Mechanics liens · Washington

Washington Mechanics Lien Deadline (2026): 90 Days after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Washington, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 90 days after last work. For a last day of work on Friday, November 20, 2026, record it by Thu, Feb 18, 2027 and sue by Mon, Oct 18, 2027. On jobs of $1,000 or more, give the homeowner the state disclosure statement before work starts or you have no lien. No notice of right to lien needed.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Washington

Record the lien

90 days after last work

Record within 90 days after you last supply labor, services, materials, or equipment. Serve the homeowner a copy within 14 days or lose attorney fees.

Sue to enforce it

8 months after recording

Sue to foreclose within 8 calendar months after recording and serve within 90 days of filing, or the lien expires.

Notice to the homeowner

Disclosure before work starts

On jobs of $1,000 or more, give the homeowner the state disclosure statement before work starts or you have no lien. No notice of right to lien needed.

Homeowner rules

Check first

On an existing owner-occupied single-family home, you need no notice of right to lien. The disclosure statement is required for home jobs of $1,000 or more. You must be registered as a contractor to sue. Proof of the disclosure statement is needed to keep a lien.

Source: RCW 60.04.031, 60.04.091, 60.04.141, 18.27.114, 18.27.080 (Official RCW pages (app.leg.wa.gov, lawfilesext.leg.wa.gov); 60.04.091 last amended 1992, 18.27.114 last amended 2020)

“not later than ninety days after the person has ceased to furnish labor”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jun 11, 2026Feb 11, 2027
Jul 31, 2026Oct 29, 2026Jun 29, 2027
Nov 20, 2026Feb 18, 2027Oct 18, 2027

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Also check

Washington lien questions

How long do I have to file a mechanics lien in Washington?

Record within 90 days after you last supply labor, services, materials, or equipment. Serve the homeowner a copy within 14 days or lose attorney fees.

How long does a mechanics lien last in Washington?

Sue to foreclose within 8 calendar months after recording and serve within 90 days of filing, or the lien expires.

Does a contractor need to send a notice before filing a lien in Washington?

On jobs of $1,000 or more, give the homeowner the state disclosure statement before work starts or you have no lien. No notice of right to lien needed.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.