Lien notice · District of Columbia

District of Columbia Lien Notice to the Homeowner (2026): None Required From the Prime Contractor

What a contractor hired directly by a homeowner must give the owner in District of Columbia to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: No notice is due at signing or at the start. To have a lien, the contractor records a notice of intent in the land records during construction or within 90 days after the project is completed or terminated, and mails the owner a copy within 5 business days. On a $32,000 kitchen signed March 2 with work starting March 16: Nothing was due by March 16. The notice of intent is recorded later, and if the job is under a written home improvement contract a copy must be attached.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in District of Columbia

Rule

No notice

No notice is due at signing or at the start. To have a lien, the contractor records a notice of intent in the land records during construction or within 90 days after the project is completed or terminated, and mails the owner a copy within 5 business days.

Notice to the homeowner due

None before work

Recorded in the land records; copy to the owner by certified mail, posted at the property if returned.

Source

D.C. Code 40-301.01, 40-301.02, 40-301.03

code.dccouncil.gov (official), D.C. Code 40-301.01 to 40-301.03 and 40-303.01 to 40-303.03, current through November 9, 2026.

“during the construction or within 90 days after the earlier of the completion”

A $32,000 kitchen in District of Columbia

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

No

Nothing was due by March 16. The notice of intent is recorded later, and if the job is under a written home improvement contract a copy must be attached.

The details

Deadline

Record during construction or within 90 days after the earlier of completion or termination; certified mail to the owner within 5 business days after recording.

Required form

Sworn and notarized; must include license and good-standing proof and, for a home improvement job, a copy of the home improvement contract.

If you miss it

Lien terminates if the notice of intent is not recorded within the 90 days; a notice that omits the required contents is void (40-301.02). The lien section measures the lien by reasonable value where there is no express contract (40-301.01), so the lien chapter itself does not demand a written contract. Whether a lien holds up on an oral home improvement job is not settled in what was read; DC separately expects licensed home improvement contractors to use a written contract.

Subs and suppliers

A subcontractor records the same kind of notice and must also serve a copy on the owner. Until the owner is served, the owner's payments to the contractor reduce what the subcontractor can charge against the property (40-303.03).

District of Columbia lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in District of Columbia?

No notice is due at signing or at the start. To have a lien, the contractor records a notice of intent in the land records during construction or within 90 days after the project is completed or terminated, and mails the owner a copy within 5 business days.

What happens if a contractor misses the notice in District of Columbia?

Lien terminates if the notice of intent is not recorded within the 90 days; a notice that omits the required contents is void (40-301.02). The lien section measures the lien by reasonable value where there is no express contract (40-301.01), so the lien chapter itself does not demand a written contract. Whether a lien holds up on an oral home improvement job is not settled in what was read; DC separately expects licensed home improvement contractors to use a written contract.

Do subs and suppliers have to give notice in District of Columbia?

A subcontractor records the same kind of notice and must also serve a copy on the owner. Until the owner is served, the owner's payments to the contractor reduce what the subcontractor can charge against the property (40-303.03).

Compare other states

More District of Columbia rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.