Preliminary Notice by State (2026): What a Contractor Must Give the Homeowner to Keep Lien Rights
The notice, disclosure or filing a contractor hired directly by a homeowner must make in each state to keep its own lien rights, when it is due, and one $32,000 kitchen answered in every state.
Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.
The map
Each state by what a contractor hired directly by the homeowner must give the owner to keep its own lien rights. Tap a state for its rule and source.
One $32,000 kitchen, 51 answers
A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?
| Answer | Where |
|---|---|
| Had to act by the time work started 11 states | Arkansas, Connecticut, Florida, Hawaii, Massachusetts, Michigan, Minnesota, Oregon, Rhode Island, Texas, Washington |
| Depends on the first payment or on using subs 4 states | Iowa, Missouri, Wisconsin, Wyoming |
| Nothing due by the start of work to keep the lien 36 states | Alabama, Alaska, Arizona, California, Colorado, Delaware, District of Columbia, Georgia, Idaho, Illinois, Indiana, Kansas, Kentucky, Louisiana, Maine, Maryland, Mississippi, Montana, Nebraska, Nevada, New Hampshire, New Jersey, New Mexico, New York, North Carolina, North Dakota, Ohio, Oklahoma, Pennsylvania, South Carolina, South Dakota, Tennessee, Utah, Vermont, Virginia, West Virginia |
"No" means nothing was due by March 16 to keep the lien. It does not mean nothing is ever due: several of those states require a notice before the lien is recorded, and every state has a deadline to record it.
What changes the answer
Preliminary notice is usually described as a subcontractor's job. For a contractor hired by the homeowner, these are the rules that bite.
The deposit date
Missouri and Wyoming require the notice before you take any payment. If you take a deposit at signing, the notice was due at signing, whatever date work starts.
Using a sub or supplier
In Minnesota, Wisconsin and Iowa the prime's duty turns on using a subcontractor or material supplier. On a kitchen you almost always do.
Late is not the same everywhere
A late Arizona notice still covers the 20 days before it and everything after. A late Utah filing covers work from five days after filing. An Iowa posting covers only work after posting, even inside the 10 days.
A disclosure is not always a lien condition
Texas requires a disclosure before the owner signs but keeps the lien if you omit it; its homestead contract rules are what cost the lien. In Florida a missing warning does not bar the lien against anyone who was not adversely affected by the omission.
Who the notice goes to
In Virginia the notice goes to the mechanics' lien agent named on the building permit, if there is one. In Utah and Iowa it is a filing in a state registry. In California the direct contractor notifies only a construction lender.
All 50 states and DC
What a contractor hired directly by the homeowner must give the owner, and when. Each row links to the source read.
| State | Notice to the homeowner due |
|---|---|
| AlabamaNo notice | None for the prime A contractor hired directly by the owner (the original contractor) gives no notice before or during the work. The written notice in 35-11-218 is for everyone except the original contractor. If the owner asks, the original contractor must give a list of its suppliers, laborers and employees with their terms and prices. Ala. Code 35-11-210, 35-11-218, 35-11-219 |
| AlaskaNo notice | None for the prime No notice is required. A remodeler may give the owner a written notice of right to lien before furnishing labor or materials; giving it shifts the burden of proof on owner consent and protects the longer recording window. AS 34.35.064, 34.35.068 |
| ArizonaLien at stake | Within 20 days of starting Serve the Arizona preliminary twenty day notice on the owner (and any construction lender) within 20 days after first furnishing labor or materials. On an owner-occupied dwelling, only someone with a written contract signed directly with the owner-occupant can lien at all. A.R.S. 33-992.01, 33-1002 |
| ArkansasLien at stake | Before work starts On residential property of four or fewer units, the residential contractor must give the owner the statutory IMPORTANT NOTICE TO OWNER before work begins. Skip it and the contractor has no lien. Ark. Code 18-44-115(a) |
| CaliforniaDisclosure | In the contract Put the statutory Mechanics Lien Warning in the home improvement contract (jobs over $500). A direct contractor owes a preliminary notice only to a construction lender, if there is one. Cal. Civ. Code 8200; Bus. & Prof. Code 7159(e)(4) |
| ColoradoNo notice | None for the prime No notice is due at signing or at the start. Every claimant, the prime included, must serve a notice of intent to file a lien statement at least 10 days before filing the lien. C.R.S. 38-22-109(3), 38-22-105.5 |
