Lien notice · North Dakota

North Dakota Lien Notice to the Homeowner (2026): None Required From the Prime Contractor

What a contractor hired directly by a homeowner must give the owner in North Dakota to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: No notice is due at signing or at the start of work. Section 35-27-02(4) requires written notice that a lien will be claimed, sent to the owner by certified mail at least ten days before recording. That sentence sits in the subsection on those hired by a contractor or sub, so its reach to a contractor hired by the owner is not stated; send it anyway. On a $32,000 kitchen signed March 2 with work starting March 16: Nothing was due by March 16; the certified-mail notice comes ten days before recording.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in North Dakota

Rule

No notice

No notice is due at signing or at the start of work. Section 35-27-02(4) requires written notice that a lien will be claimed, sent to the owner by certified mail at least ten days before recording. That sentence sits in the subsection on those hired by a contractor or sub, so its reach to a contractor hired by the owner is not stated; send it anyway.

Notice to the homeowner due

None before work

Certified mail to the legal or equitable owner.

Source

N.D.C.C. 35-27-02, 35-27-13, 35-27-24

North Dakota Legislative Branch, Century Code chapter 35-27 PDF (current code).

“by certified mail at least ten days before the recording of the construction lien”

A $32,000 kitchen in North Dakota

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

No

Nothing was due by March 16; the certified-mail notice comes ten days before recording.

The details

Deadline

At least 10 days before recording the lien; the lien must be recorded within 90 days after the work is finished.

If you miss it

No penalty is stated. Treat the certified-mail notice as a condition of a valid recorded lien even for the prime, since 35-27-02(4) does not say who is exempt. Nothing is lost at the start of the job.

Subs and suppliers

Subs and suppliers follow the same pre-recording notice; their lien is limited to what the owner has not already paid.

North Dakota lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in North Dakota?

No notice is due at signing or at the start of work. Section 35-27-02(4) requires written notice that a lien will be claimed, sent to the owner by certified mail at least ten days before recording. That sentence sits in the subsection on those hired by a contractor or sub, so its reach to a contractor hired by the owner is not stated; send it anyway.

What happens if a contractor misses the notice in North Dakota?

No penalty is stated. Treat the certified-mail notice as a condition of a valid recorded lien even for the prime, since 35-27-02(4) does not say who is exempt. Nothing is lost at the start of the job.

Do subs and suppliers have to give notice in North Dakota?

Subs and suppliers follow the same pre-recording notice; their lien is limited to what the owner has not already paid.

Compare other states

More North Dakota rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .