Detached Garage Cost: 30x36 With a Mini-Split, Itemized (2026 Baseline)

A 30x36 detached garage on a slab with a truss roof, vinyl siding, two 10x8 doors, a new electric service and a mini-split, itemized with crew hours.

Direct answer: Building a 30x36 detached garage with power and a mini-split has a direct job cost of $81,247 for this garage in this example. At illustrative markups of 30% to 100%, that is a selling price of about $105,622 to $162,495. Direct job cost is labor and materials only, with no contractor overhead or profit, and is not a price: no contractor performs work at job cost. Permit and inspection fees are not included.
Clamp's Generate from description screen with the 30x36 garage described in plain words

Describe it

Clamp's review draft for the 30x36 garage: at a glance, what's included, what's not and what's assumed

Review the draft

The garage in the Clamp app: described the way a builder would text it, then the review draft with what's included, what's not and what's assumed, before the itemized estimate. Sample data.

The job at a glance

One build, fully itemized, with crew hours.

BuildJob costLaborCrew hoursMaterialsIllustrative selling price
A. 30x36 slab garage, mini-split$81,247$30,908437 to 543 h$45,193$105,622 to
$162,495

Dump fees and other costs ($5,146) are the same in every build and included in the job cost. Materials include allowances. Illustrative selling price is the job cost at a 30% to 100% markup; your price depends on your own overhead and profit. Labor hours are a planning range and include setup, daily cleanup and material runs; they are never a charge to the customer. Permit and inspection fees are not included; requirements vary by jurisdiction.

The build in detail

A. 30x36 slab garage, mini-split: $81,247

Footings, frost wall and a 1,080 sq ft slab; framed walls and a truss roof with shingles, vinyl siding and gutters; two insulated 10x8 overhead doors with openers and an entry door; a new electric service with lights and outlets; an 18,000 BTU mini-split; grading and sod. Labor is $30,908 of the $81,247 job cost, or 38.0%. It is about 437 to 543 hours of work, including setup, daily cleanup and material runs.

Labor cost by trade

Labor only. Materials, allowances and dump fees are in the line items below. Hours are person-hours at typical production from Clamp’s labor hours catalog, as a range: a planning figure, not a schedule and not a charge to the customer.

TradeHoursLabor costLow-Overhead×1.30Established×1.50Full-Service×2.00
Sitework1 to 2 h$187$243$281$374
Masonry122 to 190 h$7,649$9,944$11,474$15,298
Electrical43 to 59 h$5,798$7,537$8,697$11,596
HVAC8 to 15 h$1,562$2,031$2,343$3,124
Carpentry105 to 145 h$9,151$11,896$13,727$18,302
Exterior21 to 44 h$2,451$3,186$3,676$4,902
Roofing27 to 44 h$3,419$4,445$5,128$6,838
Landscaping9 to 19 h$691$898$1,036$1,382
Setup, cleanup and material runs31 to 96 hin the prices
All labor437 to 543 h$30,908$40,180$46,362$61,816

Every line item

Labor $30,908 + materials and allowances $45,193 + dump fees and other $5,146 = $81,247 direct job cost. Hours are person-hours at typical production, on labor rows only, and the direct-cost row adds about 15% for setup, daily cleanup and material runs; an allowance or material row names the labor line that installs it, and a subcontract row has none, because the sub’s price includes their own time. Some labor quantities include a difficulty factor, so they can exceed the measured area; each row’s derivation is in the downloadable data.

