New York Mechanics Lien Deadline (2026): 4 Months after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in New York, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 4 months after last work. For a last day of work on Friday, November 20, 2026, record it by Sat, Mar 20, 2027 and sue by Mon, Mar 20, 2028. None before filing. Your written home improvement contract must include the state's mechanics lien notice.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in New York

Record the lien

4 months after last work

On a single-family home, file within 4 months after completing the contract or last work. Other property: 8 months. Serve the homeowner 5 days before to 30 after filing.

Sue to enforce it

1 year after recording

The lien lasts 1 year from filing unless you start foreclosure and file notice of the lawsuit. Single-family liens extend only by court order.

Notice to the homeowner

Notice in the contract

None before filing. Your written home improvement contract must include the state's mechanics lien notice.

Homeowner rules

Check first

Single-family homes get a 4-month filing window instead of 8. The lien can extend past 1 year only by court order.

Source: N.Y. Lien Law 10, 11, 17 (NY Senate official Lien Law pages, sections 10, 11, 17; most recent revision shown 2014-09-22)

“within four months after the completion of the contract”

New York statute N.Y. Lien Law 10, 11, 17 (NY Senate official Lien Law pages, sections 10, 11, 17; most recent revision shown 2014-09-22)

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jul 13, 2026Jul 13, 2027
Jul 31, 2026Nov 30, 2026Nov 30, 2027
Nov 20, 2026Mar 20, 2027Mar 20, 2028

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

New York lien questions

How long do I have to file a mechanics lien in New York?

On a single-family home, file within 4 months after completing the contract or last work. Other property: 8 months. Serve the homeowner 5 days before to 30 after filing.

How long does a mechanics lien last in New York?

The lien lasts 1 year from filing unless you start foreclosure and file notice of the lawsuit. Single-family liens extend only by court order.

Does a contractor need to send a notice before filing a lien in New York?

None before filing. Your written home improvement contract must include the state's mechanics lien notice.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.