Lien notice · Ohio

Ohio Lien Notice to the Homeowner (2026): None Required From the Prime Contractor

What a contractor hired directly by a homeowner must give the owner in Ohio to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: On a home construction contract the notice of furnishing section does not apply at all, and an original contractor never has to serve one. The prime gives the owner no start-of-job notice. On a $32,000 kitchen signed March 2 with work starting March 16: No notice was due by March 16.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in Ohio

Rule

No notice

On a home construction contract the notice of furnishing section does not apply at all, and an original contractor never has to serve one. The prime gives the owner no start-of-job notice.

Notice to the homeowner due

None for the prime

Source

R.C. 1311.011(A)(1) and (B), 1311.04(O), 1311.05(A) and (E)

Ohio Revised Code official site: 1311.05 and 1311.011 effective March 30, 2007 (HB 487); 1311.04 authenticated version effective September 30, 2025 (HB 96).

“No original contractor has to serve a notice of furnishing to preserve lien rights”

A $32,000 kitchen in Ohio

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

No

No notice was due by March 16.

The details

Deadline

No start-of-job deadline for the prime.

If you miss it

Nothing lost at the start. R.C. 1311.05(A) and (E); R.C. 1311.04(O) takes home construction contracts out of the notice of commencement section.

Subs and suppliers

On a home construction contract subs and suppliers do not serve a notice of furnishing either, but their lien is cut off to the extent the owner paid the original contractor in full before receiving a copy of their lien affidavit (R.C. 1311.011(B)).

Recent change

R.C. 1311.04 (notice of commencement) was amended by HB 96, effective September 30, 2025. The current text has a four-year expiration for a notice of commencement and an owner's completion affidavit; division (O) still excludes home construction contracts.

Ohio lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in Ohio?

On a home construction contract the notice of furnishing section does not apply at all, and an original contractor never has to serve one. The prime gives the owner no start-of-job notice.

What happens if a contractor misses the notice in Ohio?

Nothing lost at the start. R.C. 1311.05(A) and (E); R.C. 1311.04(O) takes home construction contracts out of the notice of commencement section.

Do subs and suppliers have to give notice in Ohio?

On a home construction contract subs and suppliers do not serve a notice of furnishing either, but their lien is cut off to the extent the owner paid the original contractor in full before receiving a copy of their lien affidavit (R.C. 1311.011(B)).

Compare other states

More Ohio rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.