Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.
The rule in Michigan
Lien at stake
On a residential structure, a contractor has no construction lien unless the work is done under a written contract with the owner and every change is also in writing. The contract must also carry the statutory licensing statement and the contractor's license number.
In the contract
In the written contract.
MCL 570.1114, 570.1110
legislature.mi.gov (official), complete through PA 114 of 2026; section last amended by 2016 PA 415, effective April 4, 2017.
“under a written contract between the owner or lessee and the contractor”
A $32,000 kitchen in Michigan
A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?
Yes
The March 2 contract had to be in writing to keep the lien. It also had to carry the license statement and number.
The details
Deadline
At signing; every amendment or addition also in writing.
Required form
Licensing statement in type no smaller than the body of the contract: that residential builders, maintenance and alteration contractors and the listed trades must be licensed, and, if a license is required, that the contractor is licensed, with the license number.
If you miss it
No right to a construction lien on the owner's interest in the residential structure without the written contract (MCL 570.1114). The section states no separate lien consequence for a missing license statement. Later, the contractor must give the owner a sworn statement when payment is due or on demand, and cannot be paid or sue on the lien until it does (570.1110).
Subs and suppliers
Subs and suppliers give a notice of furnishing under 570.1109. The contractor hired by the owner does not.
Michigan lien notice questions
Does a contractor have to send a preliminary notice to the homeowner in Michigan?
On a residential structure, a contractor has no construction lien unless the work is done under a written contract with the owner and every change is also in writing. The contract must also carry the statutory licensing statement and the contractor's license number.
What happens if a contractor misses the notice in Michigan?
No right to a construction lien on the owner's interest in the residential structure without the written contract (MCL 570.1114). The section states no separate lien consequence for a missing license statement. Later, the contractor must give the owner a sworn statement when payment is due or on demand, and cannot be paid or sue on the lien until it does (570.1110).
Do subs and suppliers have to give notice in Michigan?
Subs and suppliers give a notice of furnishing under 570.1109. The contractor hired by the owner does not.
Compare other states
More Michigan rules for contractors
How we checked
We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .