Georgia Mechanics Lien Deadline (2026): 90 Days after Completion for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Georgia, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 90 days after completion. For a last day of work on Friday, November 20, 2026, record it by Thu, Feb 18, 2027 and sue by Fri, Feb 18, 2028. None. An optional notice of lien rights is allowed but not needed to enforce your lien.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Georgia

Record the lien

90 days after completion

File within 90 days after the work is complete. Mail the homeowner a copy within 2 business days. The claim must state the homeowner's right to contest it.

Sue to enforce it

365 days after recording

Sue within 365 days after filing the claim. Then file a notice of the lawsuit with the clerk within 30 days.

Notice to the homeowner

No notice needed

None. An optional notice of lien rights is allowed but not needed to enforce your lien.

Homeowner rules

No special rule

None If the work needs a state residential or general contractor license and you lack one, you can't enforce the contract.

Source: O.C.G.A. 44-14-361.1, 44-14-361.3, 44-14-361.5, 44-14-367 (FindLaw mirror of O.C.G.A. 44-14-361.1 (current as of March 28, 2024); Justia 2024/2025 for 44-14-361.3)

“within 90 days after the completion of the work”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jun 11, 2026Jun 11, 2027
Jul 31, 2026Oct 29, 2026Oct 29, 2027
Nov 20, 2026Feb 18, 2027Feb 18, 2028

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Also check

Georgia lien questions

How long do I have to file a mechanics lien in Georgia?

File within 90 days after the work is complete. Mail the homeowner a copy within 2 business days. The claim must state the homeowner's right to contest it.

How long does a mechanics lien last in Georgia?

Sue within 365 days after filing the claim. Then file a notice of the lawsuit with the clerk within 30 days.

Does a contractor need to send a notice before filing a lien in Georgia?

None. An optional notice of lien rights is allowed but not needed to enforce your lien.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .