Mechanics liens · Louisiana

Louisiana Mechanics Lien Deadline (2026): 60 Days after Completion for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Louisiana, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 60 days after completion. For a last day of work on Friday, November 20, 2026, record it by Tue, Jan 19, 2027 and sue by Wed, Jan 19, 2028. None for most remodels. Over $100,000, file a notice of contract signed by you and the homeowner in the mortgage records before work starts, or you have no lien.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Louisiana

Record the lien

60 days after completion

File your lien statement within 60 days after substantial completion or abandonment. A recorded notice of termination restarts the clock. A filed notice of contract changes the periods.

Sue to enforce it

1 year after recording

Sue the homeowner within 1 year after filing the lien statement, or the lien is extinguished.

Notice to the homeowner

Only over $100,000

None for most remodels. Over $100,000, file a notice of contract signed by you and the homeowner in the mortgage records before work starts, or you have no lien.

Homeowner rules

Check first

No special rule for your deadline. The 70-day residential extension covers subcontractors and suppliers, not you.

Source: La. R.S. 9:4801, 9:4811, 9:4822, 9:4823 (Louisiana State Legislature official site, R.S. 9:4822, 9:4811, 9:4823 (last amended Acts 2019, No. 325); LSLBC license types page)

“no later than sixty days after”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026May 12, 2026May 12, 2027
Jul 31, 2026Sep 29, 2026Sep 29, 2027
Nov 20, 2026Jan 19, 2027Jan 19, 2028

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Louisiana lien questions

How long do I have to file a mechanics lien in Louisiana?

File your lien statement within 60 days after substantial completion or abandonment. A recorded notice of termination restarts the clock. A filed notice of contract changes the periods.

How long does a mechanics lien last in Louisiana?

Sue the homeowner within 1 year after filing the lien statement, or the lien is extinguished.

Does a contractor need to send a notice before filing a lien in Louisiana?

None for most remodels. Over $100,000, file a notice of contract signed by you and the homeowner in the mortgage records before work starts, or you have no lien.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.