Detached ADU Cost: 600 Sq Ft, One Bed, One Bath, Itemized (2026 Baseline)

A 600-square-foot backyard ADU with one bedroom, one bath and a kitchenette, tied into the main house utilities: every line itemized with crew hours.

Direct answer: Building a 600-square-foot detached ADU with one bedroom, one bath and a kitchenette has a direct job cost of $161,495 for this ADU in this example. At illustrative markups of 30% to 100%, that is a selling price of about $209,943 to $322,989. Direct job cost is labor and materials only, with no contractor overhead or profit, and is not a price: no contractor performs work at job cost. Permit and inspection fees are not included.
Clamp's Generate from description screen with the 600 sq ft ADU described in plain words

Describe it

Clamp's review draft for the 600 sq ft ADU: at a glance, what's included, what's not and what's assumed

Review the draft

The ADU in the Clamp app: described the way a homeowner would put it, then the review draft with what's included, what's not and what's assumed, before the itemized estimate. Sample data.

The job at a glance

One build, fully itemized, with crew hours.

BuildJob costLaborCrew hoursMaterialsIllustrative selling price
A. 600 sq ft, one bed, one bath$161,495$83,9121001 to 1209 h$56,469$209,943 to
$322,989

Dump fees and other costs ($21,114) are the same in every build and included in the job cost. Materials include allowances. Illustrative selling price is the job cost at a 30% to 100% markup; your price depends on your own overhead and profit. Labor hours are a planning range and include setup, daily cleanup and material runs; they are never a charge to the customer. Permit and inspection fees are not included; requirements vary by jurisdiction.

The build in detail

A. 600 sq ft, one bed, one bath: $161,495

Drawings, survey and temporary utilities; a slab foundation; framed walls and a truss roof with siding, shingles and vinyl windows; water and sewer trenched about 80 feet to the house lines and a subpanel fed from the house; a kitchenette, a tub shower bath, finishes and site restoration. Labor is $83,912 of the $161,495 job cost, or 52.0%. It is about 1001 to 1209 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Overhead×1.30Established×1.50Full-Service×2.00
Permits & PM172 to 292 h$19,610$25,493$29,415$39,220
Demo & Prep5 to 10 h$385$501$578$770
Sitework7 to 13 h$1,456$1,893$2,184$2,912
Masonry87 to 135 h$9,618$12,503$14,427$19,236
Plumbing56 to 74 h$7,354$9,560$11,031$14,708
Electrical75 to 96 h$11,310$14,703$16,965$22,620
HVAC17 to 30 h$3,400$4,420$5,100$6,800
Insulation12 to 22 h$1,047$1,361$1,571$2,094
Drywall75 to 129 h$4,995$6,494$7,493$9,990
Carpentry134 to 172 h$13,272$17,254$19,908$26,544
Tile22 to 34 h$1,881$2,445$2,822$3,762
Flooring14 to 30 h$1,237$1,608$1,855$2,474
Painting43 to 61 h$3,495$4,544$5,242$6,990
Appliances1 to 3 h$310$403$465$620
Exterior20 to 35 h$2,084$2,709$3,126$4,168
Roofing17 to 27 h$2,451$3,186$3,676$4,902
Landscapingunder 1 h$7$9$10$14
Setup, cleanup and material runs72 to 217 hin the prices
All labor1001 to 1209 h$83,912$109,086$125,868$167,824