ItemQtyUnitHoursLaborMaterialLine cost
Demo & Prep
Dumpster Rental Weekly1week$0$0$550
Demo & Prep subtotal$550
Demo & Prep subtotal$550
Sitework
Excavation Spoils Export (Per Cubic Yard)29.5cubic_yard$0$0$1,033
Foundation Excavation (Machine, Per Cubic Yard)59cubic_yard$0$0$944
Trenching Labor50lf1 to 2 h$187$0$187
Sitework subtotal1 to 2 h$2,164
Sitework subtotal1 to 2 h$2,164
Masonry
Concrete Flatwork Install Labor1080sf33 to 70 h$3,348$0$3,348
Concrete Flatwork MaterialsLabor on: Concrete Flatwork Install Labor1188sf$0$6,237$6,237
Concrete Footing Install Labor131lf20 to 43 h$1,376$0$1,376
Concrete Footing MaterialsLabor on: Concrete Footing Install Labor144.1lf$0$2,089$2,089
Foundation Pour Labor13cubic_yard47 to 99 h$2,925$0$2,925
Foundation Pour MaterialsLabor on: Foundation Pour Labor14.3cubic_yard$0$4,076$4,076
Under-Slab Vapor Retarder (per sf)1080sf$0$0$594
Masonry subtotal122 to 190 h$20,645
Masonry subtotal122 to 190 h$20,645
Electrical
Branch Circuit Install2ea4 to 9 h$540$0$540
New Branch Circuit (labor)1ea1 to 4 h$312$0$312
Dedicated Circuit Breaker AllowanceLabor on: Branch Circuit Install3ea$0$72$72
Electrical Box and Device MaterialsLabor on: Electrical Rough-In Per Device22ea$0$187$187
Electrical Rough ConsumablesLabor on: Electrical Rough-In Per Device2ea$0$13$13
Electrical Rough-In Per Device2ea1 to 2 h$84$0$84
Feeder Cable Materials63lf$0$268$268
Garage Door Opener (per opener)Labor on: Garage Door Opener Install Labor2ea$0$650$650
HVAC Condenser Disconnect1ea$0$35$35
Add Light or Fan Box (rough-in)10ea9 to 21 h$1,350$0$1,350
Light Fixture AllowanceLabor on: Light Fixture Install10ea$0$1,500$1,500
Light Fixture Install10ea5 to 12 h$850$0$850
Meter Socket AllowanceLabor on: Service Meter and Riser Install1ea$0$150$150
Add Outlet or Switch Box (rough-in)2ea1 to 4 h$230$0$230
Romex Wire MaterialsLabor on: Electrical Rough-In Per Device235.75lf$0$189$189
Service Meter and Riser Install1ea4 to 10 h$1,200$0$1,200
Service Panel AllowanceLabor on: Service Panel Install Labor1ea$0$589$589
Service Panel Install Labor1ea4 to 11 h$1,232$0$1,232
Switch Unit AllowanceLabor on: Add Outlet or Switch Box (rough-in)2ea$0$9$9
Underground Electrical Conduit (per lf)Labor on: Trenching Labor52.5lf$0$144$144
Electrical subtotal43 to 59 h$9,604
Electrical subtotal43 to 59 h$9,604
HVAC
Condensate Drain Install1ea1 to 3 h$150$0$150
Mini Split Heat Pump Install1ea5 to 11 h$1,200$0$1,200
HVAC Install Consumables1ea$0$285$285
Mini-Split Equipment Allowance (per 12,000 BTU zone)Labor on: Mini Split Heat Pump Install1ea$0$3,600$3,600
Refrigerant Line Set Install25lf1 to 4 h$212$0$212
Refrigerant Line MaterialsLabor on: Refrigerant Line Set Install28.75lf$0$244$244
HVAC subtotal8 to 15 h$5,691
HVAC subtotal8 to 15 h$5,691
Carpentry
Door Lock Hardware AllowanceLabor on: Exterior Door Install1each$0$95$95
Door/Window Unit AllowanceLabor on: Exterior Door Install1ea$0$450$450
Engineered Beam Material AllowanceLabor on: Engineered Beam Install2ea$0$1,558$1,558
Exterior Door Install1ea2 to 5 h$500$0$500
Exterior Trim Install18lf1 to 2 h$77$0$77
Exterior Wall Framing MaterialsLabor on: Stud Wall Framing Install138.03lf$0$2,330$2,330
Engineered Beam Install2ea7 to 15 h$1,558$0$1,558
Sheathing Install2664.53sf20 to 44 h$2,931$0$2,931
