Mechanics liens · Idaho

Idaho Mechanics Lien Deadline (2026): 90 Days after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Idaho, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 90 days after last work. For a last day of work on Friday, November 20, 2026, record it by Thu, Feb 18, 2027 and sue by Wed, Aug 18, 2027. On home contracts over $2,000, give the homeowner the state disclosure statement and get a signed acknowledgment before signing the contract.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Idaho

Record the lien

90 days after last work

File within 90 days after you finish your labor or last supply materials. Serve the homeowner a copy within 5 business days after filing.

Sue to enforce it

6 months after recording

The lien stops binding the property 6 months after filing unless you start foreclosure within that time.

Notice to the homeowner

Disclosure before signing

On home contracts over $2,000, give the homeowner the state disclosure statement and get a signed acknowledgment before signing the contract.

Homeowner rules

Check first

Disclosures apply to 1 to 4 unit home contracts over $2,000. Your lien claim must include proof of the disclosures and the homeowner's signed acknowledgment. If you weren't registered with the state for the whole job, you can't sue to collect.

Source: Idaho Code 45-507, 45-510, 45-525 (Official Idaho Legislature statutes site; 45-507 last amended 2022, 45-510 last amended 2015)

“filed within ninety (90) days after the completion of the labor”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jun 11, 2026Dec 11, 2026
Jul 31, 2026Oct 29, 2026Apr 29, 2027
Nov 20, 2026Feb 18, 2027Aug 18, 2027

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Also check

Idaho lien questions

How long do I have to file a mechanics lien in Idaho?

File within 90 days after you finish your labor or last supply materials. Serve the homeowner a copy within 5 business days after filing.

How long does a mechanics lien last in Idaho?

The lien stops binding the property 6 months after filing unless you start foreclosure within that time.

Does a contractor need to send a notice before filing a lien in Idaho?

On home contracts over $2,000, give the homeowner the state disclosure statement and get a signed acknowledgment before signing the contract.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.