Every line item

Labor $83,912 + materials and allowances $56,469 + dump fees and other $21,114 = $161,495 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Permits & PM
Daily Cleanup & Staging16ea36 to 76 h$3,520$0$3,520
Engineering Review Allowance1ea$0$0$850
Final Cleanup & Walkthrough2ea7 to 17 h$600$0$600
Final Punch Walk Labor1ea2 to 6 h$290$0$290
Jobsite Supervision Labor160hr104 to 216 h$15,200$0$15,200
Permits & PM subtotal172 to 292 h$20,460
Permits & PM subtotal172 to 292 h$20,460
Demo & Prep
Dumpster Rental Weekly2week$0$0$1,100
Floor Protection Setup Labor550sfunder 1 h$28$0$28
Site Protection, Minimal (per job)1eaunder 1 h$45$0$45
Site Protection Setup Labor0.78day4 to 9 h$312$0$312
Demo & Prep subtotal5 to 10 h$1,485
Demo & Prep subtotal5 to 10 h$1,485
Sitework
Excavation Equipment Rental1day$0$0$550
Excavation Labor16cubic_yard3 to 8 h$416$0$416
Excavation Spoils Export (Per Cubic Yard)10.25cubic_yard$0$0$431
Foundation Excavation (Machine, Per Cubic Yard)41cubic_yard$0$0$2,132
Portable Toilet Rental (per month)4month$0$0$900
Site Survey and Building Staking (per project)1ea$0$0$1,650
Trenching Labor80lf2 to 6 h$1,040$0$1,040
Sitework subtotal7 to 13 h$7,119
Sitework subtotal7 to 13 h$7,119
Masonry
Concrete Flatwork Install Labor624sf19 to 41 h$2,808$0$2,808
Concrete Flatwork MaterialsLabor on: Concrete Flatwork Install Labor686.4sf$0$3,604$3,604
Concrete Footing Install Labor98lf15 to 32 h$1,078$0$1,078
Concrete Footing MaterialsLabor on: Concrete Footing Install Labor107.8lf$0$1,563$1,563
Foundation Pour Labor9.73cubic_yard35 to 74 h$5,595$0$5,595
Foundation Pour MaterialsLabor on: Foundation Pour Labor10.7cubic_yard$0$3,049$3,049
Stone Install Consumables1ea$0$135$135
Under-Slab Rigid Insulation Lay (per sf)195.96sf1 to 4 h$137$0$137
Under-Slab Vapor Retarder (per sf)600sf$0$0$510
Masonry subtotal87 to 135 h$18,479
Masonry subtotal87 to 135 h$18,479
Plumbing
Alcove tub (tub only, no surround)Labor on: Fixture Set Labor1ea$0$450$450
Countertop Plumbing Coordination Labor1ea1 to 5 h$450$0$450
Expansion Tank AllowanceLabor on: Expansion Tank Service Labor1ea$0$85$85
Expansion Tank Service Labor1ea1 to 2 h$325$0$325
Faucet AllowanceLabor on: Fixture Set Labor1ea$0$250$250
Kitchen Sink AllowanceLabor on: Fixture Set Labor1ea$0$425$425
Lavatory Sink AllowanceLabor on: Fixture Set Labor1ea$0$225$225
Toilet AllowanceLabor on: Fixture Set Labor1ea$0$350$350
Fixture Set Labor3ea4 to 11 h$975$0$975
Lavatory faucet allowanceLabor on: Fixture Set Labor1ea$0$225$225
DWV MaterialsLabor on: Plumbing Rough-In Per Fixture107.8lf$0$674$674
Rough Plumbing ConsumablesLabor on: Plumbing Rough-In Per Fixture3ea$0$126$126
Plumbing Rough-In Per Fixture3ea7 to 17 h$1,350$0$1,350
Supply Pipe MaterialsLabor on: Supply Line Install Labor37.4lf$0$131$131
Sewer Cleanout Assembly AllowanceLabor on: Sewer Cleanout Install Labor2ea$0$312$312
Sewer Cleanout Install Labor2ea5 to 12 h$1,152$0$1,152
Sewer Pipe Lay in Open Trench (per lf)80lf10 to 22 h$1,120$0$1,120
Shower valve trim allowanceLabor on: Shower/Tub Valve Set1ea$0$285$285
Shower/Tub Valve Set1ea2 to 5 h$425$0$425
Shower Valve Rough-In Body AllowanceLabor on: Shower/Tub Valve Set1ea$0$200$200
Shutoff Valve Install1eaunder 1 h$145$0$145
Supply Line Install Labor10lf1 to 2 h$85$0$85