| ConnecticutLien at stake | In the contract No lien notice is due from the original contractor. But the home improvement contract must be in writing, signed by the owner and the contractor, and carry the terms listed in Conn. Gen. Stat. 20-429. A contract that falls short is not enforceable against the owner, and Connecticut appellate courts have denied or discharged the contractor's mechanic's lien on that ground. Conn. Gen. Stat. 20-429, 49-35(a); Burns v. Adler, 325 Conn. 14 (2017); Lucien v. McCormick Construction, LLC, 122 Conn. App. 295 (2010) |
| DelawareNo notice | None before work No notice is due at signing or at the start. At or before final payment on an owner's residence, the contractor must give the owner a notarized certification that everyone has been paid or a signed release of liens, and must answer an owner's demand for a list of subs and suppliers within 10 days. 25 Del. C. 2705, 2707 (2703 for land-only work) |
| District of ColumbiaNo notice | None before work No notice is due at signing or at the start. To have a lien, the contractor records a notice of intent in the land records during construction or within 90 days after the project is completed or terminated, and mails the owner a copy within 5 business days. D.C. Code 40-301.01, 40-301.02, 40-301.03 |
| FloridaLien at stake | In the contract On a direct contract over $2,500 for a one to four unit dwelling, print the statutory construction lien warning on the front page of the contract or on a separate page the owner signs and dates. Fla. Stat. 713.015 |
| GeorgiaNo notice | None for the prime The prime gives the owner no notice to keep its own lien. A Notice of Commencement is to be filed with the superior court clerk within 15 days after the contractor physically starts work, by the owner, the owner's agent or the contractor, and posted on site. O.C.G.A. 44-14-361.5, 44-14-361.1 |
| HawaiiLien at stake | At signing Before or when the homeowner signs, a licensed contractor must explain verbally, in detail, everyone's lien rights and the owner's option to demand a bond, and put that information in a written contract signed by both sides before any work. HRS 444-25.5 |
| IdahoDisclosure | Before signing Before entering a contract over $2,000 with a homeowner, the general contractor must give a written disclosure of the owner's rights (lien waivers, proof of insurance, extended title insurance, a surety bond) and get a signed acknowledgment. Idaho Code 45-525 |
| IllinoisDisclosure | Before first payment On an owner-occupied single-family residence, give the owner the statutory 'THE LAW REQUIRES' statement in the contract or as a separate printed statement before the owner's first payment, and give a sworn statement of subs and suppliers before any payment. 770 ILCS 60/5(a), (b)(i) |
| IndianaNo notice | None for the prime A contractor hired directly by the occupying owner gives no pre-lien notice. The 30-day notice on an owner-occupied single or double family dwelling is for those who furnish on credit to a contractor, sub or anyone other than the occupying owner. IC 32-28-3-1(h), (i) |
| IowaLien at stake | Within 10 days of starting If the remodeler has or will have any subcontractor on the job, it must post a notice of commencement of work on the state Mechanics' Notice and Lien Registry within 10 days after starting, and give the owner the statutory owner notice. The posting only covers work done after it is posted, so post before starting. Iowa Code 572.13, 572.13A |
| KansasNo notice | None for the prime The contractor hired by the owner gives no notice to keep its own lien. The residential warning statement in 60-1103a conditions only a subcontractor's or supplier's lien, and the general contractor may hand it to the owner for them. K.S.A. 60-1103a |
| KentuckyNo notice | None for the prime A contractor who contracted directly with the owner gives no notice to the owner. The written notice in KRS 376.010 is for persons who have not contracted directly with the owner. KRS 376.010(4), (5) |
| LouisianaDisclosure | At signing Before or when signing a residential home improvement contract, the contractor must deliver the written NOTICE OF LIEN RIGHTS to the owner for signature and give the owner a copy. La. R.S. 9:4851 to 9:4855 |
| MaineNo notice | None for the prime A contractor with a contract with the owner gives no preliminary notice. Its lien is kept by filing an enforcement action within 120 days after the last labor or services. 10 M.R.S. 3255; 10 M.R.S. 1487 |
| MarylandNo notice | None for the prime A contractor who contracted directly with the owner gives no notice of intention to claim a lien. That notice is a subcontractor requirement. Md. Code, Real Property 9-104 |
| MassachusettsLien at stake | Written contract No notice to the owner is due at signing or at the start. The contractor's lien exists only under a written contract and only once a notice of contract is recorded at the registry of deeds, which can be done any time after signing. M.G.L. c. 254, s. 2 |
| MichiganLien at stake | In the contract On a residential structure, a contractor has no construction lien unless the work is done under a written contract with the owner and every change is also in writing. The contract must also carry the statutory licensing statement and the contractor's license number. MCL 570.1114, 570.1110 |
