What a contractor hired directly by a homeowner must give the owner in Colorado to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: No notice is due at signing or at the start. Every claimant, the prime included, must serve a notice of intent to file a lien statement at least 10 days before filing the lien. On a $32,000 kitchen signed March 2 with work starting March 16: Nothing was due by March 16; the only notice comes 10 days before a lien is filed.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in Colorado

Rule

No notice

No notice is due at signing or at the start. Every claimant, the prime included, must serve a notice of intent to file a lien statement at least 10 days before filing the lien.

Notice to the homeowner due

None for the prime

Notice of intent: personal service or registered or certified mail, return receipt requested, on the owner and the prime contractor.

Source

C.R.S. 38-22-109(3), 38-22-105.5

public.law mirror, shown as current through Fall 2025 and sourced from the 2024 official Title 38 PDF. 38-22-109 and 38-22-105.5 both read.

“at least ten days before the time of filing the lien statement”

A $32,000 kitchen in Colorado

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

No

Nothing was due by March 16; the only notice comes 10 days before a lien is filed.

The details

Deadline

At least 10 days before filing the lien statement; the lien statement itself is due within four months after the last labor or material (two months for labor-only claimants).

If you miss it

Nothing is lost for lack of an early notice. The 10-day notice of intent is tied to filing (38-22-109(3)).

Subs and suppliers

Subs and suppliers follow the same 10-day notice of intent; no separate preliminary notice.

Colorado lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in Colorado?

No notice is due at signing or at the start. Every claimant, the prime included, must serve a notice of intent to file a lien statement at least 10 days before filing the lien.

What happens if a contractor misses the notice in Colorado?

Nothing is lost for lack of an early notice. The 10-day notice of intent is tied to filing (38-22-109(3)).

Do subs and suppliers have to give notice in Colorado?

Subs and suppliers follow the same 10-day notice of intent; no separate preliminary notice.

Compare other states

More Colorado rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.