Mechanics liens · Rhode Island

Rhode Island Mechanics Lien Deadline (2026): 200 Days after Last Work for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in Rhode Island, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 200 days after last work. For a last day of work on Friday, November 20, 2026, record it by Tue, Jun 8, 2027 and sue by Sun, Jul 18, 2027. Rhode Island law has a notice of possible mechanics lien given before work starts. We couldn't read its current text, so confirm it before you sign.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in Rhode Island

Record the lien

200 days after last work

Within 200 days after your work or materials, mail a notice of intention to the homeowner by certified mail and record it.

Sue to enforce it

40 days after recording

File a lawsuit and record notice of it within 40 days of recording the notice of intention.

Notice to the homeowner

Check before work starts

Rhode Island law has a notice of possible mechanics lien given before work starts. We couldn't read its current text, so confirm it before you sign.

Homeowner rules

No special rule

None

Source: R.I. Gen. Laws 34-28-4, 34-28-4.1, 34-28-10 (Official RI legislature statute pages 34-28-4, 34-28-5, 34-28-10; 2014 S2636aa bill text)

“within two hundred (200) days after the doing of such work”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Sep 29, 2026Nov 8, 2026
Jul 31, 2026Feb 16, 2027Mar 28, 2027
Nov 20, 2026Jun 8, 2027Jul 18, 2027

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

Rhode Island lien questions

How long do I have to file a mechanics lien in Rhode Island?

Within 200 days after your work or materials, mail a notice of intention to the homeowner by certified mail and record it.

How long does a mechanics lien last in Rhode Island?

File a lawsuit and record notice of it within 40 days of recording the notice of intention.

Does a contractor need to send a notice before filing a lien in Rhode Island?

Rhode Island law has a notice of possible mechanics lien given before work starts. We couldn't read its current text, so confirm it before you sign.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.

Related