Mechanics liens · West Virginia

West Virginia Mechanics Lien Deadline (2026): 100 Days after Completion for Remodelers

How long a remodeler hired by the homeowner has to record a mechanics lien in West Virginia, what notice comes first, and the deadline to sue, worked on three dates.

Short answer: Record the lien within 100 days after completion. For a last day of work on Friday, November 20, 2026, record it by Sun, Feb 28, 2027 and sue by Sat, Aug 28, 2027. None. No early notice applies to a general contractor.

Not legal advice. General information from each state's lien statute, checked Oct 29, 2026, for a contractor hired directly by the owner of an existing home. Dates are calendar arithmetic; some states move a deadline that lands on a weekend or holiday and some don't, and a recorded notice of completion or commencement can change the clock. Before you rely on a date, check with a construction attorney in your state.

The rule in West Virginia

Record the lien

100 days after completion

Record notice of lien with the county clerk within 100 days after you complete your work.

Sue to enforce it

6 months after recording

Sue in circuit court within 6 months after recording, or the lien is discharged.

Notice to the homeowner

No notice needed

None. No early notice applies to a general contractor.

Homeowner rules

Check first

The owner of an existing or owner-occupied single-family home can defend by showing they owe you nothing or less than claimed.

Source: W. Va. Code 38-2-7, 38-2-8, 38-2-21, 38-2-34 (Official WV Legislature code site, current text (38-2-8 last amended 2002; 38-2-34 in 2015))

“within one hundred days after the completion of his work”

Three last days of work, worked

Last day to record the lien and to sue, by the last day of work
Last workRecord bySue by
Mar 13, 2026Jun 21, 2026Dec 21, 2026
Jul 31, 2026Nov 8, 2026May 8, 2027
Nov 20, 2026Feb 28, 2027Aug 28, 2027

Suit dates assume you record the lien on its last day; record earlier and a suit deadline that runs from recording comes earlier. Dates are calendar arithmetic and aren't moved off weekends or holidays.

West Virginia lien questions

How long do I have to file a mechanics lien in West Virginia?

Record notice of lien with the county clerk within 100 days after you complete your work.

How long does a mechanics lien last in West Virginia?

Sue in circuit court within 6 months after recording, or the lien is discharged.

Does a contractor need to send a notice before filing a lien in West Virginia?

None. No early notice applies to a general contractor.

Compare other states

How we checked

We read each state's mechanics lien statute on the legislature's site, for a contractor hired directly by the homeowner on an existing home. Two independent research passes covered all 50 states and DC, and a third reviewer checked the result. Where a state's own site would not load, the row names the copy we read. Last checked .

This guide explains the general rule. It is not legal advice.