Lien notice · Minnesota

Minnesota Lien Notice to the Homeowner (2026): Goes in the Contract

What a contractor hired directly by a homeowner must give the owner in Minnesota to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: If the remodeler will use any subcontractor or material supplier, the statutory lien notice must be in the written contract and the owner must get a copy. With no written contract, deliver it separately within 10 days after the work is agreed on. On a $32,000 kitchen signed March 2 with work starting March 16: The notice had to be in the contract signed March 2, since a kitchen job uses subs or material suppliers.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in Minnesota

Rule

Lien at stake

If the remodeler will use any subcontractor or material supplier, the statutory lien notice must be in the written contract and the owner must get a copy. With no written contract, deliver it separately within 10 days after the work is agreed on.

Notice to the homeowner due

In the contract

In the written contract, with a copy to the owner; if separate, personal delivery or certified mail to the owner or the owner's authorized agent.

Source

Minn. Stat. 514.011, subd. 1, 4a, 4b, 4c, 5

revisor.mn.gov (official), Minnesota Statutes 2026; history ends 1989 c 160.

“A person who fails to provide the notice shall not have the lien”

A $32,000 kitchen in Minnesota

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

Yes

The notice had to be in the contract signed March 2, since a kitchen job uses subs or material suppliers.

The details

Deadline

Written contract: at signing. No written contract: within 10 days after the work of improvement is agreed upon.

Required form

Statutory wording in at least 10-point bold type if printed, or capital letters if typewritten.

If you miss it

Whole lien lost: 'A person who fails to provide the notice shall not have the lien and remedy provided by this chapter' (514.011, subd. 1).

Subs and suppliers

Subs and suppliers give the owner their own notice within 45 days after first furnishing, by personal delivery or certified mail (subd. 2).

Minnesota lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in Minnesota?

If the remodeler will use any subcontractor or material supplier, the statutory lien notice must be in the written contract and the owner must get a copy. With no written contract, deliver it separately within 10 days after the work is agreed on.

What happens if a contractor misses the notice in Minnesota?

Whole lien lost: 'A person who fails to provide the notice shall not have the lien and remedy provided by this chapter' (514.011, subd. 1).

Do subs and suppliers have to give notice in Minnesota?

Subs and suppliers give the owner their own notice within 45 days after first furnishing, by personal delivery or certified mail (subd. 2).

Compare other states

More Minnesota rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.

Related