Kentucky Mechanics Lien Deadline (2026): 6 Months after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Kentucky, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 6 months after last work. For a last day of work on Friday, November 20, 2026, record it by Thu, May 20, 2027 and sue by Sat, May 20, 2028. None. No early notice applies when the homeowner hired you directly.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Kentucky

Record the lien

6 months after last work

File with the county clerk within 6 months after your last labor or materials. Mail the homeowner a copy within 7 days of filing or the lien dissolves.

Sue to enforce it

12 months after recording

Sue to enforce within 12 months after filing.

Notice to the homeowner

No notice needed

None. No early notice applies when the homeowner hired you directly.

Homeowner rules

Check first

On owner-occupied one- or two-family homes, only claimants not hired by the homeowner must give a 75-day notice. You have no extra duty.

Source: KRS 376.010, 376.080, 376.090 (Justia mirror of 2025 KRS 376.080 and 376.010; official KRS site for 376.090 (eff. 1942))

“within six (6) months after he ceases to labor or furnish materials”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Sep 13, 2026Sep 13, 2027
Jul 31, 2026Jan 31, 2027Jan 31, 2028
Nov 20, 2026May 20, 2027May 20, 2028

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Kentucky lien questions

How long do I have to file a mechanics lien in Kentucky?

File with the county clerk within 6 months after your last labor or materials. Mail the homeowner a copy within 7 days of filing or the lien dissolves.

How long does a mechanics lien last in Kentucky?

Sue to enforce within 12 months after filing.

Does a contractor need to send a notice before filing a lien in Kentucky?

None. No early notice applies when the homeowner hired you directly.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.