Lien notice · Mississippi

Mississippi Lien Notice to the Homeowner (2026): None Required From the Prime Contractor

What a contractor hired directly by a homeowner must give the owner in Mississippi to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: A contractor in privity with the owner gives no pre-lien notice. On single-family residential work the 10-day pre-lien notice is for subs, suppliers and design professionals not in privity with the owner. On a $32,000 kitchen signed March 2 with work starting March 16: Nothing was due by March 16. The pre-lien notice applies to those not in privity with the owner.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in Mississippi

Rule

No notice

A contractor in privity with the owner gives no pre-lien notice. On single-family residential work the 10-day pre-lien notice is for subs, suppliers and design professionals not in privity with the owner.

Notice to the homeowner due

None for the prime

Source

Miss. Code 85-7-409

Justia, 2025 Mississippi Code; history shows only Laws 2014, ch. 487. Same text on FindLaw, current as of January 1, 2025. The official code is hosted by a vendor and was not fetched.

“the claimant must provide the owner a pre-lien written notice”

A $32,000 kitchen in Mississippi

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

No

Nothing was due by March 16. The pre-lien notice applies to those not in privity with the owner.

The details

Deadline

None for the prime.

If you miss it

Nothing is lost by the prime under 85-7-409. For those not in privity, the pre-lien notice at least 10 days before filing is a condition precedent to the lien.

Subs and suppliers

Subs and suppliers must give the owner written pre-lien notice at least 10 days before filing a claim of lien, and the owner's payment to the contractor before that notice is an absolute defense.

Mississippi lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in Mississippi?

A contractor in privity with the owner gives no pre-lien notice. On single-family residential work the 10-day pre-lien notice is for subs, suppliers and design professionals not in privity with the owner.

What happens if a contractor misses the notice in Mississippi?

Nothing is lost by the prime under 85-7-409. For those not in privity, the pre-lien notice at least 10 days before filing is a condition precedent to the lien.

Do subs and suppliers have to give notice in Mississippi?

Subs and suppliers must give the owner written pre-lien notice at least 10 days before filing a claim of lien, and the owner's payment to the contractor before that notice is an absolute defense.

Compare other states

More Mississippi rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.