| MinnesotaLien at stake | In the contract If the remodeler will use any subcontractor or material supplier, the statutory lien notice must be in the written contract and the owner must get a copy. With no written contract, deliver it separately within 10 days after the work is agreed on. Minn. Stat. 514.011, subd. 1, 4a, 4b, 4c, 5 |
| MississippiNo notice | None for the prime A contractor in privity with the owner gives no pre-lien notice. On single-family residential work the 10-day pre-lien notice is for subs, suppliers and design professionals not in privity with the owner. Miss. Code 85-7-409 |
| MissouriLien at stake | Before first payment Every original contractor must give the statutory NOTICE TO OWNER before receiving any payment: at contract signing, when materials are delivered, when work starts, or with the first invoice. RSMo 429.012 |
| MontanaNo notice | None for the prime A contractor hired directly by the owner does not have to give Montana's notice of the right to claim a lien. The only steps are the later lien filing steps. MCA 71-3-531(1)(a), 71-3-531(2) |
| NebraskaNo notice | None for the prime Nebraska has no required start-of-job notice for the prime. The notice of the right to assert a lien is optional and matters for subs and suppliers, whose lien against a homeowner is capped by what the owner still owes the prime when the notice arrives. Neb. Rev. Stat. 52-135(1), 52-135(6), 52-136(1)(a) and (2) |
| NevadaDisclosure | Before signing Before the contract is signed, tell the owner about Nevada's notice of right to lien rules using the statutory form, and give each sub on the job a copy. Missing it is a licensing matter, not a lien bar. A general building contractor on a single-family residence must also give the owner a written list of its subcontractors and suppliers and a notice that they may record a lien (NRS 624.600). NRS 108.245(5), 108.245(6), 108.246(1)-(3), 108.226(6); NRS 624.600, 624.3016(6) |
| New HampshireNo notice | None for the prime A contractor with a contract with the owner has a lien under RSA 447:2 with no start-of-job notice. The written notice rule is for those working under the contractor. RSA 447:2, 447:5, 447:6, 447:8, 447:12-b |
| New JerseyNo notice | None before work No notice is due at signing or before work. To lien a home, the contractor must first lodge a Notice of Unpaid Balance and Right to File Lien with the county clerk within 60 days after last furnishing, serve it, and demand arbitration within 10 days of lodging. N.J.S.A. 2A:44A-20, 2A:44A-21(b) |
| New MexicoNo notice | None for the prime New Mexico's 60-day notice of the right to claim a lien does not apply to an original contractor, and it does not apply to any claim on residential property with four or fewer units. NMSA 1978, 48-2-2.1(A) and (B) |
| New YorkDisclosure | In the contract Every written home improvement contract must carry the mechanic's lien notice to the owner in clear and conspicuous bold face type. The section does not take away the lien if it is left out. N.Y. Gen. Bus. Law 771(1)(d) |
| North CarolinaNo notice | None for the prime The lien agent rule does not reach this job twice over: it starts at $40,000, and the owner need not name a lien agent for improvements to an existing single-family home the owner lives in. No notice to a lien agent is due. N.C.G.S. 44A-11.1(a), 44A-11.2 |
| North DakotaNo notice | None before work No notice is due at signing or at the start of work. Section 35-27-02(4) requires written notice that a lien will be claimed, sent to the owner by certified mail at least ten days before recording. That sentence sits in the subsection on those hired by a contractor or sub, so its reach to a contractor hired by the owner is not stated; send it anyway. N.D.C.C. 35-27-02, 35-27-13, 35-27-24 |
| OhioNo notice | None for the prime On a home construction contract the notice of furnishing section does not apply at all, and an original contractor never has to serve one. The prime gives the owner no start-of-job notice. R.C. 1311.011(A)(1) and (B), 1311.04(O), 1311.05(A) and (E) |
| OklahomaNo notice | None for the prime The old owner-occupied dwelling notice (42 O.S. 142.1) was repealed in 2011. The current pre-lien notice in 142.6 is for claimants other than the original contractor, so the prime sends no notice. 42 O.S. 142.6(A), (B)(1), (B)(3), (B)(6); former 142.1, 142.3, 142.5 repealed by Laws 2011, c. 23 |
| OregonLien at stake | At signing On a residential contract over $2,000, deliver the Construction Contractors Board's Information Notice to Owner About Construction Liens when the contract is signed. Without it the contractor cannot claim a lien on that contract. ORS 87.093(2)(b), (3), (4), (5), (6) |
| PennsylvaniaNo notice | None for the prime Pennsylvania's formal notice of intention to file is a subcontractor's duty. A contractor hired by the owner gives no notice before work or before filing. Mechanics' Lien Law of 1963, section 501(b.1) (49 P.S. 1501) |