Alcove tub setting materialsLabor on: Fixture Set Labor1ea$0$65$65
Tub Waste and Overflow KitLabor on: Fixture Set Labor1ea$0$65$65
Tank Water Heater AllowanceLabor on: Tank Water Heater Install1ea$0$850$850
Water Heater Connection KitLabor on: Tank Water Heater Install1ea$0$63$63
Tank Water Heater Install1ea1 to 4 h$392$0$392
Water Service Pipe Install Labor80lf4 to 10 h$720$0$720
Water Service Pipe MaterialsLabor on: Water Service Pipe Install Labor88lf$0$484$484
Water Service Pressure Test Labor1ea1 to 3 h$215$0$215
Plumbing subtotal56 to 74 h$12,619
Plumbing subtotal56 to 74 h$12,619
Electrical
Bath Fan Duct Install Labor8lfunder 1 h$60$0$60
Bath Fan Duct MaterialsLabor on: Bath Fan Duct Install Labor9.2lf$0$25$25
Bath Fan Electrical Hookup Labor1each1 to 2 h$175$0$175
Bath Fan Termination Install Labor1each1 to 3 h$275$0$275
Bath Fan Termination MaterialsLabor on: Bath Fan Termination Install Labor1each$0$45$45
Bath Fan Housing Install Labor1each1 to 5 h$450$0$450
Bath Fan Testing & Commissioning1eachunder 1 h$85$0$85
Electrical Box ExtenderLabor on: Outlet Integration Labor2ea$0$7$7
Branch Circuit Install4ea8 to 18 h$1,700$0$1,700
New Branch Circuit (labor)4ea9 to 20 h$2,040$0$2,040
Dedicated Appliance Circuit1ea2 to 5 h$425$0$425
Dedicated Circuit Breaker AllowanceLabor on: Branch Circuit Install10ea$0$270$270
240V Outlet Install1ea1 to 4 h$285$0$285
Electrical Box and Device MaterialsLabor on: Electrical Rough-In Per Device28ea$0$238$238
Electrical Load Calculation Review1ea$0$0$400
Electrical Rough ConsumablesLabor on: Electrical Rough-In Per Device4ea$0$26$26
Electrical Rough-In Per Device24ea9 to 21 h$1,320$0$1,320
Feeder Cable MaterialsLabor on: Subpanel Feeder Run Labor115lf$0$489$489
Gfci Unit AllowanceLabor on: Outlet/Switch Install1ea$0$22$22
HVAC Condenser Disconnect1ea$0$35$35
Light Fixture AllowanceLabor on: Light Fixture Install2ea$0$300$300
Light Fixture Install4ea2 to 7 h$500$0$500
Lighting Dimmer AllowanceLabor on: Outlet/Switch Install1ea$0$32$32
NM Cable 10/3 (30 A, 240 V)Labor on: Branch Circuit Install46lf$0$85$85
NM Cable 6/3 (40 to 60 A, 240 V)Labor on: Branch Circuit Install46lf$0$195$195
Outlet Integration Labor1ea1 to 3 h$260$0$260
Outlet/Switch Install20ea4 to 11 h$1,300$0$1,300
Outlet Unit AllowanceLabor on: Outlet/Switch Install16ea$0$69$69
Recessed Can AllowanceLabor on: Recessed Light, New Work (open ceiling)9ea$0$195$195
Recessed Light, New Work (open ceiling)7ea2 to 6 h$595$0$595
Romex Wire MaterialsLabor on: Electrical Rough-In Per Device536.3lf$0$429$429
Smoke / CO Detector AllowanceLabor on: Smoke/CO Detector Install2ea$0$110$110
Smoke/CO Detector Install2ea1 to 3 h$170$0$170
Subpanel Equipment AllowanceLabor on: Subpanel Install Labor1ea$0$175$175
Subpanel Feeder Run Labor1ea3 to 7 h$720$0$720
Subpanel Install Labor1ea3 to 9 h$950$0$950
Switch Unit AllowanceLabor on: Outlet/Switch Install6ea$0$42$42
Underground Electrical Conduit (per lf)Labor on: Trenching Labor84lf$0$231$231
Electrical subtotal75 to 96 h$14,730
Electrical subtotal75 to 96 h$14,730
HVAC
Bathroom Exhaust Fan Unit AllowanceLabor on: Bath Fan Housing Install Labor1ea$0$215$215
Condensate Drain Install2ea1 to 5 h$600$0$600
Mini Split Heat Pump Install2ea10 to 22 h$1,900$0$1,900
HVAC Install Consumables1ea$0$285$285
