Lien notice · Virginia

Virginia Lien Notice to the Homeowner (2026): Due Within 30 Days of Starting

What a contractor hired directly by a homeowner must give the owner in Virginia to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: If the building permit for a one- or two-family home names a mechanics' lien agent, notify that agent within 30 days of first work or materials. If the permit names none, or there is no permit, this step does not apply. On a $32,000 kitchen signed March 2 with work starting March 16: Nothing was due by March 16; if the permit named a lien agent, notice was due by April 15.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in Virginia

Rule

Lien at stake

If the building permit for a one- or two-family home names a mechanics' lien agent, notify that agent within 30 days of first work or materials. If the permit names none, or there is no permit, this step does not apply.

Notice to the homeowner due

Within 30 days of starting

Registered or certified mail, or physical delivery, to the mechanics' lien agent named on the permit.

Source

Va. Code 43-4.01(A)-(D), 36-98.01

Virginia Legislative Information System, Code of Virginia page dated 10/6/2026; history 1992, cc. 779, 787; 2001, c. 532; 2010, c. 341; 2013, c. 293.

“within 30 days of the first date that he performs labor or furnishes material”

A $32,000 kitchen in Virginia

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

No

Nothing was due by March 16; if the permit named a lien agent, notice was due by April 15.

The details

Deadline

Within 30 days of the first date labor is performed or material furnished, or within 30 days of permit issuance if work began before the permit.

Required form

Sender's name, mailing address and telephone number, the permit number, a description of the property as shown on the permit, and a statement that the sender seeks payment.

If you miss it

Late notice limits the lien to labor and materials furnished on or after the date notice is given (Va. Code 43-4.01(C)).

Subs and suppliers

Subs and suppliers have the same duty to notify a named agent within 30 days of their own first furnishing.

Recent change

HB 42 (2026) would have extended the lien agent rules beyond one- and two-family permits. It was continued to the next session in House Courts of Justice on February 11, 2026 and is not law.

Virginia lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in Virginia?

If the building permit for a one- or two-family home names a mechanics' lien agent, notify that agent within 30 days of first work or materials. If the permit names none, or there is no permit, this step does not apply.

What happens if a contractor misses the notice in Virginia?

Late notice limits the lien to labor and materials furnished on or after the date notice is given (Va. Code 43-4.01(C)).

Do subs and suppliers have to give notice in Virginia?

Subs and suppliers have the same duty to notify a named agent within 30 days of their own first furnishing.

Compare other states

More Virginia rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.

Related