. A recorded notice of substantial completion fixes that date.
180 days after recording
Start foreclosure within 180 days after filing the lien, or the lien ends.
Notice before first payment
Before taking any payment, including advances, give the homeowner the state notice of lien rights and lien waiver rights. Missing it bars the lien. Send the homeowner of record the state notice of intent to lien at least 20 days before filing.
No special rule
None
Source: Wyo. Stat. 29-2-106, 29-2-107, 29-2-109, 29-2-112 (Justia 2025 Wyoming Statutes, Title 29 ch. 2)
“file his lien statement within one hundred fifty (150) days”
Three last days of work, worked
| Last work | Record by | Sue by |
|---|---|---|
| Mar 13, 2026 | Aug 10, 2026 | Feb 6, 2027 |
| Jul 31, 2026 | Dec 28, 2026 | Jun 26, 2027 |
| Nov 20, 2026 | Apr 19, 2027 | Oct 16, 2027 |
Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.
Also check
- Before you file: Send the homeowner of record the state notice of intent to lien at least 20 days before filing.
Wyoming lien questions
How long do I have to file a mechanics lien in Wyoming?
File within 150 days after your last work or materials or substantial completion, whichever is first. A recorded notice of substantial completion fixes that date.
How long does a mechanics lien last in Wyoming?
Start foreclosure within 180 days after filing the lien, or the lien ends.
Does a contractor need to send a notice before filing a lien in Wyoming?
Before taking any payment, including advances, give the homeowner the state notice of lien rights and lien waiver rights. Missing it bars the lien. Send the homeowner of record the state notice of intent to lien at least 20 days before filing.
Compare other states
How we checked
We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .