Lien notice · West Virginia

West Virginia Lien Notice to the Homeowner (2026): None Required From the Prime Contractor

What a contractor hired directly by a homeowner must give the owner in West Virginia to keep lien rights, when it is due, and a $32,000 kitchen answered.

Short answer: No notice is due at signing or at the start of work. The general contractor perfects the lien by recording a notice of lien within 100 days after completing the contract. On a $32,000 kitchen signed March 2 with work starting March 16: Nothing was due by March 16; the 100 days run from completion.

Not legal advice. General information from each state's mechanics lien statute, checked Nov 25, 2026. It covers a contractor hired directly by the owner-occupant of an existing single-family home. Subs and suppliers have different notice duties, and later steps (recording the lien, suing on it) have their own deadlines. Ask a construction lawyer in your state before you rely on a lien.

The rule in West Virginia

Rule

No notice

No notice is due at signing or at the start of work. The general contractor perfects the lien by recording a notice of lien within 100 days after completing the contract.

Notice to the homeowner due

None for the prime

Recorded with the clerk of the county commission where the property is.

Source

W. Va. Code 38-2-1, 38-2-7, 38-2-8, 38-2-14, 38-2-20, 38-2-21(b), 38-2-34(b)

West Virginia Legislature code site, Article 38-2 PDF dated June 12, 2026.

“within one hundred days after the completion of his work”

A $32,000 kitchen in West Virginia

A remodeler signs a $32,000 kitchen contract with the owner-occupant of a single-family home on March 2 and starts work on March 16. Did the remodeler have to give the owner anything by the time work started to keep its own lien rights?

Had to act by the time work started?

No

Nothing was due by March 16; the 100 days run from completion.

The details

Deadline

Within 100 days after completion of the work under the contract.

Required form

Sufficient if in the form set out in W. Va. Code 38-2-8, sworn.

If you miss it

Lien discharged if not recorded in time (38-2-7, 38-2-14). Nothing is lost at the start of the job.

Subs and suppliers

Subs and suppliers serve the owner and record their notice of lien within 100 days; on an existing or owner-occupied single-family dwelling the owner can defend by showing it owes the contractor nothing or less than the lien.

West Virginia lien notice questions

Does a contractor have to send a preliminary notice to the homeowner in West Virginia?

No notice is due at signing or at the start of work. The general contractor perfects the lien by recording a notice of lien within 100 days after completing the contract.

What happens if a contractor misses the notice in West Virginia?

Lien discharged if not recorded in time (38-2-7, 38-2-14). Nothing is lost at the start of the job.

Do subs and suppliers have to give notice in West Virginia?

Subs and suppliers serve the owner and record their notice of lien within 100 days; on an existing or owner-occupied single-family dwelling the owner can defend by showing it owes the contractor nothing or less than the lien.

Compare other states

More West Virginia rules for contractors

How we checked

We read each state's mechanics lien statute and contractor board rules for what a contractor hired directly by a homeowner must give the owner at signing, before work, before payment or shortly after starting. Two independent research passes covered all 50 states and DC. Where a state's own site would not load, the row names the copy we read. A state stays "still being checked" until its current section has been read. Last checked .

This guide explains the general rule. It is not legal advice.

Related