Georgia Lien Notice to the Homeowner (2026): None Required From the Prime Contractor
What a contractor hired directly by a homeowner must give the owner in Georgia to keep lien rights, when it is due, and a $32,000 kitchen answered.
Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.
The rule in Georgia
No notice
The prime gives the owner no notice to keep its own lien. A Notice of Commencement is to be filed with the superior court clerk within 15 days after the contractor physically starts work, by the owner, the owner's agent or the contractor, and posted on site.
None for the prime
Filed with the clerk of superior court in the county of the project; copy posted on the site; copy to any sub or supplier within 10 days of a written request.
O.C.G.A. 44-14-361.5, 44-14-361.1
44-14-361.5 read on Justia, 2025 Code of Georgia; history ends at Ga. L. 2014. 44-14-361.1 read on FindLaw, current as of March 28, 2024. The official code is hosted by a vendor and was not fetched.
“who does not have privity of contract with the contractor”
A $32,000 kitchen in Georgia
A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?
No
Nothing was needed by March 16 to keep the lien. The Notice of Commencement window ran to March 31.
The details
Deadline
Notice of Commencement: not later than 15 days after the contractor physically commences work. The prime's own steps come later: claim of lien within 90 days after the work, with a copy to the owner within two business days of filing, and a lien action within 365 days of filing (44-14-361.1).
If you miss it
No loss of the prime's own lien is stated. If no Notice of Commencement is filed, the section's Notice to Contractor requirement does not apply (44-14-361.5(d)), so remote claimants keep lien rights without notifying the contractor.
Subs and suppliers
Anyone without a contract with the prime (second-tier subs, suppliers to subs) must give a Notice to Contractor when a Notice of Commencement has been filed.
Georgia lien notice questions
Does a contractor have to send a preliminary notice to the homeowner in Georgia?
The prime gives the owner no notice to keep its own lien. A Notice of Commencement is to be filed with the superior court clerk within 15 days after the contractor physically starts work, by the owner, the owner's agent or the contractor, and posted on site.
What happens if a contractor misses the notice in Georgia?
No loss of the prime's own lien is stated. If no Notice of Commencement is filed, the section's Notice to Contractor requirement does not apply (44-14-361.5(d)), so remote claimants keep lien rights without notifying the contractor.
Do subs and suppliers have to give notice in Georgia?
Anyone without a contract with the prime (second-tier subs, suppliers to subs) must give a Notice to Contractor when a Notice of Commencement has been filed.
Compare other states
More Georgia rules for contractors
How we checked
We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .
This guide explains the general rule. It is not legal advice.