Delaware Mechanics Lien Deadline (2026): 180 Days after Completion for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Delaware, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 180 days after completion. For a last day of work on Friday, November 20, 2026, record it by Wed, May 19, 2027. None. No early notice applies when the homeowner hired you directly.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Delaware

Record the lien

180 days after completion

File in Superior Court within 180 days after completion. Other dates, like your final invoice or homeowner acceptance, also count. Attach the contract if it fixes the price.

Sue to enforce it

See the rule

Filing the claim in Superior Court is the lawsuit. There is no separate deadline to sue.

Notice to the homeowner

No notice needed

None. No early notice applies when the homeowner hired you directly.

Homeowner rules

No special rule

None

Source: 25 Del. C. 2711, 2712 (Official Delaware Code online, Title 25 ch. 27 subch. II; sections last amended by 84 Del. Laws c. 42)

“within 180 days after the completion of such structure”

Delaware statute 25 Del. C. 2711, 2712 (Official Delaware Code online, Title 25 ch. 27 subch. II; sections last amended by 84 Del. Laws c. 42)

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Sep 9, 2026See the rule
Jul 31, 2026Jan 27, 2027See the rule
Nov 20, 2026May 19, 2027See the rule

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Delaware lien questions

How long do I have to file a mechanics lien in Delaware?

File in Superior Court within 180 days after completion. Other dates, like your final invoice or homeowner acceptance, also count. Attach the contract if it fixes the price.

How long does a mechanics lien last in Delaware?

Filing the claim in Superior Court is the lawsuit. There is no separate deadline to sue.

Does a contractor need to send a notice before filing a lien in Delaware?

None. No early notice applies when the homeowner hired you directly.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .