Mechanics liens · Connecticut

Connecticut Mechanics Lien Deadline (2026): 90 Days after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Connecticut, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 90 days after last work. For a last day of work on Friday, November 20, 2026, record it by Thu, Feb 18, 2027 and sue by Fri, Feb 18, 2028. None. Your contract must still follow the state Home Improvement Act.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Connecticut

Record the lien

90 days after last work

Record the lien with the town clerk within 90 days after you stop work. Then serve the homeowner a copy within 30 days of recording.

Sue to enforce it

1 year after recording

Start foreclosure and record notice of the lawsuit within 1 year of recording, or within 60 days after a court rules on a challenge to the lien, whichever is later.

Notice to the homeowner

Compliant contract required

None. Your contract must still follow the state Home Improvement Act.

Homeowner rules

Check first

Home improvement work needs state registration and a signed written contract that meets the Home Improvement Act. If your contract falls short, courts have refused to foreclose your lien unless the homeowner acted in bad faith.

Source: Conn. Gen. Stat. 49-33, 49-34, 49-39 (Justia mirror of 2025 Connecticut General Statutes, ch. 847; CGA OLR report 2006-R-0063)

“within ninety days after he has ceased to do so”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jun 11, 2026Jun 11, 2027
Jul 31, 2026Oct 29, 2026Oct 29, 2027
Nov 20, 2026Feb 18, 2027Feb 18, 2028

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Connecticut lien questions

How long do I have to file a mechanics lien in Connecticut?

Record the lien with the town clerk within 90 days after you stop work. Then serve the homeowner a copy within 30 days of recording.

How long does a mechanics lien last in Connecticut?

Start foreclosure and record notice of the lawsuit within 1 year of recording, or within 60 days after a court rules on a challenge to the lien, whichever is later.

Does a contractor need to send a notice before filing a lien in Connecticut?

None. Your contract must still follow the state Home Improvement Act.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.