| Rhode IslandLien at stake | Before work starts Put the statutory Notice of Possible Mechanic's Lien conspicuously in the written contract, or send it by certified mail, return receipt requested, before starting work or delivering materials. Without it the contractor has no lien. R.I.G.L. 34-28-4.1 |
| South CarolinaNo notice | None for the prime The prime has a lien by agreement with the owner and owes no start-of-job notice. Filing a notice of project commencement within 15 days of starting is optional and only changes the rules for sub-subs and suppliers. S.C. Code 29-5-10(a), 29-5-20, 29-5-23, 29-5-90 |
| South DakotaNo notice | None for the prime No start-of-job notice to the owner is required. The owner or the contractor may file a notice of project commencement within 30 days of starting; it is optional and is aimed at sub-subs and suppliers. SDCL 44-9-50, 44-9-51, 44-9-53 |
| TennesseeDisclosure | Before work starts Before starting work or making the contract on residential real property, deliver the statutory notice to the owner. Missing it is a Class B misdemeanor if a lien is later filed, but the statute says it does not affect the contractor's lien. T.C.A. 66-11-203, 66-11-206(a) and (c), 66-11-146 |
| TexasLien at stake | Before work starts On a homestead, the lien needs a written contract signed before any labor or material, signed by both spouses if the owner is married, and filed with the county clerk. Separately, give the statutory disclosure statement before the owner signs; leaving that out does not void the lien. Tex. Prop. Code 53.254(a)-(g), 53.255(a)-(c) |
| UtahLien at stake | Within 20 days of starting File a preliminary notice in the State Construction Registry no later than 20 days after starting work. The rule covers anyone who wants a construction lien, the original contractor included. Utah Code 38-1a-501(1)(a), (c), (d), (e); 38-11-107(1)(a); 38-11-108(1) |
| VermontNo notice | None for the prime A person working under a contract with the owner has a lien without giving notice. The written notice rule is for those hired by the contractor or a sub. 9 V.S.A. 1921(a), (b) |
| VirginiaLien at stake | Within 30 days of starting If the building permit for a one- or two-family home names a mechanics' lien agent, notify that agent within 30 days of first work or materials. If the permit names none, or there is no permit, this step does not apply. Va. Code 43-4.01(A)-(D), 36-98.01 |
| WashingtonLien at stake | Before work starts On a residential job of $1,000 or more, give the customer the statutory Notice to Customer disclosure before starting work, get it signed, and keep the signed copy three years. A lien claim fails unless the contractor pleads and proves it was given. RCW 18.27.114(1), (2), (4), (5); RCW 60.04.031(2)(a), (3) |
| West VirginiaNo notice | None for the prime No notice is due at signing or at the start of work. The general contractor perfects the lien by recording a notice of lien within 100 days after completing the contract. W. Va. Code 38-2-1, 38-2-7, 38-2-8, 38-2-14, 38-2-20, 38-2-21(b), 38-2-34(b) |
| WisconsinLien at stake | In the contract A prime contractor who uses or will use any sub, supplier or service provider must put the statutory lien notice in the written contract and give the owner a copy. With no written contract, serve it separately within 10 days after first labor or materials. No notice is needed on a building with more than four family units, on nonresidential work, or where the prime contractor is itself an owner of the land (779.02(1)(c)-(d)). Wis. Stat. 779.02(1)(a)-(e), 779.02(2)(a), (b), (c), (e) |
| WyomingLien at stake | Before first payment Send the owner the statutory preliminary notice of right to lien before taking any payment, a deposit included. Missing the deadline bars the lien. W.S. 29-2-112(a)(i)-(iv), 29-10-101 |
Preliminary notice questions
Does a general contractor have to send a preliminary notice?
Often not: in 26 states the contractor hired by the owner gives no notice before work. But 18 states make the prime's own lien depend on a notice, a contract term or a filing, and missing it can cost the whole lien.
When is a preliminary notice due?
It depends on the state: at signing in Oregon and Hawaii, before work starts in Arkansas, Rhode Island and Washington, before the first payment in Missouri and Wyoming, and within 20 days of starting in Arizona and Utah.
What happens if I miss the notice?
In the strict states you lose the lien for the whole job. In others a late notice covers only work after it, or the consequence is a fine or discipline with the lien kept. Each state page gives what the statute says.
Do my subs and suppliers have to send their own notice?
Usually yes, on their own deadlines. Your notice does not cover them and theirs does not cover you.
Is a preliminary notice the same as a lien?
No. It is a notice or disclosure early in the job that preserves the right to record a lien later. Recording the lien is a separate step with its own deadline.
How we checked
We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .
This guide explains the general rule. It is not legal advice.