Mechanics liens · District of Columbia

District of Columbia Mechanics Lien Deadline (2026): 90 Days after Completion for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in District of Columbia, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 90 days after completion. For a last day of work on Friday, November 20, 2026, record it by Thu, Feb 18, 2027 and sue by Tue, Aug 17, 2027. None. You owe the homeowner no notice before or during the job.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in District of Columbia

Record the lien

90 days after completion

Record a notice of intent to lien during the job or within 90 days after completion or termination, whichever is first. Mail the homeowner a copy within 5 business days.

Sue to enforce it

180 days after recording

Sue within 180 days after recording the notice of intent. Record notice of the lawsuit within 10 days of suing.

Notice to the homeowner

No notice needed

None. You owe the homeowner no notice before or during the job.

Homeowner rules

Check first

If you worked under a home improvement contract, include a copy of it with your notice of intent.

Source: D.C. Code 40-301.02, 40-303.13 (Official DC Council Code site, current text (last amended D.C. Law 23-269, 2021))

“within 90 days after the earlier of the completion or termination of the project”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jun 11, 2026Dec 8, 2026
Jul 31, 2026Oct 29, 2026Apr 27, 2027
Nov 20, 2026Feb 18, 2027Aug 17, 2027

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

District of Columbia lien questions

How long do I have to file a mechanics lien in District of Columbia?

Record a notice of intent to lien during the job or within 90 days after completion or termination, whichever is first. Mail the homeowner a copy within 5 business days.

How long does a mechanics lien last in District of Columbia?

Sue within 180 days after recording the notice of intent. Record notice of the lawsuit within 10 days of suing.

Does a contractor need to send a notice before filing a lien in District of Columbia?

None. You owe the homeowner no notice before or during the job.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .