Delaware Lien Notice to the Homeowner (2026): None Required From the Prime Contractor
What a contractor hired directly by a homeowner must give the owner in Delaware to keep lien rights, when it is due, and a $32,000 kitchen answered.
Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.
The rule in Delaware
No notice
No notice is due at signing or at the start. At or before final payment on an owner's residence, the contractor must give the owner a notarized certification that everyone has been paid or a signed release of liens, and must answer an owner's demand for a list of subs and suppliers within 10 days.
None before work
25 Del. C. 2705, 2707 (2703 for land-only work)
delcode.delaware.gov (official), online code; latest history cite on these sections is 84 Del. Laws, c. 42.
“when the owner has made either full or final payment to the contractor”
A $32,000 kitchen in Delaware
A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?
No
Nothing was due by March 16; the Delaware duties arise on the owner's demand and at final payment.
The details
Deadline
Certification or release: at or before final payment. List of persons who furnished labor or material: within 10 days after the owner's demand.
If you miss it
A contractor who fails for 10 days to furnish the list on the owner's demand gets no further payments and cannot use the lien chapter (25 Del. C. 2705). Failing to give the final-payment certification or release is cause for license suspension or revocation (2707).
Subs and suppliers
Subs and suppliers have no preliminary notice in the sections read; on an owner's residence their lien is cut off by the owner's good-faith full or final payment to the contractor (2707).
Delaware lien notice questions
Does a contractor have to send a preliminary notice to the homeowner in Delaware?
No notice is due at signing or at the start. At or before final payment on an owner's residence, the contractor must give the owner a notarized certification that everyone has been paid or a signed release of liens, and must answer an owner's demand for a list of subs and suppliers within 10 days.
What happens if a contractor misses the notice in Delaware?
A contractor who fails for 10 days to furnish the list on the owner's demand gets no further payments and cannot use the lien chapter (25 Del. C. 2705). Failing to give the final-payment certification or release is cause for license suspension or revocation (2707).
Do subs and suppliers have to give notice in Delaware?
Subs and suppliers have no preliminary notice in the sections read; on an owner's residence their lien is cut off by the owner's good-faith full or final payment to the contractor (2707).
Compare other states
More Delaware rules for contractors
How we checked
We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .
This guide explains the general rule. It is not legal advice.