Stud Wall Framing Install164.32lf21 to 45 h$1,643$0$1,643
Garage Door Install (per door)2ea10 to 22 h$965$0$965
Garage Door Opener Install Labor2ea4 to 10 h$330$0$330
Garage Door Unit (per door)Labor on: Garage Door Install (per door)2ea$0$2,794$2,794
Permit Drawing Set (Design and Drafting)1ea$0$0$2,025
Roof Trusses and Roof Sheathing Materials (per roofing square)Labor on: Roof Truss Set and Brace (per roofing square)14.18square$0$6,877$6,877
Roof Truss Set and Brace (per roofing square)13.5square14 to 30 h$1,147$0$1,147
Wall Sheathing MaterialsLabor on: Sheathing Install1445.99sf$0$1,374$1,374
Window and Door Install ConsumablesLabor on: Exterior Door Install1ea$0$48$48
Window Exterior Trim MaterialsLabor on: Exterior Trim Install18lf$0$58$58
Carpentry subtotal105 to 145 h$26,760
Carpentry subtotal105 to 145 h$26,760
Exterior
Exterior Caulking and Sealing Labor20lfunder 1 h$29$0$29
Vinyl Siding Install Labor1309sf20 to 43 h$2,422$0$2,422
Vinyl Siding MaterialsLabor on: Vinyl Siding Install Labor1439.9sf$0$4,464$4,464
Exterior subtotal21 to 44 h$6,915
Exterior subtotal21 to 44 h$6,915
Roofing
Asphalt Shingle Install Labor13.5square14 to 30 h$2,430$0$2,430
Asphalt Shingle MaterialsLabor on: Asphalt Shingle Install Labor14.85square$0$2,599$2,599
Downspout Install Labor2ea1 to 3 h$110$0$110
Downspout MaterialsLabor on: Downspout Install Labor2ea$0$110$110
Drip Edge MaterialsLabor on: Asphalt Shingle Install Labor154.32lf$0$147$147
Gutter Install Labor70lf3 to 8 h$315$0$315
Gutter MaterialsLabor on: Gutter Install Labor77lf$0$424$424
Ice Water Shield Install Labor2.03sq1 to 3 h$73$0$73
Ice Water Shield MaterialsLabor on: Ice Water Shield Install Labor2.03sq$0$193$193
Ridge Vent Install Labor44.09lf1 to 2 h$86$0$86
Ridge Vent MaterialsLabor on: Ridge Vent Install Labor44.09lf$0$187$187
Synthetic Underlayment Install Labor13.5square2 to 6 h$405$0$405
Synthetic Underlayment Materials14.18square$0$213$213
Roofing subtotal27 to 44 h$7,292
Roofing subtotal27 to 44 h$7,292
Landscaping
Site Grading Labor1048sf1 to 2 h$115$0$115
Sod Install Labor1048sf8 to 17 h$576$0$576
Sod MaterialsLabor on: Sod Install Labor1100.4sf$0$935$935
Landscaping subtotal9 to 19 h$1,626
Landscaping subtotal9 to 19 h$1,626
DIRECT JOB COST437 to 543 h$81,247
DIRECT JOB COST437 to 543 h$81,247

Methodology & reproducibility

One reviewed snapshot for this build. The build is frozen from its own estimate run and priced by the published pricer.

Direct cost equals the sum of each row’s rounded quantity × (labor + material + other). Amounts are shown in whole dollars; every column adds to its total.

Scope selection, prose accuracy, arithmetic and provenance mapping reviewed; not independent market-rate verification.

Questions

Why is there a new electric service?

There is no house on the lot yet. The garage gets its own service and panel from the utility at the property, which is a real part of the cost on a phased lot.

What can push this job higher?

A taller building or a second floor, insulation and finished interior walls, plumbing, a concrete apron or driveway, or poor soil that needs deeper footings. Each is its own line.

Is the markup on top of this?

Yes. Direct job cost is what the garage costs a contractor to perform. The markup table shows what it sells for at illustrative markups of 30% to 100%.