Iowa Lien Notice to the Homeowner (2026): Due Within 10 Days of Starting
What a contractor hired directly by a homeowner must give the owner in Iowa to keep lien rights, when it is due, and a $32,000 kitchen answered.
Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.
The rule in Iowa
Lien at stake
If the remodeler has or will have any subcontractor on the job, it must post a notice of commencement of work on the state Mechanics' Notice and Lien Registry within 10 days after starting, and give the owner the statutory owner notice. The posting only covers work done after it is posted, so post before starting.
Within 10 days of starting
Posting to the Mechanics' Notice and Lien Registry (the administrator then mails the owner notice); owner notice in writing.
Iowa Code 572.13, 572.13A
legis.iowa.gov (official): 572.13A read in the Iowa Code 2026 PDF; 572.13 read in the Iowa Code 2021 PDF (2025 and current files would not load; its history shows no amendment after 2013).
“no later than ten days after the commencement of work on the property”
A $32,000 kitchen in Iowa
A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?
It depends
If any sub is used, post before work starts on March 16 to cover everything; the outside date is March 26 and it does not reach work done before posting.
The details
Deadline
Registry posting: no later than 10 days after commencement of work, effective only for labor and material furnished after posting. Owner notice under 572.13: no deadline stated.
Required form
Owner notice in boldface type of at least 10 points, with the registry's internet address and toll-free number.
If you miss it
A general contractor who fails to provide notice under either section is not entitled to a lien (572.13(3), 572.13A(4)); posting within the 10 days still leaves pre-posting work uncovered (572.13A(1)).
Subs and suppliers
Subs post their own preliminary notice to the registry (572.13B) and may post the notice of commencement if the general contractor has not.
Iowa lien notice questions
Does a contractor have to send a preliminary notice to the homeowner in Iowa?
If the remodeler has or will have any subcontractor on the job, it must post a notice of commencement of work on the state Mechanics' Notice and Lien Registry within 10 days after starting, and give the owner the statutory owner notice. The posting only covers work done after it is posted, so post before starting.
What happens if a contractor misses the notice in Iowa?
A general contractor who fails to provide notice under either section is not entitled to a lien (572.13(3), 572.13A(4)); posting within the 10 days still leaves pre-posting work uncovered (572.13A(1)).
Do subs and suppliers have to give notice in Iowa?
Subs post their own preliminary notice to the registry (572.13B) and may post the notice of commencement if the general contractor has not.
Compare other states
More Iowa rules for contractors
How we checked
We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .
This guide explains the general rule. It is not legal advice.