Missouri Lien Notice to the Homeowner (2026): Due Before the First Payment
What a contractor hired directly by a homeowner must give the owner in Missouri to keep lien rights, when it is due, and a $32,000 kitchen answered.
Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.
The rule in Missouri
Lien at stake
Every original contractor must give the statutory NOTICE TO OWNER before receiving any payment: at contract signing, when materials are delivered, when work starts, or with the first invoice.
Before first payment
Written notice to the person the contract is made with (or the owner if there is no contract); no mailing method is specified.
RSMo 429.012
revisor.mo.gov (official); version effective January 1, 2017.
“prior to receiving payment in any form of any kind from such person”
A $32,000 kitchen in Missouri
A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?
It depends
If a deposit was taken at signing, the notice was due March 2; otherwise it was due before the first payment, at the latest with the first invoice.
The details
Deadline
Prior to receiving payment in any form of any kind.
Required form
Ten-point bold type, headed NOTICE TO OWNER, with the statutory text.
If you miss it
Whole lien lost: compliance is a condition precedent to the creation, existence or validity of any mechanic's lien in favor of the original contractor (429.012.2). Failing to give it with intent to defraud is a class B misdemeanor.
Subs and suppliers
On owner-occupied residential repair work, anyone other than the original contractor needs the owner's signed consent form under 429.013 to have a lien (seen in a search snippet, not read in full).
Missouri lien notice questions
Does a contractor have to send a preliminary notice to the homeowner in Missouri?
Every original contractor must give the statutory NOTICE TO OWNER before receiving any payment: at contract signing, when materials are delivered, when work starts, or with the first invoice.
What happens if a contractor misses the notice in Missouri?
Whole lien lost: compliance is a condition precedent to the creation, existence or validity of any mechanic's lien in favor of the original contractor (429.012.2). Failing to give it with intent to defraud is a class B misdemeanor.
Do subs and suppliers have to give notice in Missouri?
On owner-occupied residential repair work, anyone other than the original contractor needs the owner's signed consent form under 429.013 to have a lien (seen in a search snippet, not read in full).
Compare other states
More Missouri rules for contractors
How we checked
We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .
This guide explains the general rule. It is not legal advice.