Mechanics liens · Missouri

Missouri Mechanics Lien Deadline (2026): 6 Months after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Missouri, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 6 months after last work. For a last day of work on Friday, November 20, 2026, record it by Thu, May 20, 2027 and sue by Sat, Nov 20, 2027. Before any payment, give the homeowner the state notice to owner in 10-point bold. Use the contract, delivery, start of work, or first invoice.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Missouri

Record the lien

6 months after last work

File with the circuit clerk within 6 months after the debt accrued, generally your last day of work or materials.

Sue to enforce it

6 months after recording

Sue within 6 months after filing the lien.

Notice to the homeowner

Notice before first payment

Before any payment, give the homeowner the state notice to owner in 10-point bold. Use the contract, delivery, start of work, or first invoice.

Homeowner rules

Check first

The notice is required for any lien by a contractor hired by the owner, not just on homes. Separate owner-occupied rules govern subcontractors and suppliers.

Source: RSMo 429.012, 429.080, 429.170 (Missouri Revisor of Statutes section pages: 429.080 (eff. 8/28/2007), 429.012 (eff. 1/1/2017), 429.170 (eff. 8/28/1959))

“within six months after the indebtedness shall have accrued”

Missouri statute RSMo 429.012, 429.080, 429.170 (Missouri Revisor of Statutes section pages: 429.080 (eff. 8/28/2007), 429.012 (eff. 1/1/2017), 429.170 (eff. 8/28/1959))

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Sep 13, 2026Mar 13, 2027
Jul 31, 2026Jan 31, 2027Jul 31, 2027
Nov 20, 2026May 20, 2027Nov 20, 2027

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Missouri lien questions

How long do I have to file a mechanics lien in Missouri?

File with the circuit clerk within 6 months after the debt accrued, generally your last day of work or materials.

How long does a mechanics lien last in Missouri?

Sue within 6 months after filing the lien.

Does a contractor need to send a notice before filing a lien in Missouri?

Before any payment, give the homeowner the state notice to owner in 10-point bold. Use the contract, delivery, start of work, or first invoice.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.