Mini-Split Equipment Allowance (per 12,000 BTU zone)Labor on: Mini Split Heat Pump Install1ea$0$3,600$3,600
Radiant Underslab Insulation Board (per sf)Labor on: Under-Slab Rigid Insulation Lay (per sf)205.76sf$0$370$370
Refrigerant Line Set Install50lf2 to 7 h$900$0$900
Refrigerant Line MaterialsLabor on: Refrigerant Line Set Install57.5lf$0$489$489
HVAC subtotal17 to 30 h$8,359
HVAC subtotal17 to 30 h$8,359
Insulation
Air Sealing ConsumablesLabor on: Attic Floor Air Sealing (per sf of attic)1ls$0$450$450
Attic Floor Air Sealing (per sf of attic)600sf7 to 17 h$570$0$570
Attic Blown Insulation, Installed (per sf at R-49)600sf$0$0$990
Bath Fan Air Sealing Labor1eachunder 1 h$85$0$85
Eave Ventilation Baffle (per rafter bay)24ea1 to 4 h$192$0$192
Insulation Dam Install Labor1eaunder 1 h$82$0$82
Insulation Dam MaterialsLabor on: Insulation Dam Install Labor1ea$0$75$75
Rim and Sill Air Sealing Labor98lf1 to 3 h$118$0$118
Wall Batt Insulation, Installed (per sf)783.84sf$0$0$1,137
Insulation subtotal12 to 22 h$3,699
Insulation subtotal12 to 22 h$3,699
Drywall
Drywall Finish Labor2220sf43 to 90 h$3,330$0$3,330
Drywall Hang Labor2220sf23 to 48 h$1,665$0$1,665
Drywall Sheets MaterialsLabor on: Drywall Hang Labor2442sf$0$1,832$1,832
Drywall subtotal75 to 129 h$6,827
Drywall subtotal75 to 129 h$6,827
Carpentry
Bathroom Accessory AllowanceLabor on: Bathroom Accessory Install Labor3ea$0$195$195
Bathroom Accessory Install Labor3ea1 to 2 h$144$0$144
Blower Door Test Allowance1ea$0$0$425
Cabinet Fillers, End Panels and Toe KickLabor on: Cabinet Install Labor7lf$0$420$420
Cabinet Install Labor7lf3 to 8 h$456$0$456
Door Lock Hardware AllowanceLabor on: Exterior Door Install1each$0$150$150
Door/Window Unit AllowanceLabor on: Exterior Door Install1ea$0$950$950
Exterior Door Install1ea6 to 14 h$675$0$675
Exterior Trim Install18lf1 to 2 h$81$0$81
Exterior Wall Framing MaterialsLabor on: Stud Wall Framing Install102.88lf$0$1,389$1,389
Framing Fasteners and HardwareLabor on: Stud Wall Framing Install90lf$0$99$99
Sheathing Install1533.84sf11 to 25 h$1,917$0$1,917
Stud Wall Framing Install157.98lf20 to 43 h$2,607$0$2,607
Interior Door Hardware AllowanceLabor on: Interior Door Install4each$0$340$340
Interior Door Install4ea5 to 13 h$900$0$900
Interior Door Slab AllowanceLabor on: Interior Door Install4each$0$330$330
Door Threshold Transition Labor1eachunder 1 h$75$0$75
Partition Door Rough Opening1eaunder 1 h$105$0$105
Permit Drawing Set (Design and Drafting)1ea$0$0$5,625
Roof Trusses and Roof Sheathing Materials (per roofing square)Labor on: Roof Truss Set and Brace (per roofing square)7.88square$0$3,822$3,822
Roof Truss Set and Brace (per roofing square)7.5square7 to 17 h$1,350$0$1,350
Shower Curtain Rod AllowanceLabor on: Shower Curtain Rod Install Labor1ea$0$120$120
Shower Curtain Rod Install Labor1eaunder 1 h$135$0$135
Soffit and Fascia Install98lf8 to 19 h$833$0$833
Stud Wall Framing MaterialsLabor on: Stud Wall Framing Install66lf$0$445$445
Baseboard and Casing Install294lf7 to 16 h$1,249$0$1,249
Trim MaterialsLabor on: Baseboard and Casing Install459.4lf$0$965$965
Vanity Install Labor1ea3 to 7 h$537$0$537
Wall Sheathing MaterialsLabor on: Sheathing Install862.22sf$0$819$819
Window Caulk & Flash MaterialsLabor on: Window Install7each$0$336$336
