Lien notice · Oklahoma

Oklahoma Lien Notice to the Homeowner (2026): None Required From the Prime Contractor

What a contractor hired directly by a homeowner must give the owner in Oklahoma to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: The old owner-occupied dwelling notice (42 O.S. 142.1) was repealed in 2011. The current pre-lien notice in 142.6 is for claimants other than the original contractor, so the prime sends no notice. On a $32,000 kitchen signed March 2 with work starting March 16: No notice was due by March 16.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in Oklahoma

Rule

No notice

The old owner-occupied dwelling notice (42 O.S. 142.1) was repealed in 2011. The current pre-lien notice in 142.6 is for claimants other than the original contractor, so the prime sends no notice.

Notice to the homeowner due

None for the prime

Source

42 O.S. 142.6(A), (B)(1), (B)(3), (B)(6); former 142.1, 142.3, 142.5 repealed by Laws 2011, c. 23

Justia mirror, 2025 Oklahoma Statutes; repeal read in enrolled SB 277 (2011), effective November 1, 2011.

“a person, other than an original contractor”

A $32,000 kitchen in Oklahoma

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

No

No notice was due by March 16.

The details

Deadline

No start-of-job deadline for the prime.

If you miss it

Nothing stated for the prime. 142.6(A) defines the claimant who must send a pre-lien notice as a person other than an original contractor.

Subs and suppliers

Subs and suppliers on an owner-occupied dwelling must send a pre-lien notice to the owner and the original contractor no later than 75 days after last furnishing, whatever the amount; without it the lien is not valid.

Recent change

42 O.S. 142.6 was amended by Laws 2025, c. 486, section 505, effective January 1, 2026. The 2025 edition still excludes the original contractor from the pre-lien notice; what the amendment changed was not confirmed. HB 4347 (2026, as introduced) would amend 42 O.S. 143 effective November 1, 2026; its outcome was not confirmed.

Oklahoma lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in Oklahoma?

The old owner-occupied dwelling notice (42 O.S. 142.1) was repealed in 2011. The current pre-lien notice in 142.6 is for claimants other than the original contractor, so the prime sends no notice.

What happens if a contractor misses the notice in Oklahoma?

Nothing stated for the prime. 142.6(A) defines the claimant who must send a pre-lien notice as a person other than an original contractor.

Do subs and suppliers have to give notice in Oklahoma?

Subs and suppliers on an owner-occupied dwelling must send a pre-lien notice to the owner and the original contractor no later than 75 days after last furnishing, whatever the amount; without it the lien is not valid.

Compare other states

More Oklahoma rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.

Related