Kansas Mechanics Lien Deadline (2026): 4 Months after Last Work for Remodelers
How long a remodeler hired by the homeowner has to record a mechanics lien in Kansas, what notice comes first, and the deadline to sue, worked on three dates.
Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.
The rule in Kansas
4 months after last work
File a sworn lien statement with the district court clerk within 4 months after your last labor or materials. The 1-month extension does not apply to homes.
1 year after recording
Start foreclosure within 1 year after filing the lien statement.
No notice needed
None. The residential warning statement applies only to subcontractor and supplier liens.
Check first
You cannot extend the filing deadline on residential property. An owner-occupied remodel counts as residential.
Source: K.S.A. 60-1101, 60-1102, 60-1103a, 60-1105 (Official Kansas Revisor of Statutes pages; 60-1102 last amended L. 2005 ch. 101)
“within four months after the date”
Three last days of work, worked
| Last work | Record by | Sue by |
|---|---|---|
| Mar 13, 2026 | Jul 13, 2026 | Jul 13, 2027 |
| Jul 31, 2026 | Nov 30, 2026 | Nov 30, 2027 |
| Nov 20, 2026 | Mar 20, 2027 | Mar 20, 2028 |
Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.
Kansas lien questions
How long do I have to file a mechanics lien in Kansas?
File a sworn lien statement with the district court clerk within 4 months after your last labor or materials. The 1-month extension does not apply to homes.
How long does a mechanics lien last in Kansas?
Start foreclosure within 1 year after filing the lien statement.
Does a contractor need to send a notice before filing a lien in Kansas?
None. The residential warning statement applies only to subcontractor and supplier liens.
Compare other states
How we checked
We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .
This guide explains the general rule. It is not legal advice.