Mechanics liens · Texas

Texas Mechanics Lien Deadline (2026): 15th Day of the 3rd Month for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Texas, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien by the 15th day of the 3rd month after the month you finish. For a last day of work on Friday, November 20, 2026, that's Tuesday, February 16, 2027, because February 15 is Presidents' Day. Sue by February 16, 2028. Give the homeowner the state disclosure statement before the contract. On a homestead, sign the written contract before work and file it with the county clerk.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Texas

Record the lien

15th day of the 3rd month

File by the 15th day of the 3rd month after the month the contract is completed, terminated, or abandoned. Nonresidential gets the 4th month. Copy the homeowner within 5 days.

Sue to enforce it

1 year after the deadline

Sue within 1 year after the last day you could file the lien. A recorded written agreement with the homeowner can extend this to 2 years after filing.

Notice to the homeowner

Disclosure and written contract

Give the homeowner the state disclosure statement before the contract. Missing it does not void the lien. On a homestead, sign the written contract before work and file it with the county clerk.

Homeowner rules

Check first

Homestead: before work, the homeowner and both spouses sign a written contract filed with the county clerk. Your lien affidavit needs the required not-a-lien heading. Remodels need a 3-day cancellation right and signing location terms.

Source: Tex. Prop. Code 53.003, 53.052, 53.055, 53.158, 53.254, 53.255; Tex. Const. art. XVI 50(a)(5) (texas.public.law mirror (verified May 2025) of Ch. 53 as amended by HB 2237 eff. 2022-01-01; SB 929 enrolled text and HB 2237 Senate analysis on capitol.texas.gov)

“for residential construction projects, not later than the 15th day of the third month”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jun 15, 2026Jun 15, 2027
Jul 31, 2026Oct 15, 2026Oct 15, 2027
Nov 20, 2026Feb 15, 2027Feb 15, 2028

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Also check

Texas lien questions

How long do I have to file a mechanics lien in Texas?

File by the 15th day of the 3rd month after the month the contract is completed, terminated, or abandoned. Nonresidential gets the 4th month. Copy the homeowner within 5 days.

How long does a mechanics lien last in Texas?

Sue within 1 year after the last day you could file the lien. A recorded written agreement with the homeowner can extend this to 2 years after filing.

Does a contractor need to send a notice before filing a lien in Texas?

Give the homeowner the state disclosure statement before the contract. Missing it does not void the lien. On a homestead, sign the written contract before work and file it with the county clerk.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .