Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.
The rule in Montana
No notice
A contractor hired directly by the owner does not have to give Montana's notice of the right to claim a lien. The only steps are the later lien filing steps.
None for the prime
MCA 71-3-531(1)(a), 71-3-531(2)
mca.legmt.gov (official), Montana Code Annotated 2025; history ends 2009, ch. 182.
“directly to the owner at the owner's request”
A $32,000 kitchen in Montana
A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?
No
No notice was due by March 16; the prime's first deadline is the lien filing after the work ends.
The details
Deadline
No start-of-job deadline for the prime.
If you miss it
Nothing is lost at the start of the job. MCA 71-3-531(1)(a) takes the original contractor out of the notice duty in 71-3-531(2).
Subs and suppliers
Subs and suppliers on a home with fewer than five units must give the owner a notice of the right to claim a lien, generally within 20 days of first furnishing, by certified mail or personal delivery, and file a copy with the clerk and recorder.
Montana lien notice questions
Does a contractor have to send a preliminary notice to the homeowner in Montana?
A contractor hired directly by the owner does not have to give Montana's notice of the right to claim a lien. The only steps are the later lien filing steps.
What happens if a contractor misses the notice in Montana?
Nothing is lost at the start of the job. MCA 71-3-531(1)(a) takes the original contractor out of the notice duty in 71-3-531(2).
Do subs and suppliers have to give notice in Montana?
Subs and suppliers on a home with fewer than five units must give the owner a notice of the right to claim a lien, generally within 20 days of first furnishing, by certified mail or personal delivery, and file a copy with the clerk and recorder.
Compare other states
More Montana rules for contractors
How we checked
We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .
This guide explains the general rule. It is not legal advice.