Window and Door Install ConsumablesLabor on: Exterior Door Install1ea$0$48$48
Window Exterior Trim MaterialsLabor on: Exterior Trim Install18lf$0$58$58
Window Install7ea17 to 37 h$1,683$0$1,683
Window Stool and Apron Stock (per window)Labor on: Window Stool and Apron Install7ea$0$171$171
Window Stool and Apron Install7ea2 to 6 h$525$0$525
Window Unit AllowanceLabor on: Window Install7each$0$2,012$2,012
Carpentry subtotal134 to 172 h$31,991
Carpentry subtotal134 to 172 h$31,991
Tile
Tile Grout Install Labor110sf3 to 7 h$193$0$193
Tile Grout MaterialsLabor on: Tile Grout Install Labor110sf$0$50$50
Bathroom Tile Install Labor110sf9 to 20 h$1,100$0$1,100
Bathroom Tile Material AllowanceLabor on: Bathroom Tile Install Labor55sf$0$303$303
Bath Tile Setting MaterialsLabor on: Bathroom Tile Install Labor121sf$0$103$103
Bathroom Tile Substrate MaterialsLabor on: Bathroom Tile Substrate Prep Labor110sf$0$164$164
Bathroom Tile Substrate Prep Labor110sf3 to 7 h$358$0$358
Tile Waterproofing Install Labor60sf1 to 4 h$135$0$135
Bath Tile Waterproofing MaterialsLabor on: Tile Waterproofing Install Labor60sf$0$117$117
Bathroom wall tile material allowanceLabor on: Bathroom Tile Install Labor66sf$0$429$429
Tile Grout Sealer9sfunder 1 h$5$0$5
Tile Material AllowanceLabor on: Wall Tile Install9sf$0$49$49
Tile Setting MaterialsLabor on: Wall Tile Install9sf$0$17$17
Wall Tile Install9sf1 to 2 h$90$0$90
Tile subtotal22 to 34 h$3,113
Tile subtotal22 to 34 h$3,113
Flooring
Floor Transition MaterialsLabor on: Door Threshold Transition Labor1ea$0$35$35
Floor Underlayment Materials550sf$0$303$303
Flooring Install Consumables1ea$0$85$85
LVP/LVT Install550sf14 to 30 h$1,237$0$1,237
LVP/LVT Material AllowanceLabor on: LVP/LVT Install605sf$0$2,117$2,117
Flooring subtotal14 to 30 h$3,777
Flooring subtotal14 to 30 h$3,777
Painting
Interior Ceiling Paint Apply Labor600sf3 to 8 h$480$0$480
Interior Door Paint (per door)4ea3 to 7 h$420$0$420
Interior Paint Apply Labor1620sf11 to 25 h$972$0$972
Paint Hardware Removal Labor1eaunder 1 h$7$0$7
Paint Masking Setup Labor1620sfunder 1 h$16$0$16
Premium Paint AllowanceLabor on: Interior Paint Apply Labor16.14gallon$0$775$775
Paint Prep Labor1620sf2 to 6 h$178$0$178
Paint Primer Application Labor2220sf4 to 10 h$666$0$666
Paint and Primer MaterialsLabor on: Paint Primer Application Labor7.38gallon$0$236$236
Paint Sundries Materials1ls$0$150$150
Trim Caulk and Filler MaterialsLabor on: Trim Paint Apply Labor472lf$0$104$104
Trim Paint Apply Labor336lf7 to 17 h$756$0$756
Painting subtotal43 to 61 h$4,760
Painting subtotal43 to 61 h$4,760
Vanity & Fixtures
Cabinet Hardware (per piece)11ea$0$94$94
Cabinet Install Fasteners and ShimsLabor on: Cabinet Install Labor11lf$0$30$30
Cabinet Material AllowanceLabor on: Cabinet Install Labor7lf$0$2,275$2,275
Fixture Set MaterialsLabor on: Fixture Set Labor3ea$0$135$135
Stone Countertop Fabrication21.6sf$0$0$648
Stone Countertop Install21.6sf$0$0$475
Stone Countertop Material AllowanceLabor on: Vanity Install Labor21.6sf$0$1,188$1,188
Vanity Cabinet AllowanceLabor on: Vanity Install Labor4lf$0$1,280$1,280
Vanity & Fixtures subtotal$6,125
Vanity & Fixtures subtotal$6,125
Appliances
Range Set and Connect1ea1 to 2 h$185$0$185
Range Unit AllowanceLabor on: Range Set and Connect1ea$0$1,400$1,400
