Illinois Lien Notice to the Homeowner (2026): Due Before the First Payment, Lien Kept if Missed
What a contractor hired directly by a homeowner must give the owner in Illinois to keep lien rights, when it is due, and a $32,000 kitchen answered.
Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.
The rule in Illinois
Disclosure
On an owner-occupied single-family residence, give the owner the statutory 'THE LAW REQUIRES' statement in the contract or as a separate printed statement before the owner's first payment, and give a sworn statement of subs and suppliers before any payment.
Before first payment
Part of the contract or a separate printed statement.
770 ILCS 60/5(a), (b)(i)
ilga.gov (official); source line reads P.A. 103-827, eff. 1-1-25.
“either as part of the contract or as a separate printed statement”
A $32,000 kitchen in Illinois
A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?
No
No lien condition was due by March 16; the statement is due in the March 2 contract or before the first payment, whenever that is.
The details
Deadline
Statement: in the contract or before the owner makes the first payment. Sworn statement: before the owner pays or advances any money.
Required form
At least 10 point boldface type; statutory wording beginning 'THE LAW REQUIRES THAT THE CONTRACTOR SHALL SUBMIT A SWORN STATEMENT'.
If you miss it
Section 5 as amended states no consequence for the contractor's lien.
Subs and suppliers
A sub on an existing owner-occupied single-family residence has its own 60-day notice to the occupant under section 21(c) (seen in the Public Act text snippet, not read in full).
Recent change
Public Act 103-827 (HB 4660), effective January 1, 2025: rewrote section 5; subsections (b)(ii) and (b)(iii) are now blank and the subcontractor notice for owner-occupied residences sits in section 21(c).
Illinois lien notice questions
Does a contractor have to send a preliminary notice to the homeowner in Illinois?
On an owner-occupied single-family residence, give the owner the statutory 'THE LAW REQUIRES' statement in the contract or as a separate printed statement before the owner's first payment, and give a sworn statement of subs and suppliers before any payment.
What happens if a contractor misses the notice in Illinois?
Section 5 as amended states no consequence for the contractor's lien.
Do subs and suppliers have to give notice in Illinois?
A sub on an existing owner-occupied single-family residence has its own 60-day notice to the occupant under section 21(c) (seen in the Public Act text snippet, not read in full).
Compare other states
More Illinois rules for contractors
How we checked
We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .
This guide explains the general rule. It is not legal advice.