Tennessee Lien Notice to the Homeowner (2026): Due Before Work Starts, Lien Kept if Missed
What a contractor hired directly by a homeowner must give the owner in Tennessee to keep lien rights, when it is due, and a $32,000 kitchen answered.
Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.
The rule in Tennessee
Disclosure
Before starting work or making the contract on residential real property, deliver the statutory notice to the owner. Missing it is a Class B misdemeanor if a lien is later filed, but the statute says it does not affect the contractor's lien.
Before work starts
Registered mail or otherwise, to the owner or owners.
T.C.A. 66-11-203, 66-11-206(a) and (c), 66-11-146
Counsel Stack mirror for 66-11-203 (shows amendment by 2020 Tenn. Acts, ch. 749, eff. 7/1/2020) and Justia's 2021 edition for 66-11-206. Tennessee's official code is hosted by a vendor that does not load in this tool.
“shall in no way affect the lien rights of a contractor”
A $32,000 kitchen in Tennessee
A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?
No
The notice was due before work began on March 16 (or at contracting on March 2), but the lien does not depend on it.
The details
Deadline
Prior to commencing the improvement or making of the contract.
Required form
Substantially the statutory form in 66-11-203, signed by the contractor.
If you miss it
Lien preserved: noncompliance "shall in no way affect the lien rights" of the contractor (T.C.A. 66-11-206(c)). Criminal exposure under 66-11-206(a).
Subs and suppliers
On residential real property (an owner-occupied home) only the prime contractor has a lien under 66-11-146, so subs and suppliers have no lien and no notice step on such a job.
Tennessee lien notice questions
Does a contractor have to send a preliminary notice to the homeowner in Tennessee?
Before starting work or making the contract on residential real property, deliver the statutory notice to the owner. Missing it is a Class B misdemeanor if a lien is later filed, but the statute says it does not affect the contractor's lien.
What happens if a contractor misses the notice in Tennessee?
Lien preserved: noncompliance "shall in no way affect the lien rights" of the contractor (T.C.A. 66-11-206(c)). Criminal exposure under 66-11-206(a).
Do subs and suppliers have to give notice in Tennessee?
On residential real property (an owner-occupied home) only the prime contractor has a lien under 66-11-146, so subs and suppliers have no lien and no notice step on such a job.
Compare other states
More Tennessee rules for contractors
How we checked
We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .
This guide explains the general rule. It is not legal advice.