Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.
The rule in Oklahoma
4 months after last work
File a sworn lien statement with the county clerk within 4 months after you last supply labor or materials.
1 year after recording
Start foreclosure within 1 year after filing the lien.
Pre-lien notice, to be safe
The pre-lien notice law excludes original contractors, but the wording is unclear. To be safe, send the homeowner the notice within 75 days of your last work.
Check first
Subcontractors and suppliers on owner-occupied homes must give a prelien notice at any amount. A homestead is not exempt from a valid lien.
Source: 42 O.S. 142, 142.6, 143.1, 172 (Justia 2025 Oklahoma Statutes, Title 42 (142, 172); Oklahoma Bar Journal June 2024 for leads)
“shall be filed within four (4) months after the date”
Three last days of work, worked
| Last work | Record by | Sue by |
|---|---|---|
| Mar 13, 2026 | Jul 13, 2026 | Jul 13, 2027 |
| Jul 31, 2026 | Nov 30, 2026 | Nov 30, 2027 |
| Nov 20, 2026 | Mar 20, 2027 | Mar 20, 2028 |
Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.
Oklahoma lien questions
How long do I have to file a mechanics lien in Oklahoma?
File a sworn lien statement with the county clerk within 4 months after you last supply labor or materials.
How long does a mechanics lien last in Oklahoma?
Start foreclosure within 1 year after filing the lien.
Does a contractor need to send a notice before filing a lien in Oklahoma?
The pre-lien notice law excludes original contractors, but the wording is unclear. To be safe, send the homeowner the notice within 75 days of your last work.
Compare other states
How we checked
We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .
This guide explains the general rule. It is not legal advice.