Refrigerator Install Labor1ea1 to 2 h$125$0$125
Refrigerator Unit AllowanceLabor on: Refrigerator Install Labor1ea$0$2,200$2,200
Appliances subtotal1 to 3 h$3,910
Appliances subtotal1 to 3 h$3,910
Exterior
Exterior Caulking and Sealing Labor80lf1 to 4 h$140$0$140
House Wrap Install Labor784sf4 to 9 h$298$0$298
House Wrap MaterialsLabor on: House Wrap Install Labor862.4sf$0$362$362
Soffit and Fascia MaterialsLabor on: Soffit and Fascia Install98lf$0$833$833
Vinyl Siding Install Labor784sf12 to 26 h$1,646$0$1,646
Vinyl Siding MaterialsLabor on: Vinyl Siding Install Labor862.4sf$0$2,673$2,673
Exterior subtotal20 to 35 h$5,952
Exterior subtotal20 to 35 h$5,952
Specialty
Temporary Utilities Setup1ea$0$0$1,150
Utility Locate Service1ea$0$0$450
Specialty subtotal$1,600
Specialty subtotal$1,600
General
Generic Install Consumables1ls$0$85$85
General subtotal$85
General subtotal$85
Roofing
Asphalt Shingle Install Labor6.9square7 to 15 h$1,311$0$1,311
Asphalt Shingle MaterialsLabor on: Asphalt Shingle Install Labor7.59square$0$1,328$1,328
Downspout Install Labor2ea1 to 3 h$150$0$150
Downspout MaterialsLabor on: Downspout Install Labor2ea$0$110$110
Drip Edge MaterialsLabor on: Asphalt Shingle Install Labor110.32lf$0$105$105
Gutter Install Labor54lf2 to 6 h$297$0$297
Gutter MaterialsLabor on: Gutter Install Labor59.4lf$0$327$327
Ice Water Shield Install Labor1.04squnder 1 h$47$0$47
Ice Water Shield MaterialsLabor on: Ice Water Shield Install Labor1.04sq$0$99$99
Ridge Vent Install Labor31.52lf1 to 2 h$79$0$79
Ridge Vent MaterialsLabor on: Ridge Vent Install Labor31.52lf$0$134$134
Synthetic Underlayment Install Labor6.9square1 to 3 h$207$0$207
Synthetic Underlayment Materials7.25square$0$109$109
Vent Boot AllowanceLabor on: Vent Boot Replacement Labor2each$0$44$44
Vent Boot Replacement Labor2each1 to 3 h$360$0$360
Roofing subtotal17 to 27 h$4,707
Roofing subtotal17 to 27 h$4,707
Landscaping
Site Grading Labor12sfunder 1 h$7$0$7
Trench Surface Restoration (per lf)178lf$0$0$1,691
Landscaping subtotalunder 1 h$1,698
Landscaping subtotalunder 1 h$1,698
DIRECT JOB COST1001 to 1209 h$161,495
DIRECT JOB COST1001 to 1209 h$161,495

Methodology & reproducibility

One reviewed snapshot for this build. The build is frozen from its own estimate run and priced by the published pricer.

Direct cost equals the sum of each row’s rounded quantity × (labor + material + other). Amounts are shown in whole dollars; every column adds to its total.

Scope selection, prose accuracy, arithmetic and provenance mapping reviewed; not independent market-rate verification.

Questions

Why does an ADU cost more per square foot than a house?

An ADU carries a full kitchen line, a bath, a foundation, a roof and utility runs over only 600 feet, plus drawings and site work a bigger house spreads over more area. Small buildings always price high per foot.

What can push this job higher?

Separate utility meters, a long or uphill sewer run that needs a pump, a panel upgrade at the main house, a steep or rocky site, or impact and tap fees, which this page excludes because they vary so much by town.

Is the markup on top of this?

Yes. Direct job cost is what the ADU costs a contractor to perform. The markup table shows what it sells for at illustrative markups of 30% to 100%.