Mechanics liens · Iowa

Iowa Mechanics Lien Deadline (2026): 90 Days after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Iowa, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 90 days after last work. For a last day of work on Friday, November 20, 2026, record it by Thu, Feb 18, 2027 and sue by Sun, Feb 18, 2029. If you use subs, give the homeowner the state's bold notice with the registry web address and phone. Post a commencement notice on the registry within 10 days of starting.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Iowa

Record the lien

90 days after last work

Post on the state lien registry within 90 days of last work. Later posts, up to 2 years 90 days, need personal service and cover only the unpaid balance.

Sue to enforce it

2 years after the deadline

Sue within 2 years after the 90-day posting period ends. If the homeowner demands it, sue within 30 days or lose the lien.

Notice to the homeowner

Notice and registry posting

If you use subs, give the homeowner the state's bold notice with the registry web address and phone. Post a commencement notice on the registry within 10 days of starting.

Homeowner rules

Check first

For single- and two-family homes, skipping the required homeowner notice or the commencement notice means no lien. The lien covers only counties named in your posted notices.

Source: Iowa Code 572.8, 572.9, 572.10, 572.11, 572.13, 572.13A, 572.27, 572.28, 572.34(11) (Official Iowa Legislature site, Iowa Code 2026, chapter 572 PDF)

“within two years and ninety days after the date”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jun 11, 2026Jun 11, 2028
Jul 31, 2026Oct 29, 2026Oct 29, 2028
Nov 20, 2026Feb 18, 2027Feb 18, 2029

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Iowa lien questions

How long do I have to file a mechanics lien in Iowa?

Post on the state lien registry within 90 days of last work. Later posts, up to 2 years 90 days, need personal service and cover only the unpaid balance.

How long does a mechanics lien last in Iowa?

Sue within 2 years after the 90-day posting period ends. If the homeowner demands it, sue within 30 days or lose the lien.

Does a contractor need to send a notice before filing a lien in Iowa?

If you use subs, give the homeowner the state's bold notice with the registry web address and phone. Post a commencement notice on the registry within 10 days of starting.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.