Mechanics liens · California

California Mechanics Lien Deadline (2026): 90 Days after Completion for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in California, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 90 days after completion. For a last day of work on Friday, November 20, 2026, record it by Thu, Feb 18, 2027 and sue by Wed, May 19, 2027. None to the homeowner. If there is a construction lender, notify it within 20 days of starting. Your contract must include the Mechanics Lien Warning.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in California

Record the lien

90 days after completion

Record within 90 days after the project is complete, or 60 days after a recorded completion notice. Serve the homeowner a copy with the required Notice of Mechanics Lien.

Sue to enforce it

90 days after recording

Sue to foreclose within 90 days after recording, or the lien expires.

Notice to the homeowner

Warning in the contract

None to the homeowner. If there is a construction lender, notify it within 20 days of starting. Your contract must include the Mechanics Lien Warning.

Homeowner rules

Check first

Home improvement contracts must be in writing and include the Mechanics Lien Warning. There is no separate lien deadline for owner-occupied homes. Where the work needs a state license, an unlicensed contractor can't sue to collect or enforce a lien.

Source: Cal. Civ. Code 8200, 8412, 8460; Bus. & Prof. Code 7031, 7159 (public.law mirror of Cal. Civil Code (8200, 8412, 8460), verified Oct 2026)

“Ninety days after completion of the work of improvement.”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jun 11, 2026Sep 9, 2026
Jul 31, 2026Oct 29, 2026Jan 27, 2027
Nov 20, 2026Feb 18, 2027May 19, 2027

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Also check

California lien questions

How long do I have to file a mechanics lien in California?

Record within 90 days after the project is complete, or 60 days after a recorded completion notice. Serve the homeowner a copy with the required Notice of Mechanics Lien.

How long does a mechanics lien last in California?

Sue to foreclose within 90 days after recording, or the lien expires.

Does a contractor need to send a notice before filing a lien in California?

None to the homeowner. If there is a construction lender, notify it within 20 days of starting. Your contract must include the Mechanics Lien Warning.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.