Lien notice · Massachusetts

Massachusetts Lien Notice to the Homeowner (2026): Written Contract Required

What a contractor hired directly by a homeowner must give the owner in Massachusetts to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: No notice to the owner is due at signing or at the start. The contractor's lien exists only under a written contract and only once a notice of contract is recorded at the registry of deeds, which can be done any time after signing. On a $32,000 kitchen signed March 2 with work starting March 16: The March 2 contract had to be in writing to keep the lien. The notice of contract could be recorded any time after signing and before the outside dates.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in Massachusetts

Rule

Lien at stake

No notice to the owner is due at signing or at the start. The contractor's lien exists only under a written contract and only once a notice of contract is recorded at the registry of deeds, which can be done any time after signing.

Notice to the homeowner due

Written contract

Filed or recorded in the registry of deeds for the county or district where the land lies.

Source

M.G.L. c. 254, s. 2

malegislature.gov (official), current General Laws.

“at any time after execution of the written contract”

A $32,000 kitchen in Massachusetts

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

Yes

The March 2 contract had to be in writing to keep the lien. The notice of contract could be recorded any time after signing and before the outside dates.

The details

Deadline

Record the notice of contract any time after the written contract is executed, and no later than the earliest of 60 days after a recorded notice of substantial completion, 90 days after a recorded notice of termination, or 90 days after last work.

Required form

Substantially the statutory form in c. 254, s. 2.

If you miss it

No recorded notice of contract, no lien under section 2; an oral contract does not qualify.

Subs and suppliers

Subs with a written contract record their own notice of contract under section 4 (seen in a search snippet, not read in full).

Massachusetts lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in Massachusetts?

No notice to the owner is due at signing or at the start. The contractor's lien exists only under a written contract and only once a notice of contract is recorded at the registry of deeds, which can be done any time after signing.

What happens if a contractor misses the notice in Massachusetts?

No recorded notice of contract, no lien under section 2; an oral contract does not qualify.

Do subs and suppliers have to give notice in Massachusetts?

Subs with a written contract record their own notice of contract under section 4 (seen in a search snippet, not read in full).

Compare other states

More Massachusetts rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.