Wyoming Lien Notice to the Homeowner (2026): Due Before the First Payment

What a contractor hired directly by a homeowner must give the owner in Wyoming to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: Send the owner the statutory preliminary notice of right to lien before taking any payment, a deposit included. Missing the deadline bars the lien. On a $32,000 kitchen signed March 2 with work starting March 16: The deadline is the first payment, not the start date: if a deposit was taken at signing on March 2, the notice had to go out before that.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in Wyoming

Rule

Lien at stake

Send the owner the statutory preliminary notice of right to lien before taking any payment, a deposit included. Missing the deadline bars the lien.

Notice to the homeowner due

Before first payment

Written notice sent to the record owner or the owner's agent; the statute names no delivery method, so keep proof of sending.

Source

W.S. 29-2-112(a)(i)-(iv), 29-10-101

Counsel Stack mirror labeled 2026 (the legislature's Title 29 PDF would not load in this tool); cross-checked against the section text printed in the legislature's 2025 HB0253.

“By the contractor prior to receiving any payment from owner, including advances;”

A $32,000 kitchen in Wyoming

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

It depends

The deadline is the first payment, not the start date: if a deposit was taken at signing on March 2, the notice had to go out before that.

The details

Deadline

Prior to receiving any payment from the owner, including advances.

Required form

Substantially the same format and information as the form in W.S. 29-10-101; forms are available at county clerk offices.

If you miss it

Whole lien barred (W.S. 29-2-112(a)(iii)).

Subs and suppliers

Subs and suppliers send the same notice to the owner within 30 days after first providing services or materials, with a copy to the contractor.

Recent change

No change. 2025 HB0253 would have moved the sub and supplier deadline; the House did not consider it for introduction (February 3, 2025).

Wyoming lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in Wyoming?

Send the owner the statutory preliminary notice of right to lien before taking any payment, a deposit included. Missing the deadline bars the lien.

What happens if a contractor misses the notice in Wyoming?

Whole lien barred (W.S. 29-2-112(a)(iii)).

Do subs and suppliers have to give notice in Wyoming?

Subs and suppliers send the same notice to the owner within 30 days after first providing services or materials, with a copy to the contractor.

Compare other states

More Wyoming rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.

Related