Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.
The rule in New Mexico
120 days after completion
File within 120 days after you complete your contract. Send the homeowner a copy within 15 days after filing.
2 years after recording
The lien lasts 2 years after filing unless you start a lawsuit or binding arbitration to enforce it in that time.
No notice needed
None. Preliminary notice rules do not apply to homes of four or fewer units.
Check first
Preliminary notice rules do not apply to homes of four or fewer units. No other special rule was found for you.
Source: NMSA 48-2-2.1, 48-2-6, 48-2-10 (Justia mirror of 2024 New Mexico Statutes; 2023 HB 179 final text on nmlegis.gov)
“within one hundred twenty days after the completion of a contract”
Three last days of work, worked
| Last work | Record by | Sue by |
|---|---|---|
| Mar 13, 2026 | Jul 11, 2026 | Jul 11, 2028 |
| Jul 31, 2026 | Nov 28, 2026 | Nov 28, 2028 |
| Nov 20, 2026 | Mar 20, 2027 | Mar 20, 2029 |
Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.
New Mexico lien questions
How long do I have to file a mechanics lien in New Mexico?
File within 120 days after you complete your contract. Send the homeowner a copy within 15 days after filing.
How long does a mechanics lien last in New Mexico?
The lien lasts 2 years after filing unless you start a lawsuit or binding arbitration to enforce it in that time.
Does a contractor need to send a notice before filing a lien in New Mexico?
None. Preliminary notice rules do not apply to homes of four or fewer units.
Compare other states
How we checked
We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .
This guide explains the general rule. It